EL26-67-001 · 2026-07-20 · Indicated PJM Transmission Owners

The Indicated PJM Transmission Owners submit Request for Clarification, or in the Alternative, Rehearing of the 06/18/2026 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.
)

Docket No. EL26-67-000

REQUEST FOR CLARIFICATION, OR IN THE ALTERNATIVE, REHEARING OF
THE INDICATED PJM TRANSMISSION OWNERS

Pursuant to Section 313 of the Federal Power Act (“FPA”)1 and Rules 212 and 713 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),2 the Indicated PJM Transmission Owners (“PJM Transmission Owners”)3 respectfully request clarification, or in the alternative, rehearing of the Commission’s order issued on June 18, 2026, in this proceeding relating to the appropriate definitions of “large load” and “electrically proximate large load.”4

On June 18, 2026, the Commission issued show cause orders under section 206 of the FPA to PJM Interconnection, L.L.C. (“PJM”), Midcontinent Independent System Operator, Inc., Southwest Power Pool, Inc., California Independent System Operator Corporation, ISO New England Inc., and New York Independent System Operator, Inc., together with their transmission

1 16 U.S.C. § 825l(a).
2 18 C.F.R. §§ 385.212 and 385.713 (2025).
3 The Indicated PJM Transmission Owners are:  American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; and Rockland Electric Company.
4 PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211 (2026) (“PJM Show Cause Order” or “Order”).

PDF page 2

2
owners,5 directing each region to justify or reform the tariff provisions governing how large loads connect to and receive service from the transmission system.6

The PJM Show Cause Order preliminarily found that PJM’s existing Open Access
Transmission Tariff (“PJM Tariff”) appeared to be unjust, unreasonable, or unduly discriminatory or preferential because of a lack of sufficiently clear and consistent provisions to address service for large loads and related configurations.7  The Commission therefore directed PJM and its transmission owners, within 60 days, to show cause why the PJM Tariff remains just and reasonable without provisions addressing:  (1) the application process, study procedures, and ongoing operational requirements for Eligible Customers8 seeking transmission service on behalf of large loads; (2) additional transparency concerning Network Upgrade costs for such service, together with the absence of a pro forma cost recovery agreement and a mechanism to ensure related payments are properly credited to transmission owners’ revenue requirements; (3) transmission service options tailored to flexible large loads willing and able to limit their use of the transmission system under certain conditions; and (4) rates, terms, and conditions applicable to interconnection customers serving “electrically proximate large load” or co-located load.9  The

5 Midcontinent Indep. Sys. Operator, Inc., et al., 195 FERC ¶ 61,212 (2026), Southwest Power Pool, et al., 195 FERC ¶ 61,213 (2026), California Indep. Sys. Operator, Inc., et al., 195 FERC ¶ 61,214 (2026), ISO New England Inc., et al., 195 FERC ¶ 61,215 (2026), New York Indep. Sys. Operator, Inc., et al., 195 FERC ¶ 61,216 (2026) (collectively, the “Show Cause Orders”).
6 The Commission’s June 18, 2026, show cause orders follow the Secretary of Energy’s letter, pursuant to section 403 of the Department of Energy Organization Act, directing FERC to initiate a rulemaking proceeding and to consider its advanced notice of proposed rulemaking (“ANOPR”) to accelerate large load interconnections.  See Letter and ANOPR of Chris Wright, Sec’y, U.S. Dep’t of Energy (Oct. 23, 2025).  The Commission subsequently invited comments on the proposed ANOPR.  See Notice Inviting Comments, Docket No. RM26-4-000 (issued Oct. 27, 2025).
7 PJM Show Cause Order at PP 3, 35.
8 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff.
9 PJM Show Cause Order at PP 3, 35.

PDF page 3

3
Commission directed PJM either to justify the absence of such provisions or to propose Tariff revisions addressing those concerns.10

The PJM Transmission Owners share the underlying goals driving the Commission’s issuance of the Show Cause Orders: namely, to enable new large load customers to efficiently interconnect to the transmission system while simultaneously ensuring reliability and protecting existing customers.  To that end, the PJM Transmission Owners respectfully seek clarification, or in the alternative, rehearing of two preliminary findings in the PJM Show Cause Order:

1. The Commission should clarify that adopting the definition of “large load” proposed in the Show Cause Order, including the 50 MW threshold criteria, does not prevent PJM and the PJM Transmission Owners from proposing and supporting additional service-specific criteria for large load customers relating to the types of services contemplated in the Show Cause Order.  If the Commission declines to make this clarification, it should grant rehearing, as a one-size-fits-all approach for all customers that meet the definition of “large load” is likely to be over-inclusive and unduly discriminatory, and undermine the Commission’s speed-to-power goals for large load customers, particularly large computational loads that are crucial to serving AI processes.

2. The Commission should clarify that PJM and the PJM Transmission Owners will be permitted to propose and support a definition of “large load” and “electrically proximate large load” that are not based on the location of facilities relative to the Point of Interconnection,11 e.g., by proposing a definition that relies on the Point of Change of Ownership.  If the Commission declines to adopt this clarification, it should grant rehearing.  As PJM and the PJM Transmission Owners have explained in the PJM co- located load proceeding, there are significant problems with adopting such definitions based on facilities on the customer-side of the Point of Interconnection, including potentially encouraging gaming activities that will undermine the efficient and reliable interconnection of large loads.

