EL26-67-001 · 2026-07-20 · Exelon Corporation, The FirstEnergy Transmission Companies

Exelon Corporation and FirstEnergy Service Company submit Request for Rehearing of the 06/18/2026 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)

Docket No. EL26-67-000

REQUEST FOR REHEARING OF EXELON CORPORATION AND
FIRSTENERGY SERVICE COMPANY

Pursuant to Federal Power Act (“FPA”) section 3131 and Rule 7132 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), Exelon Corporation3 and FirstEnergy Service Company4 (together “Exelon and FirstEnergy”) request rehearing of the Commission’s June 18 Order Instituting Proceeding Under Section 206 of the Federal Power Act (“Show Cause Order”)5 insofar as the Commission found that PJM’s Open Access Transmission Tariff (“PJM Tariff”) appears to be unjust and unreasonable without new transmission services that would be available to “large load” customers, specifically what the Show Cause Order refers to as “flexible large loads.”6  The Commission’s findings that the PJM Tariff appears to be unjust and unreasonable without these new transmission service options is arbitrary and capricious and not based upon reasoned decision making.

1
16 U.S.C. § 825l(a).
2
See 18 C.F.R. § 385.713.
3 Exelon Corporation submits this rehearing request on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company.
4 FirstEnergy Service Company submits this rehearing request as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”).
5 PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211 (2026).
6 See id. at P 86.

PDF page 2

2

In the Show Cause Order, the Commission preliminarily found that PJM’s Tariff appears to be unjust and unreasonable because it “does not include transmission services that reflect Eligible Customers taking transmission service on behalf of flexible large loads that are willing and able to limit their use of the transmission system under certain conditions.”7  The Commission noted that the existing transmission services in PJM consist of Network Integration Transmission Service and firm and non-firm Point-to-Point Transmission Service.  While the Commission stated that these remain just and reasonable options, the Commission directed PJM to address whether its Tariff remains just and reasonable without allowing Eligible Customers taking transmission service on behalf of “flexible large loads” the option of taking one or more of the three new transmission services that the Commission directed in its December 18, 2025 order on Co-Located Load in PJM.8

Exelon and FirstEnergy seek rehearing of these findings for the same reasons they sought rehearing of the December 18 Co-Located Load Order’s requirement to adopt these new transmission services for Co-Located Load customers.  As with the December 18 Co-Located Load Order, the purported purpose of the Commission’s findings at issue here is to improve the availability of service to new large load customers and ensure that service to such customers does not impose unnecessary costs on existing customers.  But the creation of these new forms of transmission service will not hasten or improve service and instead merely reduce transmission charges for large loads at the expense of other customers.  Requiring new transmission services for “flexible large loads” or other large load customers will not resolve any actual inadequacy in

7 Id.
8 Id. at 87 (citing PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18 Co-Located Load Order”)).  This request for rehearing refers to the proceedings addressed by the December 18 Co-Located Load Order (Docket Nos. EL25-49, et al.) as the “PJM Co-Located Load Proceedings.”

PDF page 3

3

the PJM Tariff and instead will provide an unreasonable and unduly preferential gift to a favored class.

I. Statement of Issues/Specification of Error.
In accordance with 18 C.F.R. § 385.713(c)(1) and (2), the Exelon and FirstEnergy provide the following specification of errors and statement of issues, including citations to representative Commission and judicial precedent.

1. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has Not Been Shown to Be Unjust and Unreasonable.  See 16 U.S.C. § 824e(a); Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021) (explaining that “[t]he burden of proving” that a rate is unjust or unreasonable is placed on “the party that initiated the proceeding”).

a. There is No Evidence In the Record That Flexible Large Loads or Any Other Large Loads Are Unable to Obtain Reliable, Timely, and Reasonably Priced Service Using the Existing Network Service Construct.  Therefore, the Commission Fails To Satisfy the Requirement Under the Administrative Procedure Act (“APA”) That Its Decision Be Supported With Substantial Evidence.

i. The APA requires the Commission to “examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made,’” and to base its decision on substantial evidence; because FERC has failed to do so, its decision is arbitrary and capricious.  Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co. (“State Farm”), 463 U.S. 29, 43 (1983) (citation omitted); see Fla. Gas Transmission Co. v. FERC (“Florida Gas”), 604 F.3d 636, 639 (D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y. v. NLRB, 305 U.S. 197, 229 (1938) (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

ii. The PJM Tariff provides two transmission service options (Network Integration Transmission Service and Point-to-Point Transmission Service) and includes provisions to explain how those services work and how Network Customers will be served. See PJM Tariff at §§ 31.1, 31.2, 31.3, 31.6 and 32; see also generally PJM Tariff , OATT Definitions.

PDF page 4

4

iii. To the extent that parties have argued they are unable to interconnect or are experiencing delays, that is false and any delay is of their own making.  See, e.g., Exelon Dec. 8, 2025 Comments at 3-4; Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20, at Ex. 5 Attach 1 (providing Exelon’s Nov. 12, 2024 Letter).  FERC arbitrarily and capriciously disregarded evidence that Network Service under the current tariff is feasible and has been used for co-location arrangements.  Compare PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) and PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule F, Part F.4 (June 1, 2024), with Press Release, Talen Energy, Talen Energy Expands Nuclear Energy Relationship with Amazon

(June
11,
2025),
https://ir.talenenergy.com/news-
releases/news-release-details/talen-energy-expands-nuclear- energy-relationship-amazon.  See also Exelon Dec. 8, 2025 Comments at 6.

iv. Ignoring data in the record regarding the ability of large loads to interconnect to the transmission system violates the APA and renders FERC’s decision arbitrary and capricious.  See State Farm, 463 U.S. at 43.

v. There is no evidence in the record that the cost of Network Service adversely impacts flexible large loads or any other large loads.  Nor is there evidence to support that existing Network Service imposes unnecessary upgrades on all customers.  Nor is there evidence that new forms of transmission service will allow for faster interconnection.  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

vi. The Commission has not met its burden under FPA section 206 because it acknowledges that the existing transmission services remain just and reasonable options.  See June 18, 2026 Order, 195 FERC ¶ 61,209 at P 195 (finding Network Service charged on a gross demand basis to be “one just and reasonable transmission service option”).

