ER27-25-000 · 2026-10-23 · Data Center Coalition

Motion to Intervene and Comments of Data Center Coalition on Midcontinent Independent System Operator, Inc.’s proposal to establish the Large Load…

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

    )
Midcontinent Independent System
    )                               Docket No. ER27-25-000
Operator, Inc.
                                        )

MOTION TO INTERVENE
AND COMMENTS OF THE DATA CENTER COALITION

Pursuant to Rules 211, 212, and 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or the “Commission”)1 and the Commission’s October 2, 2026 Combined Notice of Filings #1,2 the Data Center Coalition (“DCC”) hereby moves to intervene and submits these comments on Midcontinent Independent System Operator, Inc.’s (“MISO”) proposal to establish the Large Load Additional Resource Study (LARS) framework3

I. INTRODUCTION
DCC is the membership organization for the U.S. data center industry, representing leading data center owners and operators that develop, operate, and maintain data center infrastructure and teams across the country.4 DCC members operate data centers that constitute significant loads within the MISO region and DCC has been an active stakeholder in regional efforts to ensure reliability, enable new generation, and discipline load forecasts. DCC and its members have been at the forefront of efforts to advance reforms to accommodate the growth of

1 118 C.F.R. §§ 385.212 and 385.214. 2 Midcontinent Independent System Operator, Inc., et al., Docket No. ER27-25-000 et al., Combined Notice of Filings #1 (Oct, 2, 2026).
3 Midcontinent Independent System Operator, Inc., Docket No. ER27-25-000, Proposal of Midcontinent Independent System Operator, Inc. to Establish the Large Load Resource Addition Study (Oct. 2, 2026) (“Filing”).
4 The DCC is a membership organization of leading data center owners and operators. Public testimony and written comments submitted by DCC do not necessarily reflect the views of each individual DCC member. A list of current DCC members is accessible at https://www.datacentercoalition.org/members.

PDF page 2

2

large loads within the MISO region while maintaining reliability and protecting existing retail customers.

As the industry unlocks unprecedented economic opportunities across the country and in the MISO region, supporting affordability is a foundational priority for DCC members and the communities they serve. DCC advocates for grid reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate responsible load growth, support the development of new generation, and enhance grid resilience system-wide without imposing undue costs on existing ratepayers. DCC members are committed to supporting the generation and infrastructure additions required to serve their demand responsibly.

DCC commends MISO’s proactive engagement with stakeholders and the data center community to develop innovative study process reforms to facilitate the timely integration of large loads while maintaining system reliability and affordability. DCC member facilities depend upon reliable and cost-effective electricity service, and DCC shares MISO’s objective of ensuring that the interconnection and operation of large load customers does not adversely affect reliability, system operations, or other transmission customers. Accordingly, DCC supports MISO’s proposed LARS framework for the expedited, coordinated study of certain generation- load pairs as a pragmatic new pathway to “facilitate the cost effective, timely and reliable integration of new large loads into the system”5 by allowing large loads to support both the generation as well as infrastructure additions required to serve their demand while also addressing Commission directives in its June 18, 2026 Order to Show Cause.6

5 Filing, Transmittal Letter at 2.
6 Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”).

PDF page 3

3

II. COMMENTS IN SUPPORT
A. LARS Modernizes Transmission Service and Generator Interconnection Study
Processes to Align with the Pace of Economic Growth
DCC members are committed to supporting regional economic expansion as reliable grid citizens, supporting reforms that facilitate responsible load growth and new generation development while protecting ratepayer affordability and system resilience. MISO projects annual load growth of 1% to 3% through 2044, driven by the expansion of energy-intensive industries including data centers as well as advanced manufacturing.7 Meeting the unprecedented growth in MISO’s footprint responsibly and reliably requires a modernized approach to resource integration and identification of grid upgrades and the LARS proposal embodies this necessary evolution. The LARS proposal provides a productive and targeted framework for studying qualifying large loads (200 MW or greater) alongside contractually paired new generation in the same Local Resource Zone (“LRZ”) on an expedited 120-day cycle. By evaluating this group of load and generation pairs on a coordinated and concurrent basis, LARS offers a practical tool that will bring essential supply online quickly to support MISO’s economic growth while optimizing network upgrades and protecting overall customer affordability. Such an approach is directly aligned with DCC’s objective of ensuring data centers and other large load customers take appropriate responsibility for supporting the development of new generation and infrastructure necessary to serve their demand.

