EL26-68-000 · 2026-07-22 · Southwest Power Pool, Inc.
Answer of Southwest Power Pool, Inc. in opposition to Motion for the Establishment of Settlement Procedures and Convening of a Settlement Conference, or, in the Alternative, for the Appointment of a Settlement Judge of L.M. Marlowe
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Southwest Power Pool, Inc.
)
Docket No.
EL26-68-000
)
ANSWER OF
SOUTHWEST POWER POOL, INC.
Pursuant to Rules 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (the “Commission” or “FERC”), 18 C.F.R. §§ 385.213, Southwest Power Pool, Inc. (“SPP”) submits this answer to the Motion for the Establishment of Settlement Procedures and Convening of a Settlement Conference, or, in the Alternative, for the Appointment of a Settlement Judge of L.M. Marlowe (“Movant”)1 filed in this proceeding. The Commission should deny the Marlowe Motion as described below and allow SPP to move forward with responding to the Commission with regional solutions to the issues outlined in this docket.
1 Motion for Establishment of Settlement Procedures and Convening of a Settlement Conference, or, in the Alternative, for the Appointment of a Settlement Judge of L.M. Marlowe, Docket No. EL26-68-000 (July 8, 2026) (“Marlowe Motion”). L.M. Marlowe is also known as Lisa Melton.
PDF page 2
2
I. BACKGROUND
On June 18, 2026, the Commission issued show cause orders to SPP2 and all other regional transmission organizations and independent system operators (collectively “Show Cause Orders”).3 Each of the Show Cause Orders are tailored specifically to each of the six regional grid operators under the Commission’s jurisdiction. In the Show Cause Orders, the Commission directed each regional grid operator and its transmission owners to, within sixty (60) days, justify why their current tariffs remain just and reasonable in the absence of clear and consistent provisions for large load customers or, alternatively, to propose changes.4 Numerous entities have filed motions to intervene in the Show Cause Orders dockets.
In the Marlowe Motion, the Movant requests that the Commission: (1) establish settlement procedures and convene a settlement conference of the participants pursuant to Rule 601 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.601; or in the alternative, and if the if the Commission finds settlement-judge procedures appropriate, appoint a settlement judge pursuant to Rule 603 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.603, to facilitate settlement of the matters 2
Sw. Power Pool, Inc., 195 FERC ¶ 61,213 (2026) (“SPP Show Cause Order”). The Show Cause Order directed SPP to provide, within thirty days, a detailed informational report.
3 See, PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026); N.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216 (2026); Midcontinent Indep. Sys. Operator, Inc., 195 FERC ¶ 61,212 (2026); California Independent System Operator Corporation, 195 FERC ¶ 61,214 (2026); ISO New England Inc., 195 FERC ¶ 61,215 (2026).4 SPP Show Cause Order at P 3.
PDF page 3
3
presented.5 The Movant claims, without justification or legal support, that the establishment of settlement proceedings in these dockets would allow the participants in these dockets of the Show Cause Orders the ability “to work toward mutually acceptable reliability, observability, and cost-allocation methodologies under the guidance of a neutral, rather than through protracted contested proceedings alone.”6 Of note, through the Movant’s Marlowe Motion and other filings in the docket, the Movant’s interest in the proposed settlement procedures appears to be based, at least in part, on the Movant’s own commercial interests.7 As stated in the Marlow Motion, the “Movant is the author and rights-holder of a framework responsive to these questions, and seeks its consideration.”8 These commercial interests provide no basis to support a nationwide settlement proceeding.
On July 15, 2026, the Southwest Power Pool Transmission Owner Group filed an answer in response to the Marlowe Motion.9 Although not responding to the SPP TO Group
5 Marlow Motion at 1.6 Marlowe Motion at 1.7 See Marlowe Motion at 1; see also, Supplemental Technical Comment and Reservation of Rights of L.M. Marlowe at 1-2 (July 8, 2026) (“Commenter is an independent author and developer of a published, timestamped analytical framework addressing deterministic reliability invariants, real-time observability of computational load behavior, dependency mapping, and the allocation of reliability and capacity burdens created by large computational loads. Commenter’s published work — including the Architecture of Dependency and Autonomy™, the MARLOWE™ Invariant-Based Diagnostic Framework, Intent-Aware Telemetry™, Continuous Invariant Validation™, Execution Sovereignty™, and the associated Ghost Load™ dependency analysis — bears directly on the reliability and cost-causation questions presented in these dockets.”)8 Marlowe Motion at 2.9 Answer of the Southwest Power Pool Transmission Owner Group, EL26-68-000, et al. (July 15, 2026) (“SPP TO Group Answer”).
