EL26-68-000 · 2026-06-18 · FERC

SPP show cause order

Contents · 31 sections
  1. D. Extending New Transmission Services to Eligible Customers Taking Service on p. 2
  2. I. Background p. 7
  3. A. Growth of Large and Co-Located Loads and ANOPR p. 7
  4. B. Recent Proceedings Addressing Large and Co-Located Loads p. 11
  5. 1. PJM Co-Location Proceedings p. 12
  6. 2. SPP High Impact Large Load and High Impact Large Load Generation Assessment Processes p. 14
  7. 3. SPP Conditional High Impact Large Load Service p. 16
  8. II. SPP’s Existing Processes p. 17
  9. A. Existing Tariff Processes p. 17
  10. B. Recent Stakeholder Proceedings in SPP p. 20
  11. III. Discussion p. 21
  12. A. Transmission Service to Eligible Customers on Behalf of Large Loads p. 23
  13. 1. Jurisdiction p. 24
  14. 2. Tariff Provisions p. 27
  15. B. Cost Shifting Risk Among Transmission Customers p. 30
  16. 1. Jurisdiction p. 30
  17. 2. Additional Cost Transparency p. 32
  18. 3. Cost Recovery Agreements p. 36
  19. C. Co-Location Arrangements and Load with Behind the Meter Generation p. 40
  20. 1. Definition p. 41
  21. 2. Jurisdiction p. 42
  22. 3. Tariff Provisions p. 42
  23. D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads p. 47
  24. E. Informational Report p. 49
  25. IV. Briefing Questions p. 51
  26. I. Overview of Today’s Orders p. 81
  27. II. The Commission Needs Good Records to Ensure Reasoned Decision-Making p. 82
  28. III. The Commission Needs to Pursue Meaningful Customer Protection p. 83
  29. IV. The Commission Needs to Understand the Implications of Extending New Transmission Services to Additional Loads and Regions p. 85
  30. V. The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies p. 86
  31. VI. Conclusion p. 86

Read topic-matched comments in EL26-68

Topics in the text: Cost allocation · Connecting load and generation · Filing procedure

Elsewhere in the record

Other parties on the same questions, in their own documents.

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

195 FERC ¶ 61,213 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Laura V.
Read this passage

D. Extending New Transmission Services to Eligible Customers Taking Service on

printed heading · Topic match: Connecting load and generation

See infra P 15. 8 We note that SPP’s Tariff does not have a formal definition of “co-located load” or “co-location arrangement.” As discussed below, for the purposes of HILLGA, the generating facility only must be in close electrical proximity.
Read this passage

I. Background

PDF bookmark

I.
Read this passage

A. Growth of Large and Co-Located Loads and ANOPR

PDF bookmark · Topic match: Cost allocation

EL26-68-000 - 9 - that it was clear that additional “action is warranted to support further progress where it is needed.”24 In response to the ANOPR, SPP states that it is facing significant operational, planning, and market challenges in response to unprecedented growth in large and non-…
Read this passage

B. Recent Proceedings Addressing Large and Co-Located Loads

PDF bookmark · Topic match: Filing procedure

It is in this context, and in recognition of SPP’s recent reforms to implement a new process for studying requests for Eligible Customers taking transmission service on behalf of large loads and a new conditional, non-firm transmission service for Eligible Customers taking transmission service on…
Read this passage Filed comments: Filing procedure

1. PJM Co-Location Proceedings

PDF bookmark · Topic match: Connecting load and generation

PJM Co-Location Proceedings On February 20, 2025, the Commission initiated a show cause proceeding against PJM and the PJM transmission owners regarding the lack of tariff provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to…
Read this passage Filed comments: Filing procedure

2. SPP High Impact Large Load and High Impact Large Load Generation Assessment Processes

PDF bookmark · Topic match: Connecting load and generation

P 32 (explaining that SPP will grant HILLGA customers a new type of interconnection service, load limited resource interconnection service, which grants limited interconnection service solely to serve the associated HILL). 58 Id.
Read this passage

3. SPP Conditional High Impact Large Load Service

PDF bookmark · Topic match: Reliability and curtailment

P 64. 64 SPP CHILLS Order, 195 FERC ¶ 61,196 at P 1. 65 Id.
Read this passage

II. SPP’s Existing Processes

PDF bookmark

II.
Read this passage

A. Existing Tariff Processes

PDF bookmark · Topic match: Connecting load and generation

Pursuant to the Tariff, an interconnection customer may request, and SPP may provide, interim interconnection service prior to the completion of requisite Interconnection Facilities, Network Upgrades, Distribution Upgrades, or System Protection Facilities.89 The scope of the interim availability…
Read this passage

B. Recent Stakeholder Proceedings in SPP

PDF bookmark · Topic match: Connecting load and generation

As such, and as the Commission explained in the April Order Regarding Intent to Act, we find that the Commission must now take further action to ensure that SPP promptly proposes revisions to ensure that its Tariff remains just and reasonable.
Read this passage

III. Discussion

PDF bookmark · Topic match: Filing procedure

We emphasize that we will not grant such abeyances reflexively, that any abeyance will be limited to 90 days, and that we will look with great disfavor toward requests to extend the abeyance period.
Read this passage Filed comments: Filing procedure

A. Transmission Service to Eligible Customers on Behalf of Large Loads

PDF bookmark · Topic match: Filing procedure

Transmission Service to Eligible Customers on Behalf of Large Loads As noted above, the Commission recently approved revisions to SPP’s Tariff that established an enhanced process for SPP to study the provision of transmission service to Eligible Customers on behalf of HILLs and help to ensure that…
Read this passage Filed comments: Filing procedure