10 PJM Show Cause Order at PP 3, 35.
11 Id. at P 94 & n.7.

PDF page 4

4
I. REQUESTS FOR CLARIFICATION AND REHEARING
A. Statement of Issues and Specification of Errors
To the extent that the Commission declines to grant clarification as set forth below, the PJM Transmission Owners submit the following Statement of Issues and Specification of Errors pursuant to Rule 713(c)(1) and 713(c)(2) of the Commission’s Rules of Practice and Procedure:12  To the extent that the definition of “large load” proposed in the PJM Show Cause Order is intended to restrict PJM and the PJM Transmission Owners from proposing and supporting additional service-specific criteria for large load customers, the PJM Show Cause Order is arbitrary and capricious, does not reflect reasoned decision-making, and is unsupported by substantial evidence in violation of the Administrative Procedure Act because the Commission did not develop a sufficient record to support such a restriction, and such a restriction would be unjust, unreasonable, and unduly discriminatory.  Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43 (1983) (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”) (citation omitted) (“State Farm”); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265 (D.C. Cir. 2022); Consol. Edison Co. of N.Y. v. FERC, 347 F.3d 964, 972 (D.C. Cir. 2003); PJM Interconnection, L.L.C., 161 FERC ¶ 61,252 (2017); Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004)) (“Fla. Gas”); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318 (2007); Midwest Indep. Transmission Sys. Operator, Inc., 117 FERC ¶ 61,113 (2006) (“Midwest ISO”).

 The PJM Show Cause Order is arbitrary and capricious, does not reflect reasoned decision-making, and is unsupported by substantial evidence in violation of the Administrative Procedure Act because the Commission did not develop a sufficient record to support defining “large load” or “electrically proximate large load” by reference to the interconnection customer’s point of interconnection.  State Farm, 463 U.S. at 43 (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”) (citation omitted); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th 265; Consol. Edison Co. of N.Y. v. FERC, 347 F.3d at 972; PJM Interconnection, L.L.C., 161 FERC ¶ 61,252; Fla. Gas, 604 F.3d at 639 (quoting Pac. Gas & Elec. Co.

v. FERC, 373 F.3d at 1319); PJM Interconnection, L.L.C., 119 FERC ¶ 61,318; Midwest ISO, 117 FERC ¶ 61,113.

12 18 C.F.R. § 385.713(c)(1), (c)(2).

PDF page 5

5
B. Arguments
1. The Commission Should Clarify That the Proposed Definition of
“Large Load” in the Show Cause Order Does not Limit PJM and the
PJM Transmission Owners From Proposing Additional Service-
Specific Criteria for the Services Contemplated in the Order.
In the PJM Show Cause Order, the Commission preliminarily found that the PJM Tariff appears unjust and unreasonable because it lacks certain provisions governing the process to provide transmission service to Eligible Customers on behalf of large loads, including a definition of large load, as a new category of load.  The Commission further stated that, based on the ANOPR record, it would be reasonable to define a large load as a new commercial or industrial customer at a single site, behind one or more points of interconnection, with a peak load of 50 MW or greater, interconnected at a voltage above 69 kV, and not part of a co-location arrangement.  The Commission therefore directed PJM either to show cause why the PJM Tariff remains just and reasonable without such a definition or to propose tariff revisions establishing its own definition of large load.

The Commission should clarify that this definition, including the 50 MW threshold, does not limit PJM or the PJM Transmission Owners from proposing additional criteria or reasonable distinctions between large load customers for purposes of designing and implementing the products addressed in the Order.  It may not be appropriate to offer identical services to all large load customers.  For instance, considerations such as seasonality versus peak load measurements and functional distinctions between types of customers (e.g., hyperscale computational loads versus “traditional” manufacturing and commercial customers) may merit distinctions in how different products are designed, offered and priced.  The Commission therefore should clarify that the proposed large load definition does not prejudge the appropriate criteria for every other purpose under the PJM Tariff.

PDF page 6

6
If the Commission declines to adopt this clarification, the Commission should grant rehearing.  The PJM Show Cause Order fails to justify a conclusion that the proposed large load definition requires that every customer meeting the definition of large load must be offered the same services under the same rates, terms and conditions.13  To the contrary, requiring a one-size- fits all approach for all large load customers with respect to each new service is likely to undermine the goals of the Show Cause Order, particularly the desire for speed-to-power. As the PJM Transmission Owners explained in their comments on the ANOPR, an overly inclusive definition of “large load” risks repeating the same flaws that occurred with inflated generation interconnection queues.14  It is therefore of critical importance that PJM and the PJM Transmission Owners have sufficient flexibility to design and implement services with appropriate criteria that account for meaningful differences between large load customers.  Limiting this flexibility would be arbitrary, capricious, and would not reflect reasoned decision-making.

