EL26-67-000 · 2026-07-08 · Individual No Affiliation

Supplemental Technical Comment of L.M. Marlowe on the integration of large, high-density electric loads and the associated reliability, observability, and cost-allocation methodologies under consideration by the Commission

An individual commenter filing as L.M. Marlowe submits a supplemental technical comment across the six show cause dockets, urging boundary telemetry, cost-causation allocation and a four-gate verification standard at the point of interconnection, and reserves rights in her framework.

Asks FERC to: Consider continuous boundary telemetry and a four-gate verification standard in the large-load interconnection and cost-allocation methods, and note the commenter's reservation of intellectual property rights.

Comment filed in EL26-67 and the other show cause dockets; its cost-causation and observability proposals bear on the cost-shifting and transparency directives and curtailment questions raised by the June orders.

E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: Cost transparency (P 71, p. 51) E-7 PJM: Service for flexible loads (P 85, p. 56)

Key points

  1. She argues reliability checks should move from periodic review to continuous validation at the interconnection boundary, since large computational loads change state in sub-cycle time.
    reliability verification should migrate from periodic review toward continuously operating validation performed at the interconnection boundary, sampled at sub-cycle resolution PDF p. 3
  2. Reliability burdens from large computational loads should be assigned to the loads that cause them, not to residential and small-commercial ratepayers.
    should be assigned to the loads that cause them, on a cost-causation basis, rather than socialized onto residential and small-commercial ratepayers. PDF p. 4
  3. She asks whether curtailment priority could place federally directed computational load ahead of ordinary large loads, citing DOE's 15-minute backup-generation curtailment of loads of 50 MW or more.
    directed curtailment of data centers and large loads of 50 MW or greater onto backup generation within fifteen minutes of an emergency signal PDF p. 4
  4. She proposes four verification gates at the point of common coupling: timing and stability, dependency map, throughput settlement, and certification.
    Such a standard would operate as a sequence of verification gates applied at interconnection, each addressing a specific consideration raised in this comment PDF p. 7
  5. The commenter reserves rights in a proprietary framework covered by pending patent applications.
    Commenter reserves all rights, including the right to seek appropriate relief in the proper forum. PDF p. 9
Contents · 17 sections
  1. I. Interest of the Commenter p. 1
  2. II. Documented Priority — Diagnostic-to-Action Correlation p. 2
  3. III. Technical Considerations for the Commission p. 3
  4. A. From periodic review to continuous validation. p. 3
  5. B. Observability beyond consumption — high-resolution boundary telemetry. p. 3
  6. C. Embedded reliability boundaries and machine-speed corrective action. p. 3
  7. D. Execution sovereignty and software common-mode risk. p. 3
  8. E. Dependency mapping and hidden burden. p. 4
  9. F. Cost-causation. p. 4
  10. G. Curtailment priority and observability of federally-accelerated computational load. p. 4
  11. H. Unpriced resource consumption and diffuse externalized costs. p. 4
  12. I. Transparency and the orientation of the just and reasonable standard. p. 5
  13. IV. Toward a Resolution — Verification at the Point of Interconnection p. 7
  14. III. It certifies, against the full set of boundary invariants, whether the load can ramp, curtail, and operate p. 8
  15. V. Relationship to the Current Record and Pending Deadlines p. 8
  16. VI. Reservation of Rights p. 9
  17. VII. Conclusion p. 9

Read topic-matched comments in EL26-67

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 6.

Opening text

opening text · Topic match: Cost allocation

It is offered for the public benefit — to improve grid reliability, transparency in large-load cost allocation, and the protection of ratepayers from systemic waste and undue cost- shifting.
Read this passage Filed comments: Cost allocation

I. Interest of the Commenter

printed heading · Topic match: Cost allocation

Commenter’s object in these proceedings is that the reliability of the system be protected and that the costs of large computational load be borne by those who cause them rather than by residential and small-commercial ratepayers; Commenter submits this comment in good faith and in furtherance of…
Read this passage Filed comments: Cost allocation

II. Documented Priority — Diagnostic-to-Action Correlation

printed heading · Topic match: Cost allocation

Documented Priority — Diagnostic-to-Action Correlation Commenter reported the specific conditions now before the Commission and the reliability community beginning January 17, 2026 — months before the corresponding federal actions.
Read this passage Filed comments: Cost allocation