1. Jurisdiction

PDF bookmark · Topic match: Retail and wholesale authority

Specifically, we find that it is within the Commission’s exclusive authority to ensure that transmission provider and/or transmission owner tariffs include sufficiently clear and consistent provisions governing how transmission service to Eligible Customers on behalf of large loads interconnecting…
Read this passage

2. Tariff Provisions

PDF bookmark · Topic match: Cost allocation

This transparency and informational requirement is warranted for the regulatory scheme we are establishing for transmission service requests by Eligible Customers on behalf of large loads given demand from and the expedited development timelines for large load customers.
Read this passage

B. Cost Shifting Risk Among Transmission Customers

PDF bookmark · Topic match: Cost allocation

Cost Shifting Risk Among Transmission Customers We next preliminarily find that SPP’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers, which may result in unjust and unreasonable rates for…
Read this passage

1. Jurisdiction

PDF bookmark · Topic match: Cost allocation

To fulfill its responsibility to ensure that transmission rates are just and reasonable, the Commission must act to address the risk of cost shifting among transmission customers due to (1) the process transmission providers and/or transmission owners use to evaluate the facilities needed, and the…
Read this passage

2. Additional Cost Transparency

PDF bookmark · Topic match: Cost allocation

As an initial matter, we note that SPP has taken numerous steps to connect large loads to the transmission system in a reliable and expeditious manner and to enhance its study and operational requirements related to provision of transmission service to Eligible Customers on behalf of large…
Read this passage

3. Cost Recovery Agreements

PDF bookmark · Topic match: Cost allocation

EL26-68-000 - 37 - entity taking wholesale transmission service and its retail customers, it fails “to provide any mechanism to protect other wholesale transmission customers” from stranded transmission costs.130 The Kansas Commission states that while its Large Load Power Services rate plan that…
Read this passage

C. Co-Location Arrangements and Load with Behind the Meter Generation

PDF bookmark · Topic match: Connecting load and generation

See infra P 72. 139 PJM Co-Location Order, 193 FERC ¶ 61,217 at P 2; PJM Co-Location Rehearing Order, 195 FERC ¶ 61,209 at PP 91, 102. 140 We note that SPP does not allow Eligible Customers taking transmission service on behalf of loads with behind the meter generation to reduce their transmission…
Read this passage Filed comments: Filing procedure

1. Definition

PDF bookmark · Topic match: Connecting load and generation

Definition The PJM Co-Location Order adopted the following definition of co-located load: a “configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of…
Read this passage Filed comments: Filing procedure

2. Jurisdiction

PDF bookmark · Topic match: Connecting load and generation

As we explained in the PJM Co-Location Order, states retain exclusive authority over the specific terms of retail sales and retail rate design, including retail cost allocation to the co-located load; which entities are legally permitted to provide electricity to retail customers in co-location…
Read this passage

3. Tariff Provisions

PDF bookmark · Topic match: Connecting load and generation

Additionally, in the PJM Co-Location Order, the Commission found that it was necessary to clarify that interconnection customers seeking to use new generating facilities to serve co-located load may (1) request interconnection service at a level below the generating facility’s maximum facility…
Read this passage Filed comments: Filing procedure

D. Extending New Transmission Services to Eligible Customers Taking Service on Behalf of Flexible Large Loads

PDF bookmark · Topic match: Filing procedure

Finally, we note that the Commission has found it just and reasonable that, in order for an Eligible Customer to take interim NITS, firm contract demand transmission service, and non-firm contract demand transmission service, an Eligible Customer must have necessary control technologies and/or…
Read this passage Filed comments: Filing procedure

E. Informational Report

PDF bookmark · Topic match: Reliability and curtailment

In particular, SPP’s HILLGA process and Expedited Resource Adequacy Study (ERAS) process provide generator interconnection customers the opportunity to be studied and interconnect to SPP’s transmission system more quickly in order to help ensure load serving entities are able to meet resource…
Read this passage Filed comments: Filing procedure

IV. Briefing Questions

PDF bookmark · Topic match: Cost allocation

We find that there may be a variety of possible approaches to protect customers from significant cost shifts associated with Network Upgrades triggered by large loads.
Read this passage Filed comments: Filing procedure

I. Overview of Today’s Orders

PDF bookmark · Topic match: Cost allocation

Overview of Today’s Orders In each of today’s orders to show cause, the Commission identifies a series of issues raised by the ongoing growth of large loads, directs briefing on whether existing tariffs remain just and reasonable in light of those developments, and describes possible solutions to…
Read this passage

II. The Commission Needs Good Records to Ensure Reasoned Decision-Making

PDF bookmark

The Commission Needs Good Records to Ensure Reasoned Decision-Making I first want to emphasize that the Commission needs active participation from interested stakeholders to develop thorough records in each region.
Read this passage

III. The Commission Needs to Pursue Meaningful Customer Protection

PDF bookmark · Topic match: Cost allocation

As we develop the new infrastructure, many have raised concerns about whether these costs are being fairly assigned to new and existing customers, whose benefits must be commensurate with the costs they pay.
Read this passage

IV. The Commission Needs to Understand the Implications of Extending New Transmission Services to Additional Loads and Regions

PDF bookmark · Topic match: Cost allocation

While it is important to identify innovative solutions that can adapt to the needs of the system, the Commission and grid operators must also be careful not to implement changes that create unforeseen reliability risks.
Read this passage

V. The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies

PDF bookmark

The Orders Recognize the Importance of Evaluating Advanced Transmission Technologies Lastly, today we preliminarily find that each RTO/ISO’s tariff is unjust and unreasonable because the tariff lacks clear and consistent provisions requiring the evaluation of alternative transmission technologies…
Read this passage

VI. Conclusion

PDF bookmark · Topic match: Cost allocation

While this is a long journey, even so, we must continue to move at breakneck pace to win the AI race.