ER27-25-000 · 2026-10-23 · Individual No Affiliation
Protest of Anna Farrar re Midcontinent Independent System Operator, Inc’s filing to establish the Large Load Addition Resource Study
PDF page 1
Docket No. ER27-25-0001
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc. Docket No. ER27-25-000 PROTEST OF ANNA FARRAR
Pursuant to Rule 211 of the Federal Energy Regulatory Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.211, I, Anna Farrar, submit this protest of specified provisions of the Large Load Addition Resource Study (LARS) tariff revisions filed by Midcontinent Independent System Operator, Inc. (MISO) on October 2, 2026, Docket No. ER27-25-000 (Accession No. 20261002-5074). [1] This protest concerns the proposed federal tariff process, not authorization of any particular Missouri development. I reside in Warren County, Missouri, and receive residential electric service from Ameren Missouri (Union Electric Company). I support reliable and efficient review of large loads and associated generation. My objection is to accepting a new accelerated process without sufficient explanation of the financial consequences of transmission constraints attributable to overlapping study assumptions and the treatment of upgrades identified later.
I. THE PROPOSAL INCLUDES MEANINGFUL SAFEGUARDS
The October 2 proposed clean tariff, Attachment X § 3.12.4, distinguishes mitigation identified only through generation-interconnection studies from mitigation identified through transmission or common study results. The former is assigned as a Generator Interconnection Project (GIP); the latter is classified as a Baseline Reliability Project (BRP) or Other project under applicable tariff rules. Attachment X § 3.12.7.4 addresses specified continuing obligations for assigned upgrades if the generator or associated large load withdraws. [1]
PDF page 2
Docket No. ER27-25-0002
MISO also proposes load-study scenarios incorporating other planned load additions, and evaluates the loss of associated generation. [1] I do not allege that the proposal lacks cumulative modeling, outage analysis, or all financial protections. The narrower question is whether these provisions adequately address additional transmission upgrades that are first identified through a subsequent planning cycle because two separate studies relied on overlapping available capacity.
II. MISO IDENTIFIES A DISTINCT RISK FROM OVERLAPPING STUDIES
MISO's transmittal letter discusses a potential overallocation of available transmission capacity between the LARS process and the existing Definitive Planning Phase (DPP) generator-interconnection process. It contemplates addressing resulting constraints through a subsequent MISO Transmission Expansion Plan (MTEP) project, with the cost assigned under existing tariff mechanisms, likely to load in the affected Transmission Pricing Zone. Drake characterizes the risk of overallocation as minimal. Transmittal Letter at 13; Drake Testimony at 33. [1]
In the supporting prepared testimony, Christina Drake explains that the overlapping LARS and DPP projects could proceed without additional charges arising from that overallocation, while the constraint is addressed through later transmission planning. Drake Testimony at 33 (combined filing PDF at 1511). [1]
This is a concrete concern about cost causation and the reasonableness of the proposed procedure. I do not claim any current unlawful charge, nor do I assume that all future MTEP expenditures must be borne exclusively by an individual large load. A later upgrade may provide identifiable benefits to the wider network. But MISO should explain why the costs associated with reconciling overlapping study assumptions would appropriately fall on the affected pricing zone instead of being attributed, in whole or in part, to the projects whose concurrent studies created the conflict.
PDF page 3
Docket No. ER27-25-0003
FERC has separately identified the lack of public transparency regarding large-load network upgrades and the risk that costs of unbuilt or undersubscribed large loads may shift to other transmission customers. The Commission's findings in its June 18, 2026 Section 206 show-cause order are preliminary; this protest does not present them as a final adjudication of any LARS cost allocation. EL26-70-000, 195 FERC ¶ 61,212, at paragraphs 71-83. [2]
III. PROJECT CLASSIFICATION IS NOT THE SAME AS VERIFIED COST
CAUSATION
Where the same constraint appears in both studies, the proposed tariff's BRP or Other classification may be justified by shared reliability benefits. It does not, by itself, answer which portion of an upgrade is attributable to the new load, the associated generation, or an independently existing reliability need. Attachment X § 3.12.4. [1] The Commission should require MISO to identify what records and comparison studies will be available to substantiate causation: the relevant with-load and without-load assumptions, the effects of associated generation, the scope and estimated costs of incremental upgrades, the affected pricing zones, the governing allocation rules, and any contributions or credits that prevent double recovery. Such information would allow regulators and transmission customers to examine both legitimate shared benefits and potential unjustified cost shifting.
