ER27-25-000 · 2026-10-23 · Base Electron, Corp.

Motion to Intervene and Comments of Base Electron, Corp. re Midcontinent Independent System Operator, Inc’s filing to establish the Large Load Addition…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

Midcontinent Independent System
Operator, Inc.
)
)
)

Docket No. ER27-25-000

MOTION TO INTERVENE AND COMMENTS OF
BASE ELECTRON, CORP.

Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” or the “Commission”) Rules of Practice and Procedure,1 and the Commission’s October 2, 2026 Notice regarding the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposed revisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) to implement the Large Load Addition Resource Study (“LARS”), Base Electron, Corp. (“Base Electron”) respectfully submits this Motion to Intervene and Comments.

I. MOTION TO INTERVENE

Base Electron, an independent power producer, respectfully moves under Rules 212 and 214 of the Commission’s Rules of Practice and Procedure2 to intervene in this proceeding. Base Electron and its subsidiaries are developing a portfolio of dedicated, dispatchable power projects designed to provide large-load customers, including hyperscale data center operators, and artificial intelligence and advanced computing companies, with access to firm, reliable, cost-efficient, grid- connected power at scale. Base Electron supports the initiatives undertaken by MISO to develop LARS and implement it in its Tariff. Moreover, Base Electron participated in MISO’s stakeholder process that preceded MISO’s filing in this docket. As provided below, Base Electron seeks to

1 18 C.F.R. §§ 385.212, 385.214.
2 Id.

PDF page 2

2

intervene in this proceeding to offer limited comments on items within MISO’s proposal where clarification and confirmation would be beneficial for entities seeking to interconnect under the LARS procedures.

Given its planned development in MISO, Base Electron has a direct and substantial interest in proposed revisions to MISO’s Tariff, such as those related to LARS. Therefore, Base Electron’s interests may be directly affected by the outcome of this proceeding and cannot adequately be represented by any other party. Accordingly, Base Electron respectfully requests that the Commission grant this timely motion to intervene with full rights associated with party status in this proceeding.

II. CORRESPONDENCE AND COMMUNICATIONS

All correspondence and communications regarding this matter and filing should be addressed to the following:

Colson R. Williams*
Counsel, Commercial & Regulatory
Base Electron, Corp.
4324 Mapleshade Lane, Suite 137
Plano, Texas 75093
(214) 270-2140
cwilliams@baseelectron.com

*Admitted in Montana
Tim Woodland
Executive Vice President, Operations
Base Electron, Corp.
4324 Mapleshade Lane, Suite 137
Plano, Texas 75093
(214) 270-2140
twoodland@baseelectron.com

III. COMMENTS

At the outset, Base Electron supports timely acceptance of MISO’s LARS Tariff proposal. Base Electron’s comments neither seek to delay the resolution of this proceeding nor request FERC to condition or delay effectiveness of MISO’s LARS proposal on the requested clarification and confirmation herein.

PDF page 3

3

Base Electron’s comments seek clarification and confirmation on a single item within MISO’s proposal: for the purpose of determining the allowable Interconnection Service amount requested under the LARS Interconnection Request, whether the LARS Associated Load’s “expected peak Demand” means the load’s Demand at the time it first takes service or the expected peak Demand once any planned future phase build-outs of the load are in service.3 Put differently, how will MISO measure the LARS Associated Load’s expected peak Demand?

MISO’s proposed Tariff revisions implementing LARS provide that “[a]n Interconnection Request seeking LARS processing shall request NRIS Interconnection Service in an amount that is both: (1) not less than 200 MW, and (2) not more than 150% of the peak Demand of the LARS Associated Load.”4 Moreover, the proposed Tariff revisions later state that the Interconnection Service requested “must not exceed 150 percent of the LARS Associated Load’s expected peak Demand.”5 In further support of the need for clarification, MISO states that a LARS Associated Load can come online in phases and that “[t]he LARS Application should identify the total expected large load amount that is aligned with the full Generator Interconnection Service request not to exceed 150% of the peak demand of the LARS Associated Load.”6

Base Electron’s comments merely seek clarification and confirmation on how and based on what parameters MISO will measure the 150% limit on Interconnection Service for the interconnecting generator, when a LARS Associated Load might commence service in phases (i.e., how MISO will measure expected peak Demand). As Base Electron understands it, the 150% cap on Interconnection Service is not measured on any first or initial phase of the load, but on a total

3 MISO, Proposed Tariff, Attachment X (193.0.0), § 3.12.2; id., § 1 (Definitions).
4 Id., Attachment X (193.0.0), § 3.12.2.vi.
5 Id., Attachment X (193.0.0), § 3.12.2 (emphasis added).
6 MISO, Filing, Docket No. ER27-25-000, Tab C, Prepared Direct Testimony of Christina Drake at 26:21-27:1 (filed Oct. 2, 2026) (Drake Test.).

PDF page 4

4

expected load at the conclusion of any phases anticipated by the LARS Associated Load. Clarification and confirmation from MISO on this issue is important because, according to the LARS Tariff proposal, a generator cannot change requested Interconnection Service after the submission of the LARS Application and prior to the execution or unexecuted filing of the final Large Load Generator Interconnection Agreement.7 Likewise, MISO’s testimony states that for the LARS Associated Load, “[a]ny increase in the amount of load demanded is not allowed and the customer would need to submit a new LARS Application or apply for some other kind of Interconnection Service.”8 If the 150% limit on Interconnection Service is measured by a load’s first phase, and not the expected and anticipated future load size, the interconnecting generator would be precluded from adequately sizing its facility to meet the full load at final phased build- out. In turn, any remaining generator Interconnection Service to serve a full build-out of the load could then be required to go through MISO’s Definitive Planning Phase process, which includes a longer study timeline.

In conclusion, Base Electron respectfully requests confirmation and clarification on (1) whether “expected peak Demand” for purposes of deriving the 150% limit on Interconnection Service requested by the generator means the LARS Associated Load’s expected peak once it “commence[s] service for the full amount of transmission service requested in the LARS Application”;9 and (2) whether a LARS Interconnection Request that sizes its Interconnection Service based on the load’s full expected peak measured by future anticipated phases satisfies Attachment X, § 3.12.2.vi, even if the LARS Associated Load initially takes service at a lower level during any preliminary phase build-out.

7 See MISO, Proposed Tariff, Attachment X (193.0.0), §§ 3.12.2, 3.12.9.
8 Drake Test. at 38:9-11. 9 MISO, Proposed Tariff, Attachment X (193.0.0), § 3.12.2.vii.

PDF page 5

5

IV. CONCLUSION

For the foregoing reasons, Base Electron respectfully requests that its motion to intervene be granted by the Commission, and the preceding comments be considered by the Commission in its review of MISO’s filing in this proceeding. Base Electron reiterates that its comments merely seek clarification and confirmation, which could be provided either in any MISO answer it may file or in FERC’s order in this proceeding, and it neither seeks to delay the resolution of this proceeding nor requests FERC to condition or delay effectiveness of MISO’s LARS proposal on the requested clarification and confirmation herein.

Dated: October 23, 2026
/s/ Colson R. Williams

Colson R. Williams*
Counsel, Commercial & Regulatory
Base Electron, Corp.
4324 Mapleshade Lane, Suite 137
Plano, Texas 75093
(214) 270-2140
cwilliams@baseelectron.com

*Admitted in Montana

Counsel for Base Electron, Corp.

PDF page 6

6

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated this 23rd day of October 2026.

/s/ Colson R. Williams

Colson R. Williams