Comments of the Arkansas Public Service Commission in Support of MISO Application
Word notes use stable document IDs, such as [fn:8], which can differ from printed footnote numbers.
Document text
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc
)
)
Docket No. ER27-25-000
COMMENTS ON BEHALF OF THE SOUTHERN REGULATORS IN SUPPORT OF MISO APPLICATION
Pursuant to Rule 212 of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Rules of Practice and Procedure[fn:1], the Arkansas Public Service Commission (“APSC”) respectfully submits these comments regarding the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposed revisions to its Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff” or “MISO’s Tariff”) to establish the Large Load Addition Resource Study (“LARS”).
The APSC supports MISO’s filing to establish the LARS process, and agrees with the comments made by the Mississippi Public Service Commission and the Louisiana Public Service Commission. LARS should be accepted by the Commission because it is just and reasonable. Further, AR agrees that LARS is a reasonable response to and aligns with the requirements of the Commission’s Show Cause Order.[fn:2]
Therefore, the APSC respectfully request that the Commission accept MISO’s LARS filing.
Respectfully submitted,
/s/ Luke Kinder
Bridgette Frazier
Luke Kinder
Commission Counsel
Arkansas Public Service Commission
1000 Center Street
P.O. Box 400
Little Rock, AR 72201-4314
Telephone: (501) 682-5816
(501) 682-5766
bridgette.frazier@arkansas.gov
luke.kinder@arkansas.gov
CERTIFICATE OF SERVICE
I, hereby certify that I have this day, the 23rd of October, 2026, of served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.
/s/ Luke Kinder
Luke Kinder
Bridgette Frazier
Commission Counsel
Arkansas Public Service Commission
1000 Center Street
P.O. Box 400
Little Rock, AR 72201-4314
Telephone: (501) 682-5766
E-mail: luke.kinder@arkansas.gov
Footnotes
[fn:1] 18 C.F.R. § 385.212.
[fn:2] See Show Cause Order at P 113 (noting that the Commission preliminarily found that MISO’s existing Tariff “may be unjust and unreasonable because it does not provide generator interconnection study procedures and services that account for the operational dynamics of serving electrically proximate large loads.”).