PDF page 4
Docket No. ER27-25-0004
IV. MISSOURI RECORDS SHOW MULTIPLE LARGE-LOAD STUDIES AND
NETWORK CHANGES
MISO's April 7, 2025 Expedited Project Review (EPR) for Project P50616 documents a proposed 200-MW data-center load at Ameren's Rootbeer 345-kV substation, possible future expansion, and an estimated $5 million project cost. MISO reported no new reliability violations in the studied scenarios. [3] MISO's February 5, 2024 EPR for P50086 documents a separate proposed 250-MW data-center load at Montgomery's 161-kV facilities and names Navier, Inc. as the customer. That study likewise reported no new violations in its reviewed scenarios. [4] These are proposed loads reviewed under EPR, not demonstrated applications under LARS.
The facilities are electrically connected, rather than simply nearby on a map. Ameren witness Justin D. Wenk identifies the existing Montgomery-Rootbeer 345-kV line and describes relocating its terminal as part of the proposed Montgomery-Callaway Connector work in Missouri PSC File No. EA-2026-0058. Wenk Direct Testimony at 4. [5] Ameren witness Steven M. Wills separately explains that Rootbeer was originally developed for the Split Rail solar interconnection, before the large-load proposals, and states Ameren's expectation that large-load retail revenues would contribute toward shared network transmission expenses. The Split Rail interconnection agreement allocated the cost of a reserved future Rootbeer terminal to the entity creating the need for it. Wills Surrebuttal at 15-16; Schedule SMW-S1, original Sheet 88. [6] The Montgomery-Callaway Connector's stated generation-related purpose should not be conflated with proven data-center cost causation.
The scale of the evolving network is also documented by MISO. Its November 4, 2025 EPR results identify a 1,000-MW load at the planned Elkhorn substation (P50737) and a 400-MW load at Yoshi (P50738), with proposed 345-kV connections involving Lumberjack, the Odyssey-Montgomery corridor, and Scarlet. MISO's Elkhorn study
PDF page 5
Docket No. ER27-25-0005
identified two corrective-action projects, including P51113, a $5 million Baseline Reliability Project proposal to upgrade Montgomery 345-kV terminal equipment to 4,000 amperes following identified thermal observations. MISO recommended advancement into MTEP26 Appendix A. This is evidence of studied mitigation needs, not proof that these facilities are built or that the proposed projects have been granted final approval. [8]
Ameren Missouri's October 19, 2026 Crossroads Connector announcement identifies a further approximately 22 miles of proposed double-circuit 345-kV transmission in Warren and Montgomery counties. Phase 1 would link Lumberjack to the
Montgomery-Callaway corridor; Phase 2 would link a new Float substation west of Warrenton with the Nightingale and Lumberjack substations. Ameren expressly describes the project as intended to meet anticipated nearby data-center demand. Ameren says those customers pay direct interconnection costs up front and that it will seek future Missouri PSC approval for rates covering the remaining Crossroads costs. Those are Ameren's representations and proposed future rate treatment, not a final determination that all project costs have been recovered or assigned. [9]
Together, these official records establish an expanding set of major load additions, planned transmission paths, and at least one specifically identified load-study corrective action. Their relevance here is methodological: MISO should explain how LARS preserves consistent cumulative assumptions across EPR, DPP, and MTEP, distinguishes existing or generation-driven facilities from incremental large-load-driven costs, and retains the evidence needed to attribute later upgrades appropriately. I do not claim that the named Missouri projects are LARS applicants, that all planned lines form a completed operational loop, or that every shared transmission improvement was caused by data centers.
PDF page 6
Docket No. ER27-25-0006
V. THE SEPARATE COST-RECOVERY FRAMEWORK SHOULD NOT LEAVE
A GAP
MISO's transmittal letter anticipates a further Section 205 filing concerning pro forma large-load cost-recovery protections by November 16, 2026. MISO states that LARS can be implemented under the present proposal without awaiting those later tariff protections. The proposal also addresses the availability of later Affected System study results. Transmittal Letter at 14 n.66; Attachment X § 3.12.4. [1] An anticipated future filing cannot itself establish enforceable obligations in this docket.
MISO should explain whether the proposed withdrawal and assigned-project obligations extend to constraints and upgrades caused by study overallocation but identified only through a later MTEP cycle; which transmission customer or generator bears such obligations; when financial security becomes binding; and how state retail charges and federal transmission recovery will be reconciled to avoid duplicate collections and financial gaps.