b. The Commission Did Not Engage in Reasoned Decision Making Because It Did Not Explain its Departure from FERC Precedent Regarding the Reasonableness of the Existing Network Service.  See F.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (“[T]he requirement that an agency provide reasoned explanation for its action

PDF page 5

5

would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); New England Power Generators Ass’n v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.”); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ and Commission cases are no exception.”) (citations omitted); Cal. Pub. Utils. Comm’n v. FERC, 879 F.3d 966, 977 (9th Cir. 2018) (“FERC departed from this policy without acknowledgment or explanation.  This departure was arbitrary and capricious.”); Sw. Airlines Co. v. FERC, 926 F.3d 851, 856 (D.C. Cir. 2019) (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . . [FERC] must at least ‘acknowledge’ its seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (most alterations in original) (citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a public utility from making or granting an “undue preference or advantage” or from maintaining “any unreasonable difference in rates, charges, service, facilities, or in any other respect, . . . as between classes of service”); TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12–13 (D.C. Cir. 2015) (remanding because FERC did not adequately explain its position).

i. The Commission has a long-standing policy of rejecting
attempts by network transmission customers to avoid paying
their load ratio share of system cost.  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237 at PP 40–41, denying clarification & addressing arguments raised on reh’g, 173 FERC ¶ 61,043 at PP 13–14 (2020); see Promoting

Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888- A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,324 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002); see also, e.g., Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005); Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power

PDF page 6

6

Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam);
Idaho Power Co., 106 FERC ¶ 61,329 (2004); Ameren Servs. Co. v.
Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010); Ariz. Pub.
Serv. Co., 151 FERC ¶ 61,191 (2015); Preventing Undue
Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh’g, Order

No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh’g, Order No.
890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-
C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D,
129 FERC ¶ 61,126 (2009).
c. Flexible Large Loads and Other Large Loads Rely Upon the Entire Embedded Transmission System to Serve Their Full Gross Load.

Therefore, FERC’s Decision is Arbitrary and Capricious Because the Embedded Transmission System Costs Should Be Charged For Those

Transmission Services.  See Decl. of David Weaver, PE, Attachment 1 to Exelon Comments, Docket No. EL25-20 (Dec. 12, 2024); see also PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated Transmission Owners June 3, 2025 Answer, Declaration of Danielle S. Powers, at P 29.

i. The Commission’s failure to consider the benefits of grid
interconnection makes the Show Cause Order arbitrary and
capricious.  See State Farm, 463 U.S. at 43.
2. The Burden Has Not Been Met Under FPA Section 206: FERC’s Proposed Replacement Rate is Not Just and Reasonable.  See 16 U.S.C. § 824e(a); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. 2017) (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate . . . and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just and reasonable rate.”) (alterations in original) (citation omitted); Emera Maine v. FERC, 854 F.3d 9, 21 (D.C. Cir. 2017); Atl. City Elec. Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002).  The Show Cause Order failed to address the fact that reliability is relevant to the inquiry of whether a rate is just and reasonable.  See Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022) (“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”); NAACP v. FPC, 425 U.S. 662, 669–70 (1976) (“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”).

a. Allowing Special Treatment For Flexible Large Loads Violates the FPA’s Requirement That There Be No Undue Preference Or

Unreasonable Difference In Rates Between Classes of Service.  See 16 U.S.C. § 824d(b).

PDF page 7

7

i. To the extent that the Commission suggests that the transmission provider may move forward with interconnection before studies are completed, such course of action would jeopardize reliability and would be in tension with NERC reliability standards.  See, e.g., See NERC, FAC-002-4 – Facility Interconnection

Studies
(2022), https://www.nerc.com/globalassets/standards/reliability- standards/fac/fac-002-4.pdf; NERC, 181 FERC ¶ 61,126 (2022) (approving FAC-002-4).

ii. There is no lawful basis to require tariff changes to impose new forms of service that give certain large load customers a reduced share of embedded costs compared to all other users when they receive the same benefits.  See Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022). b. The Commission’s Emphasis on Control Technologies and Protection Systems Is In Tension With the Commission’s Open Access Policies and Therefore Is Arbitrary and Capricious.  The Commission Also Erred In Failing to Account for the Fact that Protective Systems Can and Have Failed.  See NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July 2025), https://www.nerc.com/globalassets/who-we-are/standing- committees/rstc/whitepaper-characteristics-and-risks-of-emerging-large- loads.pdf.

i. The Commission erred in proposing a policy in tension with its open access policies.  See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

c. The Show Cause Order is Arbitrary and Capricious in Abandoning the Main Construct of Service to Load, Which is That Customers Share In the Embedded Costs of the System.  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

PDF page 8

8

i. FERC’s order is arbitrary and capricious in abandoning the main construct of service to load, which is that customers share in the embedded costs of the system.  See State Farm, 463 U.S. at 43; Coal. of MISO Transmission Customers, 45 F.4th at 1009 (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)).

ii. The Show Cause Order departs from traditional cost causation principles and fails to explain or justify its departure.  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020); see also Fox Television Stations, Inc., 556 U.S. at 515 (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”) (citation omitted).

iii. The Commission provides no record evidence nor a reasoned explanation for why flexible large load should not be charged like other load, i.e., with the upgrade cost recovered as part of the transmission rates charged to all customers.  Transmission owners are permitted to earn a reasonable return on the investments necessary to construct, operate, and maintain transmission facilities, including those network upgrades required to serve co-located load.  See, e.g., Fed. Power Comm’n

v. Hope Nat. Gas Co., 320 U.S. 591 (1944); Bluefield Water Works & Improvement Co. v. Pub. Service Comm’n of W. Va., 262 U.S. 679 (1923).

d. There is No Evidence that the New Services That the Commission Proposes to Extend to Flexible Large Load Will Promote Efficiency or Change Siting.

i. The Commission’s decision to require options for contract demand service (“CD Service”) does not change how the study process or the regional planning process should work.  See PJM Tariff §§  31.1-31.3, 31.6, 32.

e. The
Commission’s
Disregard
of
Reliability
Considerations
Underscores that its Proposed Replacement Rate is Not Just and Reasonable.  See Constellation Mystic Power, LLC, 45 F.4th at 1035 (“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”); NAACP v. FPC, 425 U.S. at 669–70 (“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”).