III. Technical Considerations for the Commission

printed heading

Technical Considerations for the Commission Commenter respectfully submits the following considerations, each corresponding to matters already before the Commission and the reliability community.
Read this passage

A. From periodic review to continuous validation.

printed heading

Existing reliability mechanisms are predominantly retrospective — periodic reviews, seasonal assessments, and post-event investigations operating on intervals measured in weeks or quarters.
Read this passage

B. Observability beyond consumption — high-resolution boundary telemetry.

printed heading

Observability beyond consumption — high-resolution boundary telemetry.
Read this passage

C. Embedded reliability boundaries and machine-speed corrective action.

printed heading · Topic match: Reliability and curtailment

Consideration should be given to whether interconnection requirements should include automated, boundary-resident reliability functions — continuous invariant monitoring against defined tolerances, automated throttling or curtailment triggered when a measured quantity exceeds its bound, and…
Read this passage Filed comments: Reliability and curtailment

D. Execution sovereignty and software common-mode risk.

printed heading

Consideration should be given to whether interconnection study must characterize software and orchestration dependency — execution sovereignty — as a distinct common-mode risk alongside physical redundancy, and to whether the concentration of load behind shared control planes should be a studied…
Read this passage

E. Dependency mapping and hidden burden.

printed heading

Traditional planning methodologies quantify capacity; future methodologies may need to characterize dependency — between facilities, orchestration systems, cloud environments, regions, and execution pathways — including which facilities share identical software assumptions, which execution pathways…
Read this passage

F. Cost-causation.

printed heading · Topic match: Cost allocation

The reliability burdens created by large computational loads — including the burdens arising from the observability, validation, and dependency considerations above — should be assigned to the loads that cause them, on a cost-causation basis, rather than socialized onto residential and…
Read this passage Filed comments: Cost allocation

G. Curtailment priority and observability of federally-accelerated computational load.

printed heading · Topic match: Reliability and curtailment

Consideration should be given to how curtailment priority is to be ordered where federally-directed or security-associated computational load may qualify for exemptions available to critical facilities — such that it could sit ahead of, rather than behind, ordinary large loads in a curtailment…
Read this passage Filed comments: Reliability and curtailment

H. Unpriced resource consumption and diffuse externalized costs.

printed heading · Topic match: Cost allocation

Unpriced resource consumption and diffuse externalized costs.
Read this passage Filed comments: Cost allocation

I. Transparency and the orientation of the just and reasonable standard.

printed heading · Topic match: Cost allocation

The Commission’s authority under the Federal Power Act was established to protect consumers and to ensure that rates are just and reasonable, and cost causation is the foundation of that standard.
Read this passage Filed comments: Cost allocation

IV. Toward a Resolution — Verification at the Point of Interconnection

printed heading

Toward a Resolution — Verification at the Point of Interconnection The considerations above describe a common difficulty: the Commission is directed to ensure just and reasonable rates, reliability, and cost-causation for large computational loads whose behavior and costs it may be structurally…
Read this passage

III. It certifies, against the full set of boundary invariants, whether the load can ramp, curtail, and operate

printed heading

It certifies, against the full set of boundary invariants, whether the load can ramp, curtail, and operate flexibly while remaining within the accepted stability envelope — that is, whether its timing (Gate I), its dependency profile (Gate II), and its throughput reconciliation (Gate III) together…
Read this passage

V. Relationship to the Current Record and Pending Deadlines

printed heading · Topic match: Cost allocation

Commenter notes that the substance of these considerations — including intent-aware observability, continuous validation, software common-mode exposure, and dependency-based cost allocation — was authored and publicly timestamped prior to the actions now under consideration, and respectfully…
Read this passage Filed comments: Cost allocation

VI. Reservation of Rights

printed heading

Reservation of Rights Commenter has authored and publicly timestamped a proprietary diagnostic, observability, and stability framework and holds pending United States Patent and Trademark Office applications relating thereto (USPTO Serial Nos. 99598875, 99600821, 99613073, 99717240, 99729215, and…
Read this passage

VII. Conclusion

printed heading

Conclusion For the foregoing reasons, Commenter respectfully requests that the Commission consider these technical considerations in the above-captioned proceedings and take note of the reservation of rights stated herein.
Read this passage