ER26-3537-000 · 2026-08-17 · PJM Transmission Owners

PJM Transmission Owners' partial compliance filing implementing the Interim NITS rate

The PJM Transmission Owners file a partial compliance filing under the June 18 co-location order, adding tariff records that set the Interim NITS rate, and request a July 1, 2028 effective date.

Asks FERC to: Accept the partial compliance filing without hearing, modification or condition, effective July 1, 2028.

Carries out the E-2 order's new co-location services by filing the Interim NITS rate, ahead of the November 16 date that aligns with PJM's E-7 show cause response.

E-2 PJM: Interim NITS (P 2, p. 3) E-2 PJM: One of three new co-location services (P 2, p. 3)

Key points

  1. The filing implements the rate for Interim Network Integration Transmission Service ordered on June 18.
    the PJM Transmission Owners are submitting new and revised tariff records to the PJM Open Access Transmission Tariff PDF p. 1
  2. The three new services are Interim NITS, firm contract demand and non-firm contract demand transmission service.
    The new transmission services are: Interim NITS, firm contract demand transmission service, and non-firm contract demand transmission service. PDF p. 1
  3. FERC granted a 90-day extension to November 16, 2026, but PJM committed to file Interim NITS provisions on August 17.
    Notwithstanding its request for extension, PJM committed to submit a compliance filing on August 17, 2026, addressing several compliance directives, including those related to Interim NITS. PDF p. 2
  4. New Part XI sections 706 and 706.1 set the Interim NITS rate, with two new definitions.
    New Sections 706 and 706.1 specify the Interim NITS rate. PDF p. 2
  5. The owners request a July 1, 2028 effective date.
    The PJM Transmission Owners request that the revisions submitted with this partial compliance filing become effective on July 1, 2028. PDF p. 2
  6. They note the directives are under challenge and the tariff sheets may face a termination filing.
    the tendered tariff sheet revisions herein may be subject to a subsequent termination filing. PDF p. 1
Contents · 7 sections
  1. I. DESCRIPTION OF COMPLIANCE FILING p. 1
  2. II. Effective Date p. 2
  3. III. Additional Information p. 2
  4. A. Communications p. 2
  5. B. List of Documents Submitted with Filing p. 3
  6. C. Service p. 3
  7. IV. Conclusion p. 4

Topics in the text: Cost allocation

What the document says

PDF p. 2

The PJM TOs file the Interim NITS rate, effective July 1, 2028 to match PJM.

attached to this filing are new and revised tariff records for the PJM Tariff necessary to implement the rate for Interim NITS PDF p. 2

PDF p. 2

The PJM TOs file the Interim NITS rate, effective July 1, 2028 to match PJM.

The PJM Transmission Owners request that the revisions submitted with this partial compliance filing become effective on July 1, 2028. PDF p. 2

PDF p. 1

The TOs flag the Interim NITS rate may be terminated because FERC's directives are challenged.

the Commission’s directives being complied with herein are under challenge before the Commission and through petitions for review, such that the tendered tariff sheet revisions herein may be subject to a subsequent termination filing PDF p. 1

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

Suite 500 East 1301 K Street NW Washington, D.C. 20005-3317 August 17, 2026 Honorable Debbie-Anne A.
Read this passage

I. DESCRIPTION OF COMPLIANCE FILING

printed heading · Topic match: Cost allocation

On August 14, 2026, the Commission granted these extension requests.
Read this passage

II. Effective Date

PDF bookmark

EFFECTIVE DATE The PJM Transmission Owners request that the revisions submitted with this partial compliance filing become effective on July 1, 2028.
Read this passage

III. Additional Information

PDF bookmark

III.
Read this passage

A. Communications

PDF bookmark

Communications Communications regarding this filing should be addressed to the following individuals, whose names should be entered on the official service list maintained by the Secretary for this proceeding. 5 PJM Extension Motion at 1-2. 3 Pulin Shah Vice President of Transmission Development…
Read this passage

B. List of Documents Submitted with Filing

PDF bookmark

List of Documents Submitted with Filing In addition to this transmittal letter, this filing includes the following attachments: • Attachment A: Clean Tariff Records for the PJM Tariff • Attachment B: Redlined Tariff Records for the PJM Tariff
Read this passage

C. Service

PDF bookmark

Service PJM has served a copy of this filing on all PJM Members and on all state utility regulatory commissions in the PJM Region by posting this filing electronically.
Read this passage

IV. Conclusion

PDF bookmark

CONCLUSION For the reasons stated herein, the PJM Transmission Owners respectfully request that the Commission accept this partial compliance filing without hearing, modification or condition.