PDF page 9

9

3. FERC Exceeded Its Jurisdiction.  See 16 U.S.C. § 824(b). a. FERC’s Proposed Replacement Rate Violates the Major Questions Doctrine.  See West Virginia v. EPA, 597 U.S. 697, 723 (2022); Whitman

v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”); see also Midship Pipeline Co., v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly”) (quoting West Virginia v. EPA, 597 U.S. at 723); see Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002) (As a federal agency, “FERC is a ‘creature of statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted).

b. The Commission’s Proposed Approach Would Infringe on State Retail Authority.

i. The Commission’s new approach would infringe on state jurisdiction and is distinguishable from wholesale demand response programs.  See 16 U.S.C. § 824(b); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 270, 278–79 (2016); FERC, Energy Primer: A Handbook for Energy Market Basics, at 41 (Jan. 17, 2024), https://www.ferc.gov/news-events/news/ferc- staff-issues-2024-energy-primer-handbook-energy-market-basics.

ii. The Commission is unable to do indirectly what it cannot do directly.  Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909

F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this directly were established, the existence of power to achieve the same end indirectly through the conditioning power might well be doubted” (quoting Sunray Mid-Continent Oil Co. v. FPC, 364 U.S. 137, 152 (1960) and citing Richmond Power & Light v. FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve indirectly through conditioning power of Federal Power Act what it is otherwise prohibited from achieving directly)); Am. Gas Ass’n v. FERC, 912 F.2d 1496, 1510 (D.C. Cir. 1990) (“[T]he Commission may not use its § 7 conditioning power to do

indirectly . . . things that it cannot do at all.”); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room either for direct state regulation of the prices of interstate

PDF page 10

10

wholesales’ or for regulation that ‘would indirectly achieve the same
result.’”) (citation omitted).
II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has Not Been Shown To Be Unjust And Unreasonable.

The FPA requires that the rates and charges of a public utility “in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”9 “[A]ny such rate or charge that is not just and reasonable is . . . unlawful.”10  Under FPA section 206, the Commission may, by its own motion or upon complaint from a third party, remedy any “rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” found to be “unjust [or] unreasonable.”11  “The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or the third-party complainant.”12  In other words, a respondent to a FPA section 206 complaint is not required to make an affirmative showing that its existing rate is still just and reasonable. For the reasons below, neither FERC nor any other party have met the burden of demonstrating that PJM’s current rate is unjust and unreasonable so as to require new forms of transmission service for flexible large load or other large load customers.

A. There is No Evidence In The Record That Flexible Large Loads or Other
Large Loads Are Unable to Obtain Reliable, Timely, And Reasonably Priced
Service Using The Existing Network Service Construct.  Therefore, the
Commission Fails To Satisfy The Requirement Under The APA That Its
Findings Be Supported With Substantial Evidence.

9 16 U.S.C. § 824d(a).
10  Id.
11  Id. § 824e(a).
12  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).

PDF page 11

11

Under the APA, the Commission “must examine the relevant data and articulate a
satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”13 and must base its decision on substantial evidence in the record.14  Substantial evidence means “more than a mere scintilla,” that is, “such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.”15  The Commission’s findings in the Show Cause Order regarding the need for new transmission services does not meet this standard. The totality of the Commission’s reasoning for requiring that new forms of transmission service be offered to flexible large loads is set forth in Paragraphs 85-87 of the Show Cause Order, in which the Commission simply states that there is evidence that flexible large loads can “quickly and verifiably adjust their consumption in response to system conditions and price signals” and can “potentially defer or reduce the need for Network Upgrades, among other benefits.”16 From here, the Commission concludes that the existing PJM Tariff may be unjust and unreasonable because it does not offer flexible large loads the same transmission services as required by the Commission in the December 18 Co-Located Load Order.  However, as in that Order, the Commission’s finding in the Show Cause Order is unsupported by evidence that the current tariff service options are inadequate.  Under the current PJM Tariff, there are two transmission service options: (1) Network Integration Transmission Service (“NITS” or “Network

13  State Farm, 463 U.S. at 43 (citation omitted).
14  See, e.g., Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’” (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004))); see also 5 U.S.C. § 706.
15  Consol. Edison Co. of N.Y., 305 U.S. at 229.
16  Show Cause Order at P 85.

PDF page 12

12

Service”);17 and (2) Point-to-Point Transmission Service.18  There is no inability to determine how to serve load in PJM; the PJM Tariff already has provisions explaining how Network Service works and how loads of Network Customers will be served.  The starting point is Section 31.1 of the PJM Tariff, which (mirroring the Commission’s own pro forma Open Access Transmission Tariff (“OATT”) requires that Network Loads are to be specified in the Service Agreement.  The PJM Tariff sets forth in Sections 31.2 and 31.3 the procedures for identifying new Network Loads that will be served by the Network Customer.  If, and to the extent that, study is required of the request, the requirements of that study are spelled out in Section 32 of the PJM Tariff.  And, in recognition of the fact that loads change after commencement of service, Section 31.6 provides the process by which to report on changing loads.  Further, there are application procedures for studying any new service in Section 29 of the PJM Tariff, which require specification of all aspects of the requested service, including capabilities and operating restrictions on all proposed network resources.  These tariff provisions have been in place for decades, and already require that service requests should be assessed and analyzed based on their particular features; thus they already provide mechanisms for factoring in and assessing the individualized characteristics of the proposed service. The Show Cause Order does not even begin to explain how the existing Network Service

construct and existing PJM Tariff rules and precedent fail to provide a mechanism for loads of all sorts, including flexible large loads.  The Commission states that Eligible Customers taking

17  Under the PJM Tariff, “Network Transmission Service” “mean[s] transmission service provided pursuant to the rates, terms and conditions set forth in Tariff, Part III, or transmission service comparable to such service that is provided to a Load Serving Entity that is also a Transmission Owner.”  PJM Tariff, OATT Definitions – L – M – N, at 13-14.  The PJM Tariff defines “Network Integration Transmission Service” as “the transmission service provided under Tariff, Part III.  There are two types of firm Network Integration Transmission Service:  Regional Network Integration Transmission Service and firm Cross-Border Network Integration Transmission Service. Non-firm Network Integration Transmission Service includes Secondary Service.”  Id. at 12–13.
18  Under the PJM Tariff, “Point-To-Point Transmission Service” “mean[s] the reservation and transmission of capacity and energy on either a firm or non-firm basis from the Point(s) of Receipt to the Point(s) of Delivery under Tariff, Part II.”  Id., OATT Definitions – O – P – Q, at 10.

