Comments of Alliant Energy Corporate Services, Inc. and Consumers Energy Company in Support of MISO's Proposed Tariff Revisions
Alliant Energy Corporate Services and Consumers Energy, both load-serving entities in MISO, file comments supporting LARS as a way to study large loads and paired generation together, with continued stakeholder work on how projects keep interconnection rights.
Asks FERC to: Find MISO's LARS proposal just and reasonable and accept it.
Supports MISO's LARS filing, which MISO presents as its answer to the E-8 show cause order on operational dynamics of serving electrically proximate large loads.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- The utilities support a study process that handles generation paired with large load together.
support the need for an interconnection process that facilitates the timely study of generation paired with an associated large load(s) to arrive at optimized transmission solutions. PDF p. 1
- Joint planning can avoid duplicate or costly upgrades and lower customer costs.
eliminate duplicative or unnecessarily expensive upgrades, and help deliver lower-cost outcomes for customers. PDF p. 2
- They cite MISO's goal of finishing the parallel study in about 120 days.
with the objective of completing the process within approximately 120 days. PDF p. 2
- They back strong readiness requirements to keep speculative projects out.
Strong readiness requirements are therefore an appropriate safeguard against speculative projects consuming scarce study resources PDF p. 3
- They expect MISO to keep working with stakeholders on how projects retain interconnection rights over time.
providing greater certainty regarding the conditions under which projects may retain interconnection rights over time. PDF p. 3
Contents · 2 sections
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation · Reliability and curtailment
What the document says
PDF p. 2
Supporters say studying load and generation together removes duplicative upgrades and lowers costs.
This integrated approach will enable MISO to identify optimized transmission solutions, eliminate duplicative or unnecessarily expensive upgrades, and help deliver lower-cost outcomes for customers. PDF p. 2
PDF p. 3
Supporters want FERC to accept LARS as filed, citing its entry limits and fuel neutrality.
Strong readiness requirements are therefore an appropriate safeguard against speculative projects consuming scarce study resources PDF p. 3
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
The LARS Proposal offers a practical approach to meeting load growth while helping to maintain resource adequacy and supporting a cost-effective mix of generating resources. 1 18 C.F.R. § 385.212 (2025). 2 Consumers Energy is a Load Serving Entity (LSE) and active participant in the MISO generation…Read this passage Filed comments: Connecting load and generation
Support for LARS as a Just and Reasonable Study Pathway
PDF bookmark · Topic match: Connecting load and generation
MISO’s broader framework for integrating large loads onto its system appropriately recognizes that acceleration must be coupled with operational capabilities such as telemetry, coordination, curtailment capability, ride-through, stability controls, resilience, and security. 4 LARS Proposal at…Read this passage Filed comments: Connecting load and generation
Continued Stakeholder Collaboration on Implementation
PDF bookmark · Topic match: Connecting load and generation
For these reasons, AECS and Consumers Energy respectfully request that the Commission find MISO’s LARS Proposal is a just and reasonable approach to coordinating the study of large loads and paired generation, optimizing transmission solutions, and facilitating timely, reliable service at lower…Read this passage Filed comments: Connecting load and generation