EL26-67-001 · 2026-07-20 · Indicated PJM Transmission Owners

The Indicated PJM Transmission Owners submit Request for Clarification, or in the Alternative, Rehearing of the 06/18/2026 Order

The Indicated PJM Transmission Owners request clarification, or rehearing, that the E-7 order's proposed 50 MW large load definition allows added service-specific criteria and need not be tied to the point of interconnection.

Asks FERC to: Clarify that the large load definition does not bar service-specific criteria and that PJM may define large and electrically proximate load by other reference points such as the Point of Change of Ownership, or grant rehearing.

Rehearing and clarification request on how the E-7 order defines a large load (50 MW, above 69 kV) and an electrically proximate load, the definitional starting point for the study process directive.

E-12 NYISO: Define ‘large load’ (P 64, p. 41) E-7 PJM: Application / study process (P 6(a), p. 7)

Key points

  1. The Transmission Owners say the 50 MW definition should not prevent added criteria for the services the order contemplates.
    does not limit PJM or the PJM Transmission Owners from proposing additional criteria or reasonable distinctions between large load customers for purposes of designing and implementing the products addressed in the Order. PDF p. 5
  2. They warn a one-size-fits-all approach would be over-inclusive and undermine speed-to-power, repeating the inflated generation queue problem.
    an overly inclusive definition of “large load” risks repeating the same flaws that occurred with inflated generation interconnection queues. PDF p. 6
  3. They cite hyperscale computational load versus traditional customers as a distinction that may justify differently designed and priced products.
    functional distinctions between types of customers (e.g., hyperscale computational loads versus “traditional” manufacturing and commercial customers) may merit distinctions in how different products are designed, offered and priced. PDF p. 5
  4. They ask to define large and electrically proximate load by reference points other than the point of interconnection, such as Point of Change of Ownership.
    they will have sufficient flexibility to propose other points of reference, such as the Point of Change of Ownership. PDF p. 7
  5. They say they are not asking FERC to pick the criterion now, only to keep the point of interconnection from being required.
    the PJM Transmission Owners are not asking the Commission to decide at this time in this proceeding whether the point of interconnection or some other criteria should be used PDF p. 8
Contents · 5 sections
  1. I. requests for CLARIFICATION AND rehearing p. 4
  2. A. Statement of Issues and Specification of Errors p. 4
  3. B. Arguments p. 5
  4. 2. The Commission Should Clarify That “Large Load” and “Electrically Proximate Large Load” Need not be Defined Based on the Point of Interconnection. p. 6
  5. II. Conclusion p. 9

Read topic-matched comments in EL26-67

Topics in the text: Filing procedure · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

RM26-4-000 (issued Oct. 27, 2025). 7 PJM Show Cause Order at PP 3, 35. 8 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff. 9 PJM Show Cause Order at PP 3, 35. 3 Commission directed PJM either to justify the absence of such provisions or…
Read this passage Filed comments: Cost allocation

I. requests for CLARIFICATION AND rehearing

PDF bookmark · Topic match: Filing procedure

REQUESTS FOR CLARIFICATION AND REHEARING
Read this passage

A. Statement of Issues and Specification of Errors

PDF bookmark

Co., 463 U.S. 29, 43 (1983) (an agency “must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”) (citation omitted) (“State Farm”); Consol.
Read this passage

B. Arguments

PDF bookmark · Topic match: Filing procedure

The PJM Show Cause Order fails to justify a conclusion that the proposed large load definition requires that every customer meeting the definition of large load must be offered the same services under the same rates, terms and conditions.13 To the contrary, requiring a one-size- fits all approach…
Read this passage

2. The Commission Should Clarify That “Large Load” and “Electrically Proximate Large Load” Need not be Defined Based on the Point of Interconnection.

PDF bookmark · Topic match: Connecting load and generation

Any determination that a large load customer or electrically proximate large load customer must be defined based only on reference to the point of interconnection is therefore not based on reasoned decision-making and is not supported by substantial evidence. 19 See 30-Day Compliance Filing at 3 &…
Read this passage Filed comments: Connecting load and generation

II. Conclusion

PDF bookmark · Topic match: Filing procedure

CONCLUSION For the foregoing reasons, the PJM Transmission Owners respectfully request that the Commission grant rehearing of the PJM Show Cause Order for the reasons set forth herein, or, alternatively, clarify the Order as set forth in Section I.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 20th day of July 2026. /s/ Deiman Flores Deiman Flores Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005