EL26-67-001 · 2026-07-20 · Exelon Corporation, The FirstEnergy Transmission Companies

Exelon Corporation and FirstEnergy Service Company submit Request for Rehearing of the 06/18/2026 Order

Exelon and FirstEnergy request rehearing of the E-7 order's preliminary finding that PJM's tariff is unjust without new transmission services for flexible large loads, arguing the record lacks evidence, the services shift costs, and FERC exceeds its jurisdiction.

Asks FERC to: Grant rehearing and revoke the preliminary finding that the new co-location transmission services should be extended to flexible large loads or any other large loads.

Rehearing request aimed directly at the E-7 flexible large load transmission service finding and its reliance on the December 2025 co-location services.

E-7 PJM: Service for flexible loads (P 85, p. 56)

Key points

  1. Exelon and FirstEnergy challenge the finding that PJM's tariff lacks services for flexible large loads, calling it arbitrary and not reasoned.
    The Commission’s findings that the PJM Tariff appears to be unjust and unreasonable without these new transmission service options is arbitrary and capricious and not based upon reasoned decision making. PDF p. 1
  2. They say the new services would only cut transmission charges for large loads at other customers' expense.
    the creation of these new forms of transmission service will not hasten or improve service and instead merely reduce transmission charges for large loads at the expense of other customers. PDF p. 2
  3. They say FERC's burden under section 206 is unmet because the record shows no inability to get service under existing Network Service.
    There is No Evidence In the Record That Flexible Large Loads or Any Other Large Loads Are Unable to Obtain Reliable, Timely, and Reasonably Priced Service Using the Existing Network Service Construct. PDF p. 3
  4. They say large loads rely on the whole embedded system, so embedded costs should be charged for their full gross load.
    Flexible Large Loads and Other Large Loads Rely Upon the Entire Embedded Transmission System to Serve Their Full Gross Load. PDF p. 6
  5. They argue the new services intrude on state retail authority.
    FERC’s CD Services similarly interfere with States’ regulation of the terms of sale at retail PDF p. 30
Contents · 14 sections
  1. I. Statement of Issues/Specification of Error. p. 3
  2. II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has p. 10
  3. A. There is No Evidence In The Record That Flexible Large Loads or Other p. 10
  4. B. The Commission Did Not Engage in Reasoned Decision Making Because It Did p. 13
  5. C. The Loads Rely Upon The Entire Embedded Transmission System To Serve p. 19
  6. III. The Commission’s Suggested Replacement Rate Would Not Be Just and p. 21
  7. A. Allowing Special Treatment For Flexible Large Load Would Violate The p. 21
  8. B. The Commission’s Emphasis On Control Technologies and Protection p. 24
  9. C. CD Service Will Not Promote Efficiency Or Change Siting. p. 25
  10. D. The Commission’s Disregard of Reliability Considerations Underscores That p. 26
  11. IV. FERC Exceeded Its Jurisdiction. p. 27
  12. A. FERC’s Proposed Replacement Rate Violates the Major Questions Doctrine. p. 27
  13. B. The Commission’s New Approach Infringes On State Retail Authority. p. 28
  14. V. Conclusion p. 31

Read topic-matched comments in EL26-67

Topics in the text: Connecting load and generation · Filing procedure · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

While the Commission stated that these remain just and reasonable options, the Commission directed PJM to address whether its Tariff remains just and reasonable without allowing Eligible Customers taking transmission service on behalf of “flexible large loads” the option of taking one or more of…
Read this passage Filed comments: Connecting load and generation

I. Statement of Issues/Specification of Error.

printed heading · Topic match: Cost allocation

Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol.
Read this passage Filed comments: Cost allocation

II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has

printed heading

The FPA requires that the rates and charges of a public utility “in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”9 “[A]ny such…
Read this passage

A. There is No Evidence In The Record That Flexible Large Loads or Other

printed heading · Topic match: Connecting load and generation

Cir. 2021). 11 Under the APA, the Commission “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”13 and must base its decision on substantial evidence in the record.14 Substantial…
Read this passage Filed comments: Connecting load and generation

B. The Commission Did Not Engage in Reasoned Decision Making Because It Did

printed heading · Topic match: Connecting load and generation

In Order No. 888-A, the Commission held that customers cannot “split” their load at a delivery point—if some of the load takes Network Service, all of the load must be designated for Network Service: The concept of allowing a “split system” or splitting a discrete load is antithetical to the…
Read this passage Filed comments: Connecting load and generation

C. The Loads Rely Upon The Entire Embedded Transmission System To Serve

printed heading · Topic match: Connecting load and generation

Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ . . . and Commission cases are no exception . . . .”) (alteration in original) (citations omitted). 41 See, e.g., Cal.
Read this passage Filed comments: Connecting load and generation

III. The Commission’s Suggested Replacement Rate Would Not Be Just and

printed heading · Topic match: Connecting load and generation

Under FPA section 206,44 there are two steps: only after the Commission finds a rate to be unjust and unreasonable, may it set a replacement rate.45 Even if the Commission has established that the current PJM Tariff is unjust and unreasonable with respect to the transmission services available to…
Read this passage Filed comments: Connecting load and generation

A. Allowing Special Treatment For Flexible Large Load Would Violate The

printed heading · Topic match: Connecting load and generation

All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just and…
Read this passage Filed comments: Connecting load and generation

B. The Commission’s Emphasis On Control Technologies and Protection

printed heading · Topic match: Connecting load and generation

As the Commission recognizes from PJM’s comments, “if the protection system fails, the large load would instantly take significant energy from the system” and “though a few such configurations may seem tolerable, the risk increases with large quantities of such 48 See Florida Gas, 604 F.3d at 639…
Read this passage Filed comments: Connecting load and generation

C. CD Service Will Not Promote Efficiency Or Change Siting.

printed heading · Topic match: Cost allocation

Grid operators must plan for such eventualities to ensure system reliability.53
Read this passage Filed comments: Cost allocation

D. The Commission’s Disregard of Reliability Considerations Underscores That

printed heading · Topic match: Connecting load and generation

The Commission’s Disregard of Reliability Considerations Underscores That The Proposed Replacement Rate is Not Just and Reasonable The new transmission service options that the Commission proposes to extend to flexible large load reflect the fact that the Commission overlooked important reliability…
Read this passage Filed comments: Connecting load and generation

IV. FERC Exceeded Its Jurisdiction.

printed heading

IV.
Read this passage

A. FERC’s Proposed Replacement Rate Violates the Major Questions Doctrine.

printed heading

FERC’s Proposed Replacement Rate Violates the Major Questions Doctrine. 56 Id.
Read this passage

B. The Commission’s New Approach Infringes On State Retail Authority.

printed heading · Topic match: Retail and wholesale authority

Power Supply Ass’n, 577 U.S. 260, 275 (2016) (third alteration in original) (citation omitted). 65 Id. at 278. 66 Id. at 279–80 (alteration in original) (citations omitted). 31 unable to do indirectly what it cannot do directly, which is what it does when it intrudes on state regulatory authority…
Read this passage Filed comments: Connecting load and generation

V. Conclusion

printed heading · Topic match: Connecting load and generation

Conclusion Because neither the Commission nor any other complainant have satisfied their burden under FPA section 206 to show that PJM’s existing Tariff is unjust and unreasonable with respect to flexible large load (or any other type of load) and the Commission has not engaged in reasoned decision…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Chicago, IL this 20th day of July, 2026. /s/ Geneva Kennedy Geneva Kennedy Exelon Corporation