Missouri PSC File No. ET-2025-0184 contains an approved Ameren Missouri large-load rate plan. [7] That retail tariff does not by its existence prove that every shared, federally jurisdictional MISO transmission obligation is secured from the ultimate large-load customer. This concern parallels FERC's preliminary findings on transparency and large-load cost-recovery agreements in EL26-70-000. [2]
PDF page 7
Docket No. ER27-25-0007
VI. REQUESTED COMMISSION ACTION
I respectfully request that the Commission: (1) require MISO to substantiate its assessment that the risk of LARS/DPP transmission-capacity overallocation is minimal and explain who would bear resulting MTEP costs; (2) require an explanation of how LARS models previously reviewed EPR loads and planned network changes affecting shared facilities, and a transparent basis for identifying and allocating later-discovered upgrades, including projects classified as BRP or Other; (3) explain the binding effect and timing of any cost-recovery security, the treatment of later Affected System obligations, and credits needed to avoid double recovery; and (4) require an adequate explanation or appropriate tariff changes before accepting the proposal without conditions, or take such other action as permitted under Section 205 of the Federal Power Act.
This protest does not ask FERC to reassign the entire cost of any named Missouri transmission facility to a data-center developer or to determine Missouri retail rates. It asks for an adequately supported, reviewable federal study and cost-responsibility process.
Respectfully submitted,
/s/ Anna Farrar
Anna Farrar
Individual Protestant, appearing pro se
P.O. Box 161
Warrenton, MO 63383
Email for service: anna.farrar@wccrd.com
Telephone: 636-235-6889
October 23, 2026
PDF page 8
Docket No. ER27-25-0008
AUTHORITIES AND PRIMARY RECORDS
[1] MISO, Large Load Addition Resource Study (LARS) Section 205 Tariff Filing, Docket ER27-25-000, Oct. 2, 2026, Accession No. 20261002-5074, Transmittal Letter at 12-14, proposed clean Attachment X §§ 3.12.4, 3.12.6, 3.12.7.4 and Prepared Direct Testimony of Christina Drake at
33. FERC official filing record; MISO filing PDF.
[2] FERC, Order Instituting Proceeding Under Section 206 of the Federal Power Act, Docket EL26-70-000, 195 FERC ¶ 61,212 (June 18, 2026), especially ¶¶ 71-83 (preliminary findings on transparency and cost shifting). Official order PDF.
[3] MISO, New Rootbeer 345 kV Load Addition, Project P50616, CTSTF presentation, Apr. 7, 2025, slides 2-4. Primary MISO presentation.
[4] MISO, AmerenMO Montgomery 161 kV Substation Load Addition, Project P50086, CSPM presentation, Feb. 5, 2024, slides 2-5. Primary MISO presentation.
[5] Missouri PSC, File EA-2026-0058, Justin D. Wenk, Direct Testimony (Nov. 10, 2025), printed pp. 2, 4 (PDF pp. 4, 6). Official PSC testimony.
[6] Missouri PSC, File EA-2025-0238, Steven M. Wills, Surrebuttal Testimony (Jan. 16, 2026), printed pp. 15-16, and Schedule SMW-S1, original Sheet 88. Official PSC testimony and agreement excerpt.
[7] Missouri PSC, File ET-2025-0184, Order Regarding Ameren Missouri's Request for Approval of a Large Load Rate Plan and Associated Variance (Nov. 24, 2025; effective Dec. 4, 2025). Official docket.
[8] MISO, Expedited Project Review Results and MISO Recommendation (Nov. 4, 2025), slides 20-23 and 25-26 (P50737, P51113, P50738). MISO EPR results, official PDF.
[9] Ameren Missouri, Ameren Missouri to Host Open Houses for Transmission Project in Montgomery and Warren Counties (Oct. 19, 2026), Crossroads Connector description, phases, and stated proposed cost-recovery treatment. Ameren official release.
PDF page 9
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc.
Docket No. ER27-25-000
CERTIFICATE OF SERVICE
I hereby certify that on October 23, 2026, I served a copy of the foregoing Protest of Anna Farrar in Docket No. ER27-25-000 upon each person designated on the official email service list compiled by the Secretary of the Federal Energy Regulatory Commission for this proceeding. Service was made by electronic mail, in three separate batches, to all 120 unique email addresses included in the service list downloaded for this proceeding.
Dated October 23, 2026.
/s/ Anna Farrar
Anna Farrar
Individual Protestant, appearing pro se