Comments on Behalf of the Southern Regulators (Mississippi and Louisiana PSCs) in Support of MISO Application
The Mississippi and Louisiana Public Service Commissions, as the Southern Regulators, file comments supporting MISO's LARS filing as a 120-day parallel study of loads above 200 MW and paired generation that responds to the show cause order.
Asks FERC to: Accept MISO's LARS filing.
Supports MISO's LARS filing as a response to the E-8 show cause order finding that MISO lacks study procedures for electrically proximate large loads.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- The regulators describe LARS as meant to address the show cause order finding on electrically proximate large loads.
The LARS proposal also is intended to address the Commission's June 18, 2026 Show Cause Order finding that MISO's Tariff may be unjust and unreasonable PDF p. 1
- LARS coordinates and speeds study of loads above 200 MW and the generation identified for them.
coordinate and expedite the analyses needed to interconnect large loads above 200 MW and the new generation resources identified to support that new load. PDF p. 1
- Joint study can cut upgrade needs and costs, and LARS studies pairs in 120 days.
LARS provides for a 120-day parallel study of eligible large loads and their paired generation resources. PDF p. 2
- They say permanence supplies the certainty needed to site and finance pairings.
Making LARS a permanent process is reasonable because it provides certainty needed to site and finance large load-and-generation pairings. PDF p. 2
- They list the caps and eligibility rules that deter speculative requests.
including a 150% generation to load ceiling, a $250,000 deposit, a three-year commercial operation date, and a same-Local-Resource-Zone requirement. PDF p. 2
Read topic-matched comments in ER27-25
Topics in the text: Connecting load and generation
What the document says
PDF p. 2
LARS studies a 200 MW-plus load and its paired generation together in about 120 days.
LARS provides for a 120-day parallel study of eligible large loads and their paired generation resources. PDF p. 2Filed comments: Connecting load and generation
PDF p. 2
Supporters say studying load and generation together removes duplicative upgrades and lowers costs.
By studying load and its paired generation together, MISO can identify combined transmission solutions, avoid duplicative and costly upgrades, and produce an outcome in approximately 120 days. PDF p. 2
PDF p. 3
Supporters want FERC to accept LARS as filed, citing its entry limits and fuel neutrality.
MISO's proposal is transparent, competitive, fuel agnostic, and it does not adversely affect DPP participants. PDF p. 3
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
LARS is a reasonable response to and aligns with the requirements of the Commission’s Show Cause Order.2 LARS limits the total number of projects studied in a year to ensure that MISO can administratively support the new process; it allows no more than ten generation/load pairs per study period to…Read this passage Filed comments: Connecting load and generation