PDF page 4
4
Answer in this filing, SPP supports the SPP TO Group Answer in its request for the Commission to deny the Marlowe Motion as being premature and a profound disruption the Commission’s well-reasoned decision to address the challenge of large load additions on a regional basis through Show Cause Orders.
II. ANSWER
A. The Motion Is Inconsistent with the Commission’s Regional Approach
As stated in the SPP Show Cause Order, the “[i]ndividual show cause proceedings will allow the Commission to ensure that solutions to the problems the Secretary [of the Department of Energy] identified are tailored to the specific, varied circumstances and market constructs of each region.”10 The Commission goes on to state that the Show Cause Orders “reveals the many ways in which those orders are customized for each market’s unique circumstances and progress (or lack thereof) towards serving large load…and “leave room for each market to tailor operational requirements for large loads that are particular to their region [] and otherwise account for incumbent regional differences on topics such as cost allocation and cost transparency, study processes, and network upgrade procedures..”11 The Commission found that “[p]roceeding via [the Show Cause Order] allow the markets (and their respective transmission owners) to explain, in the first instance, how to address the Commission’s concerns.” 12
The Movant’s request for the establishment of a nationwide settlement procedures and convening of a settlement conference to facilitate resolution all of dockets the
10 SPP Show Cause Order at P 6.11 Id. 12 Id. at P 7.
PDF page 5
5
Commission issued Show Cause Orders would contravene the ability for each of the regional grid operators to appropriately respond to the Commission’s Show Cause Orders as it relates to the just and reasonableness of each entities regional open access transmission tariff. Because of the vast regional differences in such things as cost allocation, cost transparency, study processes, network upgrades, and market operations, it would be impossible to resolve all the issues presented by the Commission in the Show Cause Orders in a single settlement proceeding.
Although Movant in the Marlowe Motion claims that the Commission’s
establishment of a nationwide settlement proceeding would be timelier resolution than “protracted contested proceedings,”13 the Movant provides no justification to this claim. In reality, it would be impracticable, if not impossible, to effectively manage settlement proceedings involving the hundreds of parties that are expected to participate in the Show Cause Order proceedings. SPP and its stakeholders’ time is better spent working together on solutions to potential issues outlined in the SPP Show Cause Order rather than being required to participate in convoluted national settlement proceedings that will not result in solutions specific to the SPP region.
There is simply no basis provided in the Marlowe Motion for the Commission to grant the Movant request. Although the Commission has the discretion whether to establish settlement procedures, hold a settlement conference, or appoint a settlement judge, nothing in the Commission’s rules requires that action.14 This is especially the case when the 13
Marlowe Motion at 2.
14 18 C.F.R. § 385.601(a) (“The Commission…may convene a conference of the participants in a proceeding at any time for any purpose related to the conduct or
PDF page 6
6
settlement procedures would be detrimental to regional solutions the Commission desires from its findings in the Show Cause Orders.
B. The Motion is Premature
The Commission has only recently instituted these proceedings. Pursuant to the SPP Show Cause Order, SPP is currently evaluating the issues identified by the Commission and preparing its response. The Commission specifically afforded SPP the opportunity to utilize its stakeholder process to develop potential tariff revisions and, if appropriate, request additional time to do so. That process has not yet run its course. Because no proposed tariff revisions have been filed and no administrative record has been developed, there is presently no concrete controversy suitable for settlement. Settlement procedures are designed to facilitate resolution of identified disputes—not to substitute for the initial development of proposals that may ultimately become the subject of Commission review. Granting the Motion at this early stage would invert the ordinary sequence contemplated by Sections 205 and 206 of the FPA by requiring settlement discussions before parties have articulated the proposals that might ultimately require resolution. Finally, Although Rules 601 and 603 of the Commission’s Rules of Practices and Procedure authorize the Commission to convene settlement procedures or appoint a settlement judge, those rules are discretionary rather than mandatory. The Motion identifies no extraordinary circumstance warranting departure from the Commission's recently established procedural framework. General concerns regarding reliability and large load integration—issues that motivated issuance of the Show Cause Order itself—do not disposition of the proceeding, including submission and consