ER27-25-000 · 2026-11-19 · Southern Minnesota Municipal Power Agency, WPPI Energy

Motion for Leave to Answer and Answer of Southern Minnesota Municipal Power Agency et al. to the 11/09/2026 Motion for Leave to Answer filed by the…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc.
Docket No.  ER27-25-000

MOTION FOR LEAVE TO ANSWER AND ANSWER
OF MIDWEST TDUS
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure,1 Midwest TDUs2 respectfully move for leave to answer and answer the November 9, 2026, Motion for Leave to Answer and Answer filed by the Midcontinent Independent System Operator, Inc. (“MISO”).3 MISO’s Answer responds to, among other things, Midwest TDUs’ Limited Protest4 of MISO’s October 2, 2026 filing to revise its Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) to establish a Large Load Addition Resource Study (“LARS”) process.5

Midwest TDUs previously raised two issues with MISO’s LARS proposal: (1) an important flaw in MISO’s proposed scope for LARS eligibility that requires correction, and (2) the need to ensure that all cost-shifting issues associated with LARS are fully addressed in future filing(s). MISO’s Answer resolves neither of these concerns.

1 18 C.F.R. §§ 385.212, 385.213. 2 Midwest TDUs consist of Southern Minnesota Municipal Power Agency (“SMMPA”) and WPPI Energy (“WPPI”).
3 Motion for Leave to Answer and Answer of the Midcontinent Independent System Operator, Inc. (Nov. 9, 2026), eLibrary No. 20261109-5205 (“MISO Answer”).
4 Motion to Intervene and Limited Protest of Southern Minnesota Municipal Power Agency and WPPI Energy (Oct. 23, 2026), eLibrary No. 20261023-5191 (“Midwest TDUs Limited Protest”).
5 MISO, Large Load Addition Resource Study Process (Oct. 2, 2026), eLibrary No. 20261002-5074 (“MISO Filing”).

PDF page 2

- 2 -
First, Midwest TDUs and others previously protested MISO’s proposal to make paired generation and load within the same Local Resource Zone (“LRZ” or “Zone”) eligible for the expedited LARS process. MISO’s Answer fails to address specific problems raised about this scope. Instead, MISO’s Answer repeats vague assertions about identifying optimized sets of Network Upgrades, which fails to demonstrate that the proposed scope for LARS eligibility is just, reasonable, and not unduly discriminatory in light of the problems identified in the Commission’s Show Cause Order.6 Second, MISO’s Answer doubles down on MISO’s contradictory clam that

critical cost shifting issues will be addressed in future filing(s), but that the Commission should nevertheless accept LARS independently from those Tariff reforms essential to making LARS just, reasonable, and not unduly discriminatory or preferential. MISO’s argument rests of the false premise that the Commission must choose between timely implementation of LARS or consideration of cost shifting in the context of LARS. Not so. The Commission should instead condition any acceptations of MISO’s LARS proposal on the Commission finding, in future proceeding(s), that MISO has satisfied its obligations with respect to the Show Cause Order’s discussion of cost allocation and transparency as applied to LARS.

I. MOTION FOR LEAVE TO ANSWER
The Commission’s Rules of Practice and Procedure prohibit answers to answers unless otherwise authorized by the Commission.7 The Commission, however, has

6 Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).
7 18 C.F.R. § 385.213(a)(2).

PDF page 3

- 3 -
authority to waive this prohibition for good cause,8 and it has found good cause to waive the general prohibition on answers to answers where, among other things, the answer would assist the Commission in its decision-making process.9 Midwest TDUs’ Answer to MISO’s Answer will aid the Commission’s understanding of important issues regarding the proposed scope of eligibility for LARS as well as the relationship between MISO’s filing and the critical concerns about cost shifting identified in the Commission’s Show Cause Order.

