ER27-25-000 · 2026-10-23 · Mississippi and Louisiana PSCs
Comments on Behalf of the Southern Regulators (Mississippi and Louisiana PSCs) in Support of MISO Application
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
Operator, Inc
)
)
Docket No. ER27-25-000
COMMENTS ON BEHALF OF THE SOUTHERN REGULATORS IN SUPPORT OF
MISO APPLICATION
Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure1, and the Commission’s October 2, 2026, notice in the above-captioned docket, the Mississippi Public Service Commission and the Louisiana Public Service Commission (together, the Southern Regulators) hereby submit comments in support of the Midcontinent Independent System Operator, Inc.’s (“MISO’s”) filing to establish the Large Load Addition Resource Study (“LARS”). The LARS proposal seeks to revise MISO’s Open Access Transmission, Energy, and Operating Reserves Markets Tariff to establish a process to enable load and generation to be studied together. The LARS proposal also is intended to address the Commission’s June 18, 2026 Show Cause Order finding that MISO’s Tariff may be unjust and unreasonable because it does not provide generator interconnection study procedures and services that account for serving electrically proximate Large Loads.
The Southern Regulators support MISO’s filing to establish the LARS process and respectfully request that the Commission accept it. It is designed to coordinate and expedite the analyses needed to interconnect large loads above 200 MW and the new generation resources identified to support that new load. The LARS process may also reduce overall interconnection costs and provide more certainty for interconnection customers.
1 18 C.F.R. § 385.212.
PDF page 2
2
Large Loads are seeking interconnection with the MISO system in ever increasing numbers. Studying these loads along with the generation that is planned to serve those loads may reduce the need for and the costs of transmission upgrades that might otherwise needed if only the generation or only the load were interconnecting. LARS provides for a 120-day parallel study of eligible large loads and their paired generation resources.
LARS should be accepted by the Commission because it is just and reasonable. By studying load and its paired generation together, MISO can identify combined transmission solutions, avoid duplicative and costly upgrades, and produce an outcome in approximately 120 days. This is not currently possible across the separate MISO transmission interconnection transmission study processes. Making LARS a permanent process is reasonable because it provides certainty needed to site and finance large load-and-generation pairings. LARS is a reasonable response to and aligns with the requirements of the Commission’s Show Cause Order.2
LARS limits the total number of projects studied in a year to ensure that MISO can administratively support the new process; it allows no more than ten generation/load pairs per study period to be evaluated, and allows for only three study periods per year.3 MISO’s tariff revisions propose eligibility requirements that deter speculative interconnection requests and not interfere with the normal DPP process, including a 150% generation to load ceiling, a $250,000 deposit, a three-year commercial operation date, and a same-Local-Resource-Zone requirement.42 Show Cause Midcontinent Independent System Operator, Inc., 195 FERC ¶ 61,212, (issued June 18, 2026) (Docket No. EL26-70-000) (“Show Cause Order”) at P 113.3 MISO Transmittal at 9.4 Id. at 10, 28.
PDF page 3
3
MISO’s proposal is transparent, competitive, fuel agnostic, and it does not adversely affect DPP participants.5 It is non-discriminatory and serves a legitimate public purpose. Therefore, the Southern Regulators respectfully request that the Commission accept MISO’s LARS filing.
Barton Norfleet
Special Counsel; Federal Energy Affairs
Mississippi Public Service Commission
501 N. West Street, Suite 201-A
P.O. Box 1174
Jackson, MS 39215-1174
Phone: (601) 961-5821
barton.norfleet@psc.ms.gov
Respectfully submitted,
/s/ William D. Booth
William D. Booth
Orrie A. Walsvik
Michael Best & Friedrich LLP
1000 Maine Avenue, S.W.
Suite 400
Washington, D.C. 20024
Phone: (202) 747-9560
wdbooth@michaelbest.com
orrie.walsvik@michaelbest.com
Attorneys for the Mississippi Public Service
Commission
5 Midcontinent Independent System Operator, Inc., 192 FERC ¶ 61,064 at Para. 2 (July 21, 2025) (Docket No. ER 25-2454-000); see also MISO Transmittal at 10.
PDF page 4
4
Kathryn Bowman
Executive Counsel
Lauren Evans
Deputy General Counsel
Louisiana Public Service Commission 602 North Fifth Street, Baton Rouge, Louisiana 70802
Phone: (225) 342-9888
Kathryn.bowman@la.gov
Lauren.evans@la.gov
/s/ Noel J. Darce
Noel J. Darce
Dana M. Shelton
Justin A. Swaim
Fishman Haygood LLP
601 St. Charles Ave. Suite 4600
New Orleans LA 70170
Phone: (504) 586-5252
ndarce@fishmanhaygood.com
dshelton@fishmanhaygood.com
jswaim@fishmanhaygood.com
Attorneys for the Louisiana Public Service Commission
PDF page 5
5
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon the parties designated on the official service list for the above-captioned docket in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure.
Dated at New Orleans, Louisiana on this 23rd day of October, 2026.
/s/ Noel J. Darce