2. The Commission Should Clarify That “Large Load” and “Electrically
Proximate Large Load” Need not be Defined Based on the Point of
Interconnection.
As noted above, the Commission indicated in the PJM Show Cause Order that it would be reasonable to define a large load as a new commercial or industrial customer at a single site, behind one or more points of interconnection.15  Similarly, in discussing potential rules and procedures relating to “electrically proximate large load,” the Commission found that it would be reasonable to define “electrically proximate large load” as a large load that is sufficiently electrically close to the interconnection customer’s requested point of interconnection such that, with the exception of the transmission facilities between the two, the impact on the transmission system of the

13 PJM Show Cause Order at P 58.
14 Indicated PJM Transmission Owners Comments, Docket No. RM26-4-000, at 4-9 (filed Nov. 21, 2025).
15 PJM Show Cause Order at n.2.

PDF page 7

7
combination of the generating facility and load will be effectively the same as if they were located at the same substation.16

The Commission should clarify that in any Section 205 filing or other response to the PJM Show Cause Order, PJM and/or the PJM Transmission Owners are not limited to defining “large load” or “electrically proximate large load” based on reference to the point of interconnection, and that they will have sufficient flexibility to propose other points of reference, such as the Point of Change of Ownership.  Given the significant detail that the Show Cause Order leaves to PJM and the PJM Transmission Owners to develop as to what constitutes electrical proximity and other aspects of the Show Cause Order’s proposal, it is crucial that PJM and the PJM Transmission Owners have maximum flexibility to ensure speed-to-power, reliability, and customer protection goals are met.  Indeed, the Commission has already been presented, in the related co-located load proceeding, with evidence that the point of interconnection frequently is an imprecise boundary insofar as it may unreasonably conflate customer-owned facilities with those owned by other entities, including Transmission Owner-owned facilities.17  In that proceeding, PJM and the PJM Transmission Owners provided evidence that the definition of “Co-Located Load” should be based on the Point of Change in Ownership,18 rather than the Point of Interconnection because it reflects the legal and operational boundary between customer-owned facilities and transmission owner facilities and avoids sweeping in transmission owner interconnection facilities into the definition

16 Id. at P 94.
17 See PJM 30-Day Compliance Filing, Docket No. ER26-1088-000, at 3 & n.14 (filed Jan. 20, 2026) (“30-Day Compliance Filing”); see also PJM Transmission Owners Request for Rehearing or Clarification, Docket No. ER26- 1088-000, at 4-8 (filed May 18, 2026); PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at PP 27-28 (2026).
18 PJM defined “Point of Change in Ownership” in Tariff, Part VIII, Subpart A, section 400, Definitions P, is the point at which “the Project Developer’s Interconnection Facilities connect to the Transmission Owner’s Interconnection Facilities.”  See 30-Day Compliance Filing at n.14.

PDF page 8

8
of large load.19  The Commission has, to date, rejected PJM’s proposal to define Co-Located Load based on the Point of Change of Ownership because PJM did not seek rehearing or clarification of the Commission’s order in the separate co-located load proceeding in which it adopted that definition.20  That rejection is inapt here because the services that the Commission is proposing in the Show Cause Order involve different customers (i.e., Co-Located Load customers versus other types of large load customers), and thus, PJM and the PJM Transmission Owners cannot be limited in responding to Show Cause Order based on the Co-Located Load dockets.

Furthermore, the PJM Transmission Owners are not asking the Commission to decide at this time in this proceeding whether the point of interconnection or some other criteria should be used to define “large loads” or “electrically proximate large loads.”  Nevertheless, the Commission should clarify that the PJM Show Cause Order does not require reference to the point of interconnection, and that PJM and the PJM Transmission Owners may, in a Section 205 filing or other response to the Order, propose other criteria, subject of course to showing they are just and reasonable.  If the Commission declines to grant this clarification, it should grant rehearing on this issue.  The PJM Show Cause Order does not explain why the point of interconnection is the appropriate criterion for PJM, as opposed to other metrics such as ownership, delivery configuration, voltage, or operational effect on the transmission system.  Any determination that a large load customer or electrically proximate large load customer must be defined based only on reference to the point of interconnection is therefore not based on reasoned decision-making and is not supported by substantial evidence.

19 See 30-Day Compliance Filing at 3 & n.14; see also PJM 60-Day Compliance Filing, Docket No. ER26- 1479-000, at 32 (filed Feb. 23, 2026).
20 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at P 27.

PDF page 9

9
II. CONCLUSION
For the foregoing reasons, the PJM Transmission Owners respectfully request that the Commission grant rehearing of the PJM Show Cause Order for the reasons set forth herein, or, alternatively, clarify the Order as set forth in Section I.

Respectfully submitted,

/s/ Michael Kunselman

Michael Kunselman

Richard P. Sparling

Nicholas J. Cicale

Jonathan A. Namazi

Davis Wright Tremaine LLP

1301 K Street NW

Suite 500 East

Washington, DC 20005

Counsel for the FirstEnergy

  Companies

On behalf of the Indicated PJM

  Transmission Owners

Dated:  July 20, 2026

PDF page 10

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., this 20th day of July 2026.

/s/ Deiman Flores
Deiman Flores
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005