II. ANSWER
A. MISO’s Answer fails to justify its proposed geographic scope for
paired generation and load eligible for LARS.
As MISO summarizes in its Answer, “[m]any of the protesters,” including
Midwest TDUs, challenged MISO’s proposal to allow paired generation and load located within the same LRZ to be eligible for LARS.10 MISO acknowledges that its proposed scope for LARS differs from the Commission-suggested definition of “electrically proximate” in the Show Cause Order, but defends its filing by arguing that its proposal “provide[s] maximum flexibility for the generation/load pairs.”11

The Commission’s mandate in the Show Cause Order was not to ensure
“maximum flexibility” to a subset of load and generation that desires to interconnect to

8 Id. § 385.101(e).
9 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 191 FERC ¶ 61,131, P 24 (2025) (accepting answers to answers “because they have provided information that assisted us in our decision-making process”).
10 MISO Answer at 9.
11 Id. See also id. at 9-10 (“In developing LARS, MISO concluded that defining a maximum distance based on substations would impede the flexibility of large loads and Interconnection Customers to site their projects in a way that made the most sense for the parties.”), id. at 12 (describing its proposal as “providing maximum flexibility for participants”).

PDF page 4

- 4 -
the transmission system on an expedited basis. Rather, it was to ensure just, reasonable, and not unduly discriminatory Commission-jurisdictional rates for all customers, particularly considering the challenges associated with a significant increase in new large load interconnections. Specifically, the Commission found that “the status quo may result in inefficient and unnecessary development of infrastructure, which leads to unnecessarily higher network upgrade costs that may result in unjust and unreasonable rates,”12 whereas “electrically proximate” large load and generation may “potentially reduc[e] the need for Network Upgrades, which can accelerate the generator interconnection process.”13 Thus, the key to addressing the Show Cause Order’s concern is targeting those paired generation and large loads that are sufficiently “electrically proximate” to reduce the need for Network Upgrades.14

MISO’s Answer fails to show that its proposed zonal approach satisfies the Show Cause Order’s directive. MISO offers generic statements (with no supporting data or examples) about how studying generation and load together might reduce the need for Network Upgrades,15 but none of those statements support MISO’s specific proposal to allow pairs within the same Zone. In fact, MISO concedes that “adjacent large loads and Generating Facilities may produce the most significant Network Upgrade

12 Show Cause Order P 114.
13 Id. P 113.
14 For example, the Show Cause Order explains that electrically proximate load and generation have unique characteristics; “because the generating facility and load are located so closely on the transmission system, if the generating facility’s output matches the load’s demand, then the transmission provider would need to study only the local impacts because the impact on the transmission system of the combination of the generating facility and the load, with the exception of the transmission facilities between the two, will be effectively the same as if they were located at the same substation.” Id. P 113 n.256.
15 See MISO Answer at 10-11.

PDF page 5

- 5 -
optimization.”16 Although MISO claims that more distant pairs may also result in some reduction in Network Upgrades (at least over time in the aggregate), it offers no specific support for a zonal scope.

MISO claims that the Commission’s suggested definition of electrically
proximate (i.e., no more than two substations apart) “would be arbitrary” in the MISO context,17 but it fails to offer any reasoned basis for an alternative zonal approach. MISO does not explain why paired generation and load that cross a zonal boundary (even if electrically proximate) will likely require more costly Network Upgrades compared to a pair anywhere within a Zone (even those not electrically proximate). Nor does MISO explain why paired generation and load hundreds of miles and multiple states apart are more likely to require fewer Network Upgrades just because they are in the same Zone. MISO’s critiques of the Commission’s suggested scope also fail to justify its alternative approach. MISO claims that in some instances “two substations could still be hundreds of miles apart,”18 but that concern fails to justify a zonal approach that still allows pairs of generation and load that are not only hundreds of miles apart but also electrically distant.

MISO also claims that in areas of MISO where several substations are in close proximity, a two-substation-limit could result in “geographically proximate Generating Facility and large load [having] very limited options for interconnection” under LARS.19

16 Id. at 11.
17 Id. at 10. 18 Id.
19 Id.

PDF page 6

- 6 -
MISO does not explain why this is a problem or contrary to MISO’s stated intent to develop a “narrowly scoped”20 LARS process. Under MISO’s own proposal, only certain pairs of generation and large load have access to the expedited LARS process to begin with, and the concern expressed in the Commission’s Show Cause Order was about the timely interconnection of paired generation and load that are uniquely situated to require less significant and costly Network Upgrades. MISO has not demonstrated that it is just, reasonable, and not unduly discriminatory to extend the expedited treatment provided by LARS to pairs that lack these critical characteristics.

In addition, MISO’s Answer fails to address, much less rebut, several key problems with its proposed scope for LARS. Midwest TDUs pointed out that MISO’s proposed scope is not only overinclusive (i.e., covering generation/load pairs that are not electrically proximate), but also underinclusive (i.e., excluding pairs that may be in separate Zones but are nevertheless electrically proximate).21 MISO offers no justification for excluding electrically proximate loads that happen to fall in different Zones. MISO also fails to explain how its proposed zonal scope will produce the optimized results MISO claims, particularly given the numerous elements of LARS that broaden its scope and require additional studies.22

20 Id. at 13.
21 See Midwest TDUs Limited Protest at 5-6.
22 See id. at 6-7 (explaining how MISO’s LARS proposal (1) allows generation at multiple Points of Interconnection for a single LARS Associated Load, with separate Applications for each Point of Interconnection; (2) requires separate, serial studies, even for multiple pairs of generation and load in the same Zone and even for multiple Points of Interconnection for the same load; (3) permits generation to receive NRIS equal to 150% of the LARS Associated Load’s peak demand; and (4) permits retention of NRIS for up to a year without paired LARS associated Load).

PDF page 7

- 7 -
Finally, MISO is wrong to suggest that there is no downside to broadening the scope to LARS eligibility.23 MISO proposes to limit the number of generation/load pairs that may be studied in each LARS Study Period.24 As a result, the inclusion in LARS of pairs of generation and load that do not reduce the need for Network Upgrades (e.g., those not electrically proximate) risks crowding out those pairs that do create greater efficiencies (e.g., those that are sufficiently electrically proximate such that their impact on the transmission system is the same as if they were located at the same substation). An overbroad scope thus undermines the benefits LARS is intended to achieve. Moreover, to be just, reasonable, and not unduly discriminatory, an expedited interconnection process must be “narrowly tailored to the problem being addressed.”25 Here, MISO has failed to show that a zonal scope for LARS eligibility is responsive to the problem identified in the Commission’s Show Cause Order, and MISO has not meet its burden of showing that this scope is just, reasonable, and not unduly discriminatory.

B. MISO fails to show that the Commission can simply ignore cost
shifting concerns in this proceeding.
Midwest TDUs and numerous other participants also identified the shortcoming of MISO’s failure to address the Show Cause Order’s cost shifting concerns in its LARS proposal. MISO’s Answer reiterates MISO’s plan to address the Show Cause Order’s

23 See MISO Answer at 12 (“It should not be objectionable that LARS provides efficiency benefits in more situations than the smaller subset contemplated by the Show Cause Order.”).
24 See id. at 7 (“LARS is limited in scope both by its strict eligibility requirements and because only thirty generation and load pairs may be studied each year.”).
25 Midcontinent Indep. Sys. Operator, Inc., 194 FERC ¶ 61,050, P 55 (2026) (“In evaluating whether proposals by RTOs/ISOs to implement expedited interconnection study processes to address urgent resource adequacy needs are reasonable, the Commission has considered factors including whether those proposals were narrowly tailored to the problem being addressed.”).

PDF page 8

- 8 -
directive regarding a pro forma cost recovery agreement and transparency in future filings, but MISO nevertheless argues that its LARS proposal should be accepted without any Commission consideration of these critical upcoming reforms.26 MISO’s Answer further underscores the need for the Commission to condition any acceptations of MISO’s LARS proposal on the Commission finding, in future proceeding(s), that MISO has satisfied its obligations with respect to the Show Cause Order’s discussion of cost allocation and transparency as applied to LARS.

MISO’s Answer first points to language in its proposed Tariff it states “assigns the costs of [non-GIP local Transmission Facilities] to the LARS Associated

Transmission Customer even if the large load is ultimately not built.”27 But in the very next sentence, MISO concedes that the “enforcement mechanism for the obligations of Transmission Customers seeking Transmission Service to serve Large Loads” will be part of future filings—not the Tariff revisions before the Commission here—and that MISO will “integrate” those future reforms “into the LARS process” once those reforms are accepted.28

As a result, MISO’s statement that “the LARS proposal includes a Tariff
mechanism for identifying and assigning any necessary transmission Network Upgrades

26 MISO Answer at 14. After MISO filed its Answer, it submitted two filings on November 16, 2026, in response to the Commission’s Show Cause Order. In Docket No. ER27-526, MISO filed its “omnibus” response to the Show Cause Order, which includes (among other things) MISO’s response to the Show Cause Order’s discussion of transparency requirements and a pro forma cost recovery agreement. In Docket No. ER27-527, MISO submitted its Grid Responsive Integration Transmission Service (“GRITS”) filing, which addresses permanent firm and non-firm contract demand-based transmission service options for large loads.
27 Id. at 15.
28 Id.