For generation and load that are contractually associated, the traditional approach of disaggregated generation queue and transmission service study processes can result in inaccurate study results and unnecessary delays that fail to match the pace of economic growth and need for

7 Filing, Transmittal Letter at 2.

PDF page 4

4

new supply. Failing to reflect contractually associated generators when studying the provision of transmission service for large loads can create an incomplete and inaccurate picture of grid conditions. This may lead to the identification of inefficient, unnecessary, or costly Network Upgrades that do not match actual grid impacts.

In response to these challenges, MISO’s LARS framework provides a new pathway offering load customers new optionality to access a coordinated and expedited study pathway for the discrete set of circumstances where eligible large loads have contractually associated generation located in the same LRZ. By studying this discrete set of load-generation pairs concurrently under LARS, MISO will be able to produce a more realistic picture of the grid, creating opportunities for MISO to potentially optimize Network Upgrades.  Additionally, the more streamlined 120-day process proposed under the LARS framework can bring both needed supply and demand online efficiently, aligning with the original federal objectives of the Department of Energy’s (DOE) Speed to Power Initiative to accelerate development timelines for large-scale transmission and generation projects to meet rising electricity demand.8

B. LARS Supports Ratepayer Affordability By Facilitating New Generation,
Optimizing Network Upgrades, and Isolating Network Upgrade Costs

As the industry unlocks unprecedented economic opportunities across the country and in the MISO footprint, supporting affordability is a priority for DCC members and the communities they serve. DCC acknowledges that bringing significant new large loads online without enabling sufficient new generation supply may exacerbate tight grid conditions and resource adequacy concerns, putting upward pressure on prices or inappropriately shift costs to existing ratepayers.

8 U.S. Department of Energy’s Speed to Power Initiative (Sept. 18, 2025). See also, Filing, Transmittal Letter at 2.

PDF page 5

5

The DCC will continue to champion reforms that enable data centers to bring their own generation capacity as a method to insulate existing ratepayers from the costs of serving demand from large load customers. The LARS framework is an example of such a reform. LARS can mitigate cost risks by creating the opportunity for MISO to explore optimized transmission solutions, offering a pathway that encourages large loads to proactively identify and bring new generation supply to directly satisfy their new energy demands, and producing a more holistic view of Network Upgrades that can be appropriately allocated under future cost allocation reforms.

First, LARS supports affordability by allowing MISO to more accurately evaluate the impact of both load and generation on the transmission system, allowing MISO to consider optimized configurations of Network Upgrades, potentially reducing unnecessary infrastructure investment and associated costs. Moreover, the LARS framework can help provide cost transparency by isolating the Network Upgrades needed to support these discrete generation-load pairs, which can better inform cost allocation methods.

Additionally, access to a coordinated and expedited 120-day study process creates an incentive for new large load customers to proactively contract with new generation supply, allowing large load customers to support the generation and infrastructure additions required to serve their demand responsibly. DCC welcomes MISO’s balanced approach of introducing new pathways and optionality, without mandating that new large loads must bring their own generation.

Finally, DCC also recognizes that the appropriate allocation of costs for transmission upgrades identified through LARS, and other transmission service study processes, remains an important issue to be addressed through MISO's ongoing stakeholder process. Any resulting cost

PDF page 6

6

allocation framework should reflect cost causation, recognize benefits to the broader transmission system, and avoid inappropriate cost shifts to existing customers. In alignment with these principles, DCC members proudly joined over 200 governors, utilities, electric cooperatives, and industry leaders in supporting the White House’s “Ratepayer Protection Pledge.”9

III. CONCERNS AND ROOM FOR IMPROVEMENT
While DCC supports MISO’s LARS proposal as a productive framework that facilitates the timely integration of large loads, DCC acknowledges outstanding concerns regarding access to the generator interconnection queue under this process. Under MISO’s proposed framework, all LARS applications must be submitted exclusively through the new “LARS Associated Transmission Customer,”10 typically the Load-Serving Entity (“LSE”). As a result, third-party generation owners cannot submit a LARS generator interconnection request directly to MISO and must instead route requests through the LSE, restricting their direct participation and ability to reap the benefits of the new expedited generator interconnection study under the LARS framework.