PDF page 13

13

transmission service on behalf of Eligible Load should be allowed to “choose a transmission service that aligns with their use of the transmission system and therefore aligns the charges for service with the benefits received.”19  However, the Commission never addresses, much less explains, how the existing NITS and Point-to-Point options provide inadequate optionality to Eligible Customers taking service on behalf of large loads, relative to existing load customers in PJM.  Large load customers have been served under open access tariffs for decades and there is simply no evidence offered in the order that such customers are forced to operate inefficiently on account of the existing OATT transmission service offerings.  Indeed, as discussed below, the Commission has consistently rejected arguments that different ratemaking should be applied even where there are limits to the amount of transmission system use.20

The Commission in the Show Cause Order held that NITS and Point-to-Point service options remain just and reasonable.21  But nevertheless, the Commission preliminarily finds that flexible large load customers should be entitled to more new options.22  In short, the Commission asserts that the PJM Tariff may be unjust and unreasonable without these new service options, but provides no evidence to support the conclusion that the existing service options fail to address the needs of flexible large loads.  That is not a permissible basis to make findings or take action under FPA section 206.

B. The Commission Did Not Engage in Reasoned Decision Making Because It Did
Not Explain its Departure from FERC Precedent or Refute that, Because the
Existing PJM Tariff Provides Service on the Same Basis for All Customers, the
Existing PJM Tariff Does Not Grant an Undue Preference.

19  Show Cause Order at P 86.
20  See Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam).
21  Show Cause Order at P 86.
22  June 18, 2026 Order at P 68.

PDF page 14

14

As an initial matter, picking and choosing customers to receive preferential rate treatment runs contrary to the FPA’s requirement that “[n]o public utility shall, with respect to any transmission or sale subject to [FERC’s] jurisdiction . . . (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”23

The Commission has a long-standing policy of rejecting attempts by network transmission customers to avoid paying their load ratio share of system cost.  As the Commission recognized in the December 18 Co-Located Load Order, citing the Amtrak case, the Commission “has rejected cost causation arguments made by network customers that sought to lower their load ratio share based on actual use of the transmission system.”24  This policy has long persisted for very good reason.  The “assessment of [Network Integration Transmission Service] is not based on actual use over a particular transmission path, but rather based on the network customer’s right to use the entire system” and its effects on that system.25

The Amtrak case, which rejected an attempt by a network customer in PJM to pay for less than its full gross load, was not an outlier, but instead reflected decades of Commission precedent, rejecting challenges to uniform application of the rule that Network Service would be based on the entire gross load of the network customer, regardless of arguments (such as those advanced by

23  16 U.S.C. § 824d(b).
24  December 18 Co-Located Load Order at P 196 & n.412 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp, 171 FERC ¶ 61,237, at P 41 (2020), denying clarification and addressing reh’g, Nat’l R.R. Passenger Corp.
v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 (2020) (“Amtrak”); PJM Interconnection, L.L.C., 169 FERC ¶ 61,041, at P 60 (2019)).

25  Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020).

PDF page 15

15

Amtrak) that the customer could purportedly limit use of the system.  For example, this exact issue was addressed in Order No. 888-A and resulting appeals.  In Order No. 888-A, the Commission held that customers cannot “split” their load at a delivery point—if some of the load takes Network Service, all of the load must be designated for Network Service:

The concept of allowing a “split system” or splitting a discrete load
is antithetical to the concept of network service.  A request for
network service is a request for the integration of a customer’s
resources and loads.  Quite simply, a load at a discrete point of
delivery cannot be partially integrated—it is either fully integrated
or not integrated.  Furthermore, such a split system creates the
potential for a customer to “game the system” thereby evading some
or all of its load-ratio cost responsibility for network services.26
That ruling was expressly upheld on appeal by the U.S Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”), which accepted the Commission’s reasoning, finding that objections were “not well-taken.”27

The issue was likewise addressed in a long series of cases involving Florida Municipal Power Agency (“FMPA”) and transmission service it was taking from Florida Power and Light. As recounted by the D.C. Circuit in 2005, years of litigation in that case involved the attempt by FMPA to avoid paying for Network Service based on its overall gross load, with the Commission consistently rejecting all arguments by FMPA against such load splitting.28  In the 2005 decision, the court remanded one argument by FMPA, which is that physical constraints on the transmission system made it physically impossible for its entire load to be served by the Florida Power and

26  Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, 78 FERC ¶ 61,220 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
27  Transmission Access Pol’y Study Grp., 225 F.3d at 726.
28  Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005) (describing history of case back to 1993).

PDF page 16

16

Light system.29  On remand, the Commission found that even in the case of physical impossibility of serving the entire load, the gross load construct was most appropriate, rejecting arguments that a network customer should pay for any less than its entire system load.30

The Commission has consistently followed this precedent.31  For example, in Idaho Power,
the Commission rejected Bonneville Power Administration’s (“BPA”) attempt to remove certain of its load from its load ratio share.32  The Commission explained that, contrary to Order No. 888, “BPA’s proposal would essentially leave the behind the meter loads . . . as part of BPA’s network load served by Idaho Power’s transmission service, but eliminate the requirement that such loads be metered, i.e., included in BPA’s load ratio share, because Idaho Power’s transmission service may only be needed in rare instances.”33  Similarly, in Order No. 890,34 commenters complained that assigning transmission-related costs to customers that reduce their use of the transmission provider’s system to serve load is inconsistent with the Commission’s cost-causation principles. The Commission rejected such arguments, stating that its existing policy already provides

29  Id. at 292 (remanding because “FERC . . . failed to explain why network customers should be charged by the transmission provider for network service that the provider is physically constrained from offering and, relatedly, why physical impossibility should not be recognized as an exception to the general rule against permitting partial load ratio pricing for network customers”).
30  Fla. Power & Light, 113 FERC  ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, 264 F. App’x 4 (D.C. Cir. 2008).
31  See, e.g., Idaho Power Co., 106 FERC ¶ 61,329 (2004) (“Idaho Power”); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010) (finding that network customer failed to comply with the tariff by not designating its total load as network load); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015) (finding that a network customer's request to designate less than its entire load as network load violated both the transmission provider’s OATT and long standing Commission policy, which require network customers to designate their entire load as network load to receive network service).
32  Idaho Power, 106 FERC ¶ 61,329 at P 14.
33  Id. 34  Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh'g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh'g, Order No. 890- B, 123 FERC ¶ 61,299 (2008), order on reh'g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).