PDF page 9

- 9 -
associated with the generation/load pair to the Transmission Customer or the Interconnection Customer”29 appears to describe, at best, MISO’s future intent. But nothing in the Tariff revisions before the Commission in this proceeding appears to actually implement a mechanism that holds the LARS Associated Transmission Customer responsible for identified upgrades even if the LARS Associated Load does not commence service at the expected amount. As a result, the proposed Tariff provisions before the Commission are incomplete and wrongly suggest a level of protection against cost shifting that does not (yet) exist. Conditioning any acceptance of LARS, as described above and in Midwest TDUs’ Limited Protest, would ensure that this protection of other customers will function as intended.

MISO next attempts to dismiss cost shifting concerns by arguing that its LARS filing “is not creating a new cost-allocation problem.”30 That is not the relevant legal standard. Not only does MISO have the burden to demonstrate that its revised Tariff language is just, reasonable, and not unduly discriminatory,31 but here MISO is also responding to a Commission Show Cause Order that preliminarily found its existing Tariff to be unjust and unreasonable.32 MISO has not shown that other customers will be protected against cost shifts associated with the transmission infrastructure built to interconnect LARS projects on an expedited basis. Even assuming this cost shifting risk is not new to LARS, that is little comfort to ratepayers that face cost shifting risks under

29 Id. at 5.
30 Id. at 16.
31 16 U.S.C. § 824d(e).
32 Show Cause Order P 113.

PDF page 10

- 10 -
unjust and unreasonable Tariff provisions applied to costs incurred to serve projects interconnecting pursuant to a new LARS process.

Relatedly, MISO also argues that concerns about cost shifting should not delay the large load-related reforms included in its LARS proposal. This presents the Commission with a false choice between protecting against cost shifting and delaying implementation of LARS. Midwest TDUs do not seek to delay LARS, and the conditional acceptance we request allows the Commission to facilitate timely implementation of LARS while still fulfilling its statutory mandate to ensure just, reasonable, and not unduly discriminatory rates.33

Finally, MISO states that “there is nothing in the LARS proposal that would prevent a state regulator from allocating costs of a BRP or Other project more granularly to a specific retail customer.”34 While true, this statement misses the point. The Commission’s Show Cause Order specifically acknowledges the concern that state regulators cannot protect all wholesale transmission customers from cost shifting that occurs through Commission-jurisdictional transmission rates.35 This Commission is statutorily obligated to address cost shifting that occurs through rates subject to its jurisdiction. It can do so with respect to costs incurred for LARS projects, while still allowing timely implementation of LARS, through the conditional acceptance described herein.

33 Similarly, Google argues that the Commission could “accept and suspend the proposal, until it can be evaluated alongside any necessary customer protection measures, including the contemplated pro forma cost shifting agreement.” Limited Protest of Google at 3 (Oct. 23, 2026), eLibrary No. 20261023-5177.
34 MISO Answer at 18.
35 Show Cause Order P 79.

PDF page 11

- 11 -
CONCLUSION
For the reasons discussed above and in Midwest TDUs’ Limited Protest, the Commission should (1) reject MISO’s proposed geographic scope for paired generation and load eligible for LARS and direct MISO to revise its Tariff language consistent with the Show Cause Order; and (2) condition any acceptance on MISO’s filing in this proceeding on the Commission finding, in future proceeding(s), that MISO has satisfied its obligations with respect to the Show Cause Order’s discussion of cost allocation and transparency as applied to LARS.

Respectfully submitted,
 /s/ Cynthia S. Bogorad
Cynthia S. Bogorad
Jeffrey M. Bayne
Attorneys for Midwest TDUs
Law Offices of:
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
(202) 879-4000
November 19, 2026

PDF page 12

CERTIFICATE OF SERVICE
I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated on this 19th day of November, 2026.
 /s/ Jeffrey M. Bayne
Jeffrey M. Bayne
Law Offices of:

Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
Washington, DC 20036
(202) 879-4000