UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System
)
Docket No. ER27-25-000
Operator, Inc
)
COMMENTS OF DTE ELECTRIC COMPANY
Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure, 18 CFR §§ 385.212 and 385.214 (2013), DTE Electric Company (“DTE Electric”, “DTE”, or the “Company”) hereby submits its comments regarding the filing submitted by Midcontinent Independent System Operator, Inc. ("MISO") on October 2, 2026, in the above-captioned docket proposing to establish a Large Load Addition Resource Study ("LARS") process.1 DTE Electric supports MISO's proposal and believes the LARS framework represents a reasonable approach to evaluating the transmission, operational, and resource adequacy impacts associated with significant new load additions and associated generation resources within the MISO footprint.
I. Background
In this proceeding, MISO proposes revisions to its Tariff to establish the LARS framework. MISO states that the proposal is intended to facilitate the timely and reliable integration of significant new load additions and associated generation resources through a coordinated study process that evaluates transmission, operational, and resource adequacy impacts. Under the
1 Midcontinent Independent System Operator, Inc., Large Load Addition Resource Study (“LARS”) Process, Docket No. ER27-25-000 (October 2, 2026). (“LARS Filing.”)
PDF page 2
2
proposal, eligible load-generation pairings may request a LARS evaluation, allowing MISO and stakeholders to assess the combined impacts of associated load and generation resources, improve planning certainty, and support more efficient use of the transmission system. MISO requests that the Commission accept the proposed tariff revisions and permit the LARS framework to become effective as proposed.
II. COMMENTS
DTE Electric supports the LARS filing and respectfully requests that the Commission accept the filing as proposed. As the load-serving entity responsible for serving approximately two million customers in Michigan, DTE Electric has a direct interest in ensuring that significant new load additions are integrated through processes that appropriately account for associated generation, transmission needs, and effects on other customers.
A. The LARS filing is a just and reasonable solution to integrate new large loads while maintaining resource adequacy and reliability and supports MISO's
compliance with the Commission's Show Cause Order.
The LARS Filing directly responds to the Commission’s directive to create “a just and reasonable framework for addressing these concerns and ensuring the timely, efficient, and reliable integration of large and co-located loads onto the transmission system.”2 By allowing large loads and associated generation resources to be studied together, the proposal recognizes that jointly planned and electrically proximate resources may produce materially different system impacts than traditional stand-alone studies. This coordinated approach provides MISO with a more complete assessment of the net impacts of load and generation pairings and supports more informed planning and operational decision-making.
2 Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order”) at P 2.
PDF page 3
3
The proposal also contains meaningful safeguards designed to ensure participation is limited to qualifying projects and to discourage speculative requests. Participating projects must satisfy applicable deposit, minimum size, site control, and commercial operation requirements. In addition, load and generation pairings must demonstrate a qualifying contractual relationship, remain within the same Local Resource Zone, and maintain a long-term commitment to remain paired. These requirements provide reasonable assurance that participating projects represent durable load-generation relationships and help mitigate potential impacts to the transmission system and other customers.
The LARS filing also preserves an open and non-discriminatory framework by permitting the interconnection customer responsible for the generation component to be any eligible entity. This approach maintains flexibility for loads, generators, and load-serving entities while preserving the technical, financial, and operational safeguards necessary to protect reliability and other customers.
Taken together, these provisions establish a targeted and balanced framework that facilitates the efficient integration of significant new loads while preserving appropriate customer and reliability protections. Accordingly, DTE Electric respectfully requests that the Commission approve the LARS Filing as proposed.
III. COMMUNICATIONS
DTE Electric requests that all communications, correspondence, documents, and other materials related to this proceeding be addressed to the following persons:
PDF page 4
4
Tristin Rojeck
Regulatory Affairs
DTE Electric Company
One Energy Plaza
Detroit, Michigan 48226
(313) 235-1041
tristin.rojeck@dteenergy.com
Andrea E. Hayden
Office of the General Counsel
DTE Electric Company
One Energy Plaza
Detroit, Michigan 48226
(313) 235-6205
andrea.hayden@dteenergy.com
IV. CONCLUSION
DTE Electric believes the LARS Filing constitutes a reasonable and targeted response to the concerns identified by the Commission in the Show Cause Order. The proposal establishes an appropriately tailored framework for the coordinated study of large loads and associated generation resources while maintaining important reliability safeguards. Accordingly, DTE Electric respectfully requests that the Commission accept the LARS Filing as proposed. Respectfully submitted,
/s/Andrea E. Hayden
Andrea E. Hayden
Office of the General Counsel
DTE Electric Company
One Energy Plaza
Detroit, Michigan 48226-1279
(734)546-0179
andrea.hayden@dteenergy.com
Counsel for DTE Electric Company
Filed: October 23, 2026
PDF page 5
CERTIFICATE OF SERVICE
In accordance with 18 C.F.R. § 385.2010, I hereby certify that I have, on this 23rd day of October 2026, caused a copy of the foregoing Comments of DTE Electric Company to be served on each person designated on the official service list compiled by the Secretary of the Commission in Docket No. ER27-25.
/s/ Andrea Hayden