PDF page 17

17

customers with the opportunity to reduce network service costs to the extent a customer is not relying on the transmission system to meet its energy needs (i.e., by taking point-to-point transmission service instead of network service).35

The Show Cause Order’s preliminary finding that flexible large load should be entitled to new transmission services based on less than their entire load departs from these decades of precedent and, contrary to the APA, has failed adequately to explain such departure.36  The Commission’s prior determinations of the fairness of load ratio allocation (based on gross load— even in the case of purported physical impossibility of service to full load) of embedded costs hold true.  There is no reasoned basis for these distinctions.

The Declaration of Danielle S. Powers (“Powers Declaration”), submitted by the Indicated Transmission Owners in the PJM Co-Located Load Proceedings, explains why the assessment of Network Service is not based on actual use over specific transmission paths.37  All customers have different usage of the grid.  Many customers’ reliance upon the grid varies during different times of the year and can be distinguished from other customers’ uses.  These customers may have distinct load shapes or load factors, but they pay the same rate for Network Service as do high load factor customers.  Such customers pay the full Network Service rate, but because Network Service charges are allocated based on contribution to the system coincident peak, some customer charges

35  See Order No. 890, 119 FERC ¶ 61,119.
36  See  Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position. An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”).  At paragraph 211 of the June 18, 2026 Order, the Commission says that the current load-splitting proposal is different from prior situations because PJM need only plan for the specified contract demand rather than the full load, but this argument is not a difference from prior cases at all, such as the FPL case where there was no contention that FPL was redesigning its system to serve the full load of FMPA, or the Amtrak case where the entire premise of the argument was that Amtrak made only rare and limited use of the system.
37  See PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of Danielle S. Powers at P 29.

PDF page 18

18

may be lower on average than others if their operations occur disproportionately outside of the peak hours.  No additional rate discount is necessary or given.  Up until now, the Commission has consistently applied this approach of not carving out special rates for different customer classes for good reason—every customer can attempt to make arguments why their usage should result in a decrease of their share of the embedded costs of the transmission system.  Utilities have an obligation to serve load and that load needs to be able to call on service regardless of whether they actually utilize the system to the maximum allowable extent since weather and other factors are unpredictable.  Hence, actual usage does not reflect the benefit.  Entertaining such arguments would frustrate the rate design that the Commission has applied across the board and that was put in place following Order No. 888.38

The existing PJM Tariff effectuates the principle that those that benefit from the
transmission system should contribute on a load ratio basis to the embedded costs of the system and is consistent with the pro forma OATT in providing for Network Service and Point-to-Point Service, an important component of Order No. 888.39  Under the APA, the Commission must

explain why circumstances have changed such that this proceeding requires departure from past efforts by customers to pay for less than gross load.40  The Commission made no serious attempt

38  See, e.g., Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, 75 FERC ¶ 61,080 (1996), order on reh’g, Order No. 888-A, 78 FERC ¶ 61,220, order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000) (TAPS), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

39  See, e.g., id.
40  See Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); see also Constellation Mystic Power, LLC 45 F.4th at 1057 (finding the Commission’s decision to be arbitrary and capricious and that “the Commission’s ‘failure to provide an intelligible explanation . . . amounts to a failure to engage in reasoned decisionmaking’”) (citation omitted); New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned (cont'd)

PDF page 19

19

to do so.  Nor has the Commission distinguished why other existing customers will not qualify for discounts—many of whom can argue that they impose lesser demand on the grid by some measure. That failure to provide explanation renders FERC’s finding arbitrary and capricious and violative of the APA.41  Ultimately, this is not reasoned decision making and will create a nightmare as other customers in PJM and beyond raise a host of similar arguments that their transmission rates should be modified based on their allegedly different use of the system, which is a reason why the Commission never mandated this in the past.

C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
Their Full Gross Load.  Therefore, FERC’s Decision is Arbitrary and
Capricious Because The Embedded Transmission System Costs Should Be
Charged For Those Transmission Services.
Notwithstanding well-established Commission policy and judicial precedent to the
contrary, the Show Cause Order preliminarily finds that flexible large loads should be entitled to a preferential transmission rate.  Not only is this new rate unduly discriminatory (as discussed herein), but it is based on a false premise that the combination of transmission system burdens and user benefits of flexible loads are so insignificant as to justify the establishment of a lower, preferential rate.  The Commission is wrong, with respect to both the actual burdens on the system and the benefits to flexible large loads of being interconnected to the grid.

explanation of why those facts matter.” (citing BP Energy Co. v. FERC, 828 F.3d 959, 968 (D.C. Cir. 2016) (vacating finding of no undue discrimination where Commission identified differences between two natural-gas companies but failed to adequately explain why they provide a rational basis for the difference in treatment))); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ . . . and Commission cases are no exception . . . .”) (alteration in original) (citations omitted).

41  See, e.g., Cal. Pub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this policy without acknowledgment or explanation. This departure was arbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . .  [FERC] must at least ‘acknowledge’ its seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (alterations in original) (citation omitted).

PDF page 20

20

As for benefits, the Commission has recognized that co-located loads benefit from black start and load following service,42 and that such service properly should be charged based on gross load.  Flexible large loads are likewise reliant on black start and load following. Load following services are supplied from a diverse range of the interconnected generation facilities located throughout the system.  These services cannot be provided without use of all the transmission system’s resources and personnel.  Moreover, because it is a universal rule that generators cannot operate every hour of every year and that unexpected outages can and do occur, transmission interconnections provide an avenue for such loads to readily acquire back-up power when co- located generation facilities are not available.

