Motion to Intervene and Comments of Base Electron, Corp. re Midcontinent Independent System Operator, Inc’s filing to establish the Large Load Addition…
Text extracted from the eLibrary original (SHA-256 536e8463ffb2d573…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” or the “Commission”) Rules of Practice and Procedure,1 and the Commission’s October 2, 2026 Notice regarding the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposed revisions to its Open Access…Read this passage Filed comments: Connecting load and generation
I. MOTION TO INTERVENE
printed heading · Topic match: Connecting load and generation
Accordingly, Base Electron respectfully requests that the Commission grant this timely motion to intervene with full rights associated with party status in this proceeding.Read this passage Filed comments: Connecting load and generation
II. CORRESPONDENCE AND COMMUNICATIONS
printed heading
CORRESPONDENCE AND COMMUNICATIONS All correspondence and communications regarding this matter and filing should be addressed to the following: Colson R.Read this passage
III. COMMENTS
printed heading · Topic match: Connecting load and generation
MISO’s proposed Tariff revisions implementing LARS provide that “[a]n Interconnection Request seeking LARS processing shall request NRIS Interconnection Service in an amount that is both: (1) not less than 200 MW, and (2) not more than 150% of the peak Demand of the LARS Associated Load.”4…Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading · Topic match: Connecting load and generation
Base Electron reiterates that its comments merely seek clarification and confirmation, which could be provided either in any MISO answer it may file or in FERC’s order in this proceeding, and it neither seeks to delay the resolution of this proceeding nor requests FERC to condition or delay…Read this passage Filed comments: Connecting load and generation
CERTIFICATE OF SERVICE
printed heading
Dated this 23rd day of October 2026. /s/ Colson R.Read this passage