ER27-25-000 · 2026-10-23 · Individual No Affiliation

Protest of Anna Farrar re Midcontinent Independent System Operator, Inc’s filing to establish the Large Load Addition Resource Study

Text extracted from the eLibrary original (SHA-256 19ec541c44ce6dc0…). Download the original from the official source.

Contents · 6 sections
  1. I. THE PROPOSAL INCLUDES MEANINGFUL SAFEGUARDS p. 1
  2. II. MISO IDENTIFIES A DISTINCT RISK FROM OVERLAPPING STUDIES p. 2
  3. III. PROJECT CLASSIFICATION IS NOT THE SAME AS VERIFIED COST p. 3
  4. IV. MISSOURI RECORDS SHOW MULTIPLE LARGE-LOAD STUDIES AND p. 4
  5. V. THE SEPARATE COST-RECOVERY FRAMEWORK SHOULD NOT LEAVE p. 6
  6. VI. REQUESTED COMMISSION ACTION p. 7

Read topic-matched comments in ER27-25

Topics in the text: Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER27-25-000 PROTEST OF ANNA FARRAR Pursuant to Rule 211 of the Federal Energy Regulatory Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.211, I, Anna Farrar, submit this protest of specified provisions of the Large Load Addition Resource Study (LARS) tariff revisions filed by…
Read this passage Filed comments: Connecting load and generation

I. THE PROPOSAL INCLUDES MEANINGFUL SAFEGUARDS

printed heading

ER27-25-000 2 MISO also proposes load-study scenarios incorporating other planned load additions, and evaluates the loss of associated generation. [1] I do not allege that the proposal lacks cumulative modeling, outage analysis, or all financial protections.
Read this passage

II. MISO IDENTIFIES A DISTINCT RISK FROM OVERLAPPING STUDIES

printed heading · Topic match: Connecting load and generation

I do not claim any current unlawful charge, nor do I assume that all future MTEP expenditures must be borne exclusively by an individual large load.
Read this passage Filed comments: Connecting load and generation

III. PROJECT CLASSIFICATION IS NOT THE SAME AS VERIFIED COST

printed heading · Topic match: Cost allocation

PROJECT CLASSIFICATION IS NOT THE SAME AS VERIFIED COST CAUSATION Where the same constraint appears in both studies, the proposed tariff's BRP or Other classification may be justified by shared reliability benefits.
Read this passage Filed comments: Cost allocation

IV. MISSOURI RECORDS SHOW MULTIPLE LARGE-LOAD STUDIES AND

printed heading · Topic match: Connecting load and generation

That study likewise reported no new violations in its reviewed scenarios. [4] These are proposed loads reviewed under EPR, not demonstrated applications under LARS.
Read this passage Filed comments: Connecting load and generation

V. THE SEPARATE COST-RECOVERY FRAMEWORK SHOULD NOT LEAVE

printed heading · Topic match: Connecting load and generation

MISO states that LARS can be implemented under the present proposal without awaiting those later tariff protections.
Read this passage Filed comments: Connecting load and generation

VI. REQUESTED COMMISSION ACTION

printed heading · Topic match: Connecting load and generation

It asks for an adequately supported, reviewable federal study and cost-responsibility process.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

ER27-25-000 upon each person designated on the official email service list compiled by the Secretary of the Federal Energy Regulatory Commission for this proceeding.