In addition, in assessing flexible large loads, the Commission fails to consider the many advantages to such loads when they connect to the transmission system, regardless of whether they are able to limit their demand under certain circumstances.  These advantages become apparent when one compares islanded projects to similar projects that are interconnected to the transmission grid.  Islanded projects require extensive back-up generation to assure reliable sources of power. It is very difficult and expensive to supply islanded generation with black start capabilities or instantaneous load following.  All back-up generation on an islanded project will sit idle when not needed to serve the islanded load, thereby forgoing significant revenues from selling the surplus power into the wholesale market.  These lost opportunity sales revenues alone could likely cover the fully embedded costs of Network Service.  Ultimately, islanded generation projects are more risky and therefore more difficult to finance.  Grid interconnection is valuable, which is why large loads, including those co-located with generation, have not proposed islanded configurations.  In preliminarily finding that traditional Network Service without the option of additional services is

42  See December 18 Co-Located Load Order at PP 209, 219.

PDF page 21

21

unjust and unreasonable for flexible large load, the Commission considered none of these benefits of grid interconnection to such loads.  Failure to consider the benefits of grid interconnection makes this finding arbitrary and capricious and unreasoned.43

III. The Commission’s Suggested Replacement Rate Would Not Be Just and
Reasonable.

Under FPA section 206,44 there are two steps: only after the Commission finds a rate to be unjust and unreasonable, may it set a replacement rate.45  Even if the Commission has established that the current PJM Tariff is unjust and unreasonable with respect to the transmission services available to flexible large load, it has not demonstrated that its proposed replacement rate— extending the services that it directed in the PJM Co-Located Load Proceeding to flexible large load—is just and reasonable.

A. Allowing Special Treatment For Flexible Large Load Would Violate The
FPA’s Requirement That There Be No Undue Preference Or Unreasonable
Difference In Rates Between Classes Of Service.
As explained above, FPA section 205 prohibits any public utility charging transmission rates from “mak[ing] or grant[ing] any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage” or “maintain[ing] any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”46  Requiring extension of the new transmission services that the Commission

43  See State Farm, 463 U.S. at 43. 44  16 U.S.C. § 824e(a).
45  See id; see also Advanced Energy Mgmt. All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just and reasonable rate.”) (alterations in original) (citation omitted); Emera Maine, 854 F.3d at 21; Atl. City Elec. Co., 295 F.3d at 10.
46  16 U.S.C. § 824d(b).

PDF page 22

22

has required for Co-Located Load to flexible large load would establish rates that grant an undue preference or advantage to such loads, for the same reasons that Exelon and FirstEnergy explained in the PJM Co-Located Load Proceedings.

There already exist mechanisms (such as demand response at the state and federal levels) to address when customers can scale back their load or otherwise reduce their withdrawals when called upon.  If flexible large loads wish to be compensated for being interruptible, then they should rely upon PJM’s demand response rules, or retail rules in the various states, and the Show Cause Order fails to explain why those rules are inadequate here.  The point of FPA section 206 is not for the Commission to declare what it thinks would be better tariff options—it is to ensure that the tariff on file is just and reasonable.  Similarly, the PJM Tariff already has in place provisions to provide compensation to those customers that can ease transmission congestion—to the extent that a basis for the Commission’s orders is that some uses of the system reduce grid usage thus easing congestion, the mechanisms are already there.  The Commission does not consider those existing tariff provisions.

With respect to Interim NITS service, there is no basis for the Commission to require this new form of service prior to the completion of necessary network upgrades and studies to ensure reliability of the system.  The Commission has effectively conceded it has not yet done adequate analysis on this point in the PJM Co-Located Load Proceeding – ruling in Paragraphs 125 and 131 of the June 18, 2026 Co-Located Load Order that it is “premature” to determine the extent, if any, that the new forms of service promote efficiency or impact reliability.  The Commission cannot have it both ways – if it is premature to consider if the new services promote efficiency, or adequately protect reliability, the Commission cannot rely on purported efficiency gains, to justify

PDF page 23

23

imposition of the new services, and cannot claim to have done so in a way that is protective of reliability.

Second, the only issue that CD Services resolve is rate levels for embedded costs allocated to the loads taking such services.  The form of service does not dictate what studies should be conducted, or what upgrades might be necessary for the system.  Whether or not a customer seeks CD Service, studies should consider the actual circumstances of the proposed interconnection, which will be dictated by engineering and physics, and not by the rate level charged to the customer.  The notion that CD Service impacts issues such as where a customer interconnects depend on a fallacy that system studies consider rate levels rather than the details of the proposed interconnection.

Interconnecting to the grid burdens the system by adding new loads and operating contingencies that must be addressed by system operators.  Grid interconnections also bring significant project benefits such as the ability to receive load following service from off-site generation.  The totality of these burdens and benefits—benefits which no doubt exceed the cost of Network Service based on gross load—easily justify charging flexible large loads, and indeed all large loads, the same rate as all other transmission customers.  To allow for preferential rate treatment would allow those customers to rely upon the grid and its benefits at a price that is subsidized by all other customers.  That cannot be said to be just and or reasonable.47  Such a

47  See Coal. of MISO Transmission Customers, 45 F.4th at, 1009 (alterations in original) (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)) (“The cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”).

PDF page 24

24

decision is not grounded in reasoned decision making and is not supported by substantial evidence.48

B. The Commission’s Emphasis On Control Technologies and Protection
Systems Is In Tension With The Commission’s Open Access Policies And
Therefore Is Arbitrary And Capricious.  The Commission Also Erred In
Minimizing The Fact That Such Systems Can And Have Failed.

As Exelon, FirstEnergy and other Transmission Owners have explained in the PJM Co- Located Load Proceeding, protective systems can provide value, but they are no panacea.  Such systems do not operate instantaneously and without failure.  If a load unexpectedly draws excess supply from the grid, for even a moment, the transmission system sees a rapid demand spike, which may stress and harm the system.49  Moreover, as the Commission acknowledged, “PJM maintains that it is always possible that any protection system in an isolated (but not islanded) Co-Location Arrangement could mis-operate, be disabled, or degrade, and that, in the few instances where such schemes exist on the PJM system, PJM has observed these schemes fail, and the load has taken grid service.”50  This concern is no less applicable to flexible loads that would depend on such systems to ensure that their actual use does not exceed their planned use.