While it is appropriate for LSEs with obligations to serve load to manage load-side requests under LARS, requiring all supporting generation to route through an LSE for purposes of accessing a FERC-jurisdictional generator interconnection queue imposes unnecessary restrictions. In MISO’s primarily vertically integrated footprint, establishing the LSE as the sole LARS application facilitator narrows the pool of supply that can gain access to expedited Large

9 Ratepayer Protection Pledge, THE WHITE HOUSE, Proclamation No. 11014, 91 Fed. Reg. 11439 (Mar. 4, 2026), https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/. See also, 10 Filing, Transmittal Letter at P 7, see also id. at P 6 n. 23.

PDF page 7

7

Load Generation Interconnection Agreements (“LLGIAs”) to only those projects that are effectively approved by the LSE. In contrast, most FERC-jurisdictional queue processes, including MISO’s DPP and ERAS, allow all generators to directly submit interconnection requests and execute interconnection agreements without LSE approval, aligned with FERC’s open access principles. DCC clarifies that its concern strictly pertains to maximizing generator access to expedited LLGIAs, while fully recognizing state jurisdictional authority over retail service, including decisions regarding retail competition for generation.

In response to these concerns, DCC supports approval of the proposed LARS framework, but requests FERC encourage MISO to consider improvements for independent generator access, such as allowing third-party generators with demonstrated commercial pairings to submit LARS generator interconnect requests directly to MISO alongside the load application, or explore additional transparency and evaluation metrics regarding LSE decisions on LARS application selection. Broad access will expand the pool of supply that has access to expedited LLGIAs, ultimately supporting new demand.

Finally, following implementation experience with LARS, MISO could also consider additional improvements to ensure program effectiveness, including whether greater flexibility in the generation-to-load ratio and minimum generation project size would better support supply diversification and resilience, as well as whether a more defined transition period could help operating LARS loads maintain transmission service while securing replacement generation if such instances arise.

IV. MOTION TO INTERVENE
DCC respectfully moves to intervene in this proceeding. DCC is the membership organization for the U.S. data center industry, representing leading data center owners and

PDF page 8

8

operators that develop, operate, and maintain data center infrastructure and teams across the country. DCC members operate data centers that constitute significant loads within the MISO region and have been at the forefront of efforts to advance reforms to accommodate the growth of large loads within the MISO region while maintaining reliability and protecting existing retail customers.

DCC’s member companies provide the essential digital infrastructure that underpins the modern economy and supports critical public services, including cloud computing, artificial intelligence, emergency response systems, and public safety operations. From 2017 to 2023, the data center industry contributed $3.5 trillion to U.S. GDP. DCC advocates for grid reforms that minimize unnecessary cost burdens, align with cost causation principles, facilitate responsible load growth, support the development of new generation, and enhance grid resilience system- wide without imposing undue costs on existing ratepayers.

For the above reasons, DCC has a substantial interest in the outcome of this proceeding that cannot be represented adequately by any other participant to this proceeding. DCC’s intervention is in the public interest and its motion for leave to intervene in this proceeding should be granted.

V. CORRESPONDENCE AND COMMUNICATIONS
DCC requests that the following names be placed on the official service list for this proceeding by the Commission and that all correspondence and communications with respect to this proceeding be addressed to the following:

Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, NW

PDF page 9

9

Washington, DC  20005
morgan@datacentercoalition.org

VI. CONCLUSION
For the reasons set out above, DCC respectfully requests that the Commission issue an order consistent with these comments.

Respectfully submitted,

/s/ Morgan A. Sipple
Morgan A. Sipple
Director, Energy Policy – FERC and RTOs
DATA CENTER COALITION
1250 H Street, NW
Washington, DC  20005
morgan@datacentercoalition.org

Dated: October 23, 2026

PDF page 10

10

CERTIFICATE OF SERVICE
I hereby certify that I have this day served a copy of the foregoing document on the persons designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., this 23th day of October 2026.

/s/ Morgan A. Sipple
Morgan A. Sipple