ER27-25-000 · 2026-10-23 · DTE Electric

Comments of DTE Electric Company

DTE Electric, which serves about two million Michigan customers, comments in support of MISO's October 2 LARS filing and asks FERC to accept it as proposed, citing its entry requirements and its role in answering the show cause order.

Asks FERC to: Accept MISO's LARS filing as proposed.

Supports MISO's LARS filing as compliance with the E-8 show cause order, which DTE says directs a just and reasonable framework for integrating large and co-located loads.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. DTE Electric supports LARS as a reasonable way to evaluate load additions and paired generation.
    DTE Electric supports MISO's proposal and believes the LARS framework represents a reasonable approach to evaluating the transmission, operational, and resource adequacy impacts PDF p. 1
  2. Studying load and generation together can show different impacts than stand-alone studies.
    jointly planned and electrically proximate resources may produce materially different system impacts than traditional stand-alone studies. PDF p. 2
  3. DTE points to deposit, size, site control and pairing requirements as safeguards against speculative requests.
    Participating projects must satisfy applicable deposit, minimum size, site control, and commercial operation requirements. PDF p. 3
  4. DTE notes any eligible entity may be the interconnection customer for the generation.
    permitting the interconnection customer responsible for the generation component to be any eligible entity PDF p. 3
Contents · 5 sections
  1. I. Background p. 1
  2. II. COMMENTS p. 2
  3. A. The LARS filing is a just and reasonable solution to integrate new large loads p. 2
  4. III. COMMUNICATIONS p. 3
  5. IV. CONCLUSION p. 4

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Reliability and curtailment

What the document says

PDF p. 2

Supporters say studying load and generation together removes duplicative upgrades and lowers costs.

By allowing large loads and associated generation resources to be studied together, the proposal recognizes that jointly planned and electrically proximate resources may produce materially different system impacts PDF p. 2

PDF p. 3

MISO says LARS answers the Show Cause Order and leaves the generator queue untouched.

The LARS filing also preserves an open and non-discriminatory framework by permitting the interconnection customer responsible for the generation component to be any eligible entity. PDF p. 3
Filed comments: Connecting load and generation

PDF p. 3

Supporters want FERC to accept LARS as filed, citing its entry limits and fuel neutrality.

These requirements provide reasonable assurance that participating projects represent durable load-generation relationships and help mitigate potential impacts to the transmission system and other customers. PDF p. 3

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midcontinent Independent System ) Docket No.
Read this passage Filed comments: Connecting load and generation

I. Background

printed heading · Topic match: Connecting load and generation

Background In this proceeding, MISO proposes revisions to its Tariff to establish the LARS framework.
Read this passage Filed comments: Connecting load and generation

II. COMMENTS

printed heading · Topic match: Connecting load and generation

COMMENTS DTE Electric supports the LARS filing and respectfully requests that the Commission accept the filing as proposed.
Read this passage Filed comments: Connecting load and generation

A. The LARS filing is a just and reasonable solution to integrate new large loads

printed heading · Topic match: Connecting load and generation

Accordingly, DTE Electric respectfully requests that the Commission approve the LARS Filing as proposed.
Read this passage Filed comments: Connecting load and generation

III. COMMUNICATIONS

printed heading

COMMUNICATIONS DTE Electric requests that all communications, correspondence, documents, and other materials related to this proceeding be addressed to the following persons: 4 Tristin Rojeck Regulatory Affairs DTE Electric Company One Energy Plaza Detroit, Michigan 48226 (313) 235-1041…
Read this passage

IV. CONCLUSION

printed heading · Topic match: Connecting load and generation

Accordingly, DTE Electric respectfully requests that the Commission accept the LARS Filing as proposed.