As the Commission recognizes from PJM’s comments, “if the protection system fails, the large load would instantly take significant energy from the system” and “though a few such configurations may seem tolerable, the risk increases with large quantities of such

48  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.
49  Id.
50  December 18, 2025 Co-Located Load Order at P 44.

PDF page 25

25

configurations.”51  To address this risk, the Commission “direct[s] PJM to apply a penalty rate.”52 Assessing penalties, however, only addresses the issue after the fact and does not remediate the reliability implications of faulty protective systems.

As previously discussed, because the Commission has not addressed these issues in making its preliminary finding that flexible loads should be entitled to take the same transmission services that the Commission directed in the PJM Co-Located Load Proceeding, it has not engaged in reasoned decision making and fails to satisfy the APA requirements.

C. CD Service Will Not Promote Efficiency Or Change Siting.
To be clear, under any circumstance, project development teams for new load, whether that load is co-located or not, already have a strong incentive to site their facilities on the grid at a location that minimizes the need for transmission upgrades.  Project developers understand that additional work can add cost, increase complexity, risk project delay, and result in lost opportunity. In addition, and as discussed above, wise siting decisions will minimize the need for system upgrades, which will hasten interconnection.  That benefit is real.  But it has nothing to do with the proposed CD Service.  This is because the impacts to the grid are based on physics and engineering.  Whether the service paid for is based on net load or gross load does not change that planning and siting depend on the physics and engineering of the grid.

The Commission’s preliminary finding regarding the availability of CD Service does not change how the study process should work.  Regardless of cost allocation, ensuring there is a reliable grid is essential and understanding what load amount the system needs to support is necessary.  If transmission providers are forced to pretend a 500 MW load is only 50 MW, or even

51  Id. P 17.
52  Id. P 212.

PDF page 26

26

that it is zero, and pretend away the physics and engineering impacts, it will threaten reliability and resource adequacy and therefore cannot be said to be just and reasonable.

While protective systems can be beneficial, any suggestion that regional planning needs are automatically reduced by the establishment of CD Service is also not supported by evidence. No loads should be taken out of the broader planning process—to do so would only threaten reliability of the system.  Grid operators must plan for such eventualities to ensure system reliability.53

D. The Commission’s Disregard of Reliability Considerations Underscores That
The Proposed Replacement Rate is Not Just and Reasonable
The new transmission service options that the Commission proposes to extend to flexible large load reflect the fact that the Commission overlooked important reliability concerns.  The Commission’s ruling in the June 18, 2026 Co-Located Load Order that the issue is premature, and its failure to meaningfully address reliability issues in the Show Cause Order, highlights the fact that the Commission has not yet dealt with this issue.54  Protective systems, even when fully functioning, are intended to keep net load at zero or below, but as the Commission has held in the Co-Located Load Proceeding, it is the gross load that is being followed by resources elsewhere on the grid every minute of the day, and thus using and impacting the system every minute of the day.55  The suggestion that protective systems that only address net load obviate reliability concerns ignores physical reality.

The Commission’s preliminary finding that Interim NITS should be offered to flexible load overlooks potential resource adequacy risks.  This service is, by definition, offered before needed

53  See PJM Tariff §§ 31.1-31.3, 31.6, 32.
54  June 18, 2026 Order at P 131.
55  See id.

PDF page 27

27

transmission upgrades are completed and it is unclear from the Show Cause Order how it will be determined whether the load may be reliably served.  The purpose of this interim service is “more rapid interconnection and operation of Co-Located Loads” and the only reliability check is a determination by PJM that it can provide “some level of interim service reliably.”56  Among other things, we still do not know how PJM will determine whether it can provide “some level of interim service reliably” which is an issue that has been left for later development and filings.  Because “[t]he reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies,”57 and given that it is still unknown how one could reasonably determine what level of service can be provided before studies are conducted, it cannot be said that these transmission service options are just and reasonable.58  The Commission has failed to seriously take into account reliability implications in its finding that these new transmission services should be adopted for flexible large loads, and its decision is therefore not reasoned decision making and is arbitrary and capricious.

IV. FERC Exceeded Its Jurisdiction.
A. FERC’s Proposed Replacement Rate Violates the Major Questions Doctrine.

56  Id. P 200. 57  Constellation Mystic Power, LLC, 45 F.4th at 1035.
58  Cf. Ameren Servs. Co. v. FERC, 880 F.3d 571, 580–81 (D.C. Cir. 2018) (finding that FERC “ma[de] no real attempt to holistically assess all of the various risks and benefits to the transmission owner caused by the addition of the upgrade facilities,” that “FERC inadequately considered [the] argument that all costs, and risks, are not baked in—that, in fact, shareholders are forced to accept incremental exposure to loss with no corresponding benefit” and therefore, that FERC’s “failure to meaningfully respond to it makes FERC’s decision arbitrary and capricious”) (footnote omitted); Advanced Energy Mgmt. All., 860 F.3d at 664–65 (explaining the Commission’s rationales that “support[ed] the Commission’s finding that the energy market rules were unjust and unreasonable,” which included a rationale that “existing generator outage provisions ‘impede PJM’s ability to ensure reliability’ because they do not give PJM the authority to rescind approval for a planned outage when there is an emergency”) (citation omitted); Cent. Hudson Gas & Elec. Corp. v. FERC, 783 F.3d 92, 111 (2d Cir. 2015) (explaining that FERC, in creating the Lower Hudson Zone, considered long-term benefits that would follow accurate price signals, including that it would “alleviate the risk of reliability problems in the long run”).

