ER27-25-000 · 2026-10-23 · Data Center Coalition

Motion to Intervene and Comments of Data Center Coalition on Midcontinent Independent System Operator, Inc.’s proposal to establish the Large Load…

Text extracted from the eLibrary original (SHA-256 1207250253bc43cb…). Download the original from the official source.

Contents · 8 sections
  1. I. INTRODUCTION p. 1
  2. II. COMMENTS IN SUPPORT p. 3
  3. A. LARS Modernizes Transmission Service and Generator Interconnection Study p. 3
  4. B. LARS Supports Ratepayer Affordability By Facilitating New Generation, p. 4
  5. III. CONCERNS AND ROOM FOR IMPROVEMENT p. 6
  6. IV. MOTION TO INTERVENE p. 7
  7. V. CORRESPONDENCE AND COMMUNICATIONS p. 8
  8. VI. CONCLUSION p. 9

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER27-25-000 Operator, Inc. ) MOTION TO INTERVENE AND COMMENTS OF THE DATA CENTER COALITION Pursuant to Rules 211, 212, and 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”)1 and the Commission’s October 2, 2026 Combined Notice of…
Read this passage Filed comments: Connecting load and generation

I. INTRODUCTION

printed heading · Topic match: Cost allocation

DCC advocates for grid reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate responsible load growth, support the development of new generation, and enhance grid resilience system-wide without imposing undue costs on existing ratepayers.
Read this passage Filed comments: Cost allocation

II. COMMENTS IN SUPPORT

printed heading

II.
Read this passage

A. LARS Modernizes Transmission Service and Generator Interconnection Study

printed heading · Topic match: Connecting load and generation

LARS Modernizes Transmission Service and Generator Interconnection Study Processes to Align with the Pace of Economic Growth DCC members are committed to supporting regional economic expansion as reliable grid citizens, supporting reforms that facilitate responsible load growth and new generation…
Read this passage Filed comments: Connecting load and generation

B. LARS Supports Ratepayer Affordability By Facilitating New Generation,

printed heading · Topic match: Cost allocation

DCC welcomes MISO’s balanced approach of introducing new pathways and optionality, without mandating that new large loads must bring their own generation.
Read this passage Filed comments: Cost allocation

III. CONCERNS AND ROOM FOR IMPROVEMENT

printed heading · Topic match: Connecting load and generation

In response to these concerns, DCC supports approval of the proposed LARS framework, but requests FERC encourage MISO to consider improvements for independent generator access, such as allowing third-party generators with demonstrated commercial pairings to submit LARS generator interconnect…
Read this passage Filed comments: Connecting load and generation

IV. MOTION TO INTERVENE

printed heading · Topic match: Cost allocation

DCC advocates for grid reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate responsible load growth, support the development of new generation, and enhance grid resilience system- wide without imposing undue costs on existing ratepayers.
Read this passage Filed comments: Cost allocation

V. CORRESPONDENCE AND COMMUNICATIONS

printed heading

CORRESPONDENCE AND COMMUNICATIONS DCC requests that the following names be placed on the official service list for this proceeding by the Commission and that all correspondence and communications with respect to this proceeding be addressed to the following: Morgan A.
Read this passage

VI. CONCLUSION

printed heading

CONCLUSION For the reasons set out above, DCC respectfully requests that the Commission issue an order consistent with these comments.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 23th day of October 2026. /s/ Morgan A.