PDF page 28

28

There is no basis to change the PJM Tariff under FPA section 206 when the purpose of the change is to provide preferential treatment or a preferred service to a certain category of customers. Such action would violate the major questions doctrine.  If Congress wanted to give the

Commission authority to direct its preferred transmission service to benefit certain categories of customers, it could have done so.59  It did not do so.  FERC, like all agencies, “ha[s] only those powers given to [it] by Congress, and ‘enabling legislation’ is generally not an ‘open book to which the agency [may] add pages and change the plot line.”60  The Commission lacks authority under the FPA to order a new type of transmission service with the sole purpose to benefit some categories of load and to treat those favored types of load differently from other loads that have similar system impacts and usage.  Accordingly, FERC proposal to require new transmission services be adopted for flexible large loads—because it favors a narrow category of customers (i.e., a “subset” of large loads that “are willing and able to limit their energy withdrawals from the transmission system under certain conditions”) without reasoned explanation—violates the requirement in the FPA that no rate by a public utility grants an undue preference or advantage or unreasonable difference in rates.61

B.  The Commission’s New Approach Infringes On State Retail Authority.

59  Cf. Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”); see Atl. City Elec. Co., 295 F.3d at 8 (As a federal agency, “FERC is a ‘creature of statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted).

60 West Virginia v. EPA, 597 U.S. 697, 723 (2022) (third alteration in original) (citation omitted); see also Midship Pipeline Co. v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly”) (second alteration in original) (quoting West Virginia v. EPA, 597 U.S. at 723).
61  16 U.S.C. § 824d(b).

PDF page 29

29

The states, not the Commission, have jurisdiction to decide when and in what
circumstances retail load will be curtailed, and how utilities should charge and treat retail customers in those circumstances.  The Commission has jurisdiction over “the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce,” and over “all facilities for such transmission or sale of electric energy.”62  Except as otherwise provided in the FPA, the states retain jurisdiction over “any other sale of electric energy” and “over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.”63

States decide how the retail obligation to serve should be met.  For example, states might require the provision of backup service to retail customers who lose supply from their contracted supplier, would regulate the distribution system costs associated with such service that would be charged to the retail customer, and would regulate the costs and terms of the backup service. Rather than honoring the states’ freedom and flexibility to exercise their jurisdiction over such questions, the Commission’s new rule appears to create a new federal construct that defines the extent and terms of service in such situations.  That is, the Commission’s new rules leave it entirely up to the customer to specify a contract demand service level that it will purportedly not exceed, even if state law mandates that the local utility provide the customer with backup service in the event of an outage.  The Commission’s conclusion that the customer will not take additional service lies in direct conflict with the states’ backup service mandates.  The Commission does not have authority under the FPA to dictate the terms of retail service in that fashion.

62  16 U.S.C. § 824(b).
63  Id.

PDF page 30

30

Unlike wholesale demand response programs, which “allow[] any state regulatory body to prohibit consumers in its retail market from taking part in wholesale demand response programs,” thereby “not requir[ing] any “‘action[ ] that would violate State laws or regulations,’” the Commission’s new forms of transmission services provide no such limitation.64  As the Supreme Court has explained, however, “if indirect or tangential impacts on wholesale electricity rates sufficed, FERC could regulate now in one industry, now in another, changing a vast array of rules and practices to implement its vision of reasonableness and justice,” a result that the Court could not “imagine . . . was what Congress had in mind.”65  That is the problem here with FERC’s proposal to extend the new transmission services that it devised in the PJM Co-Located Load Proceeding to flexible large load.

As the Supreme Court explained, the FPA
“limit[s] FERC’s sale jurisdiction to that at wholesale,” reserving
regulatory authority over retail sales (as well as intrastate wholesale
sales) to the States.  FERC cannot take an action transgressing that
limit no matter how direct, or dramatic, its impact on wholesale
rates.  Suppose, to take a far-fetched example, that the Commission
issued a regulation compelling every consumer to buy a certain
amount of electricity on the retail market.  Such a rule would
necessarily determine the load purchased on the wholesale market
too, and thus would alter wholesale prices.  But even given that
ineluctable consequence, the regulation would exceed FERC’s
authority, as defined in § 824(b), because it specifies terms of sale
at retail—which is a job for the States alone.66
FERC’s CD Services similarly interfere with States’ regulation of the terms of sale at retail, dictating the terms and circumstances of service to end use customers who lose their contracted retail power supplier—an area that is directly within the States’ domain.  The Commission is

64  FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 275 (2016) (third alteration in original) (citation omitted).
65  Id. at 278.
66  Id. at 279–80 (alteration in original) (citations omitted).

PDF page 31

31

unable to do indirectly what it cannot do directly, which is what it does when it intrudes on state regulatory authority over retail service in this fashion.67

The Commission should leave retail service questions to the retail regulator.  The
imposition of CD Service rates to usurp these questions exceeds the Commission’s lawful authority.

V. Conclusion
Because neither the Commission nor any other complainant have satisfied their burden
under FPA section 206 to show that PJM’s existing Tariff is unjust and unreasonable with respect to flexible large load (or any other type of load) and the Commission has not engaged in reasoned decision making in the Show Cause Order the Commission should grant rehearing and revoke its preliminary finding in the Show Cause Order that the new transmission service offerings that it devised in the PJM Co-Located Load Proceeding should be extended to flexible large loads, or any other large loads.

67  Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909 F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this directly were established, the existence of power to achieve the same end indirectly through the conditioning power might well be doubted”) (quoting Sunray Mid-Continent Oil Co. v. FPC, 364 U.S. 137, 152 (1960) and citing Richmond Power & Light v. FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve indirectly through conditioning power of Federal Power Act what it is otherwise prohibited from achieving directly)); Am. Gas Ass’n, 912 F.2d at 1510 (“[T]he Commission may not use its § 7 conditioning power to do indirectly . . . things that it cannot do at all.”); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room either for direct state regulation of the prices of interstate wholesales’ or for regulation that ‘would indirectly achieve the same result.’”) (citation omitted).

PDF page 32

32

Respectfully submitted,

/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs

Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com /s/ Bradley R. Perkins

Bradley R. Perkins
Vice President and Deputy General Counsel Exelon Corporation

Chase Building
10 S. Dearborn, 52nd Floor
Chicago, IL 60603
(312)394-2632
Telephone: 312-394-2632
Email: bradley.perkins@exeloncorp.com

On behalf of Exelon Corporation

/s/ Amanda P. Parker
Amanda P. Parker
Corporate Counsel
FirstEnergy Service Company
341 White Pond Drive
Akron, OH 44320

Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com

On behalf of The FirstEnergy
Transmission Companies

PDF page 33

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets.

Dated at Chicago, IL this 20th day of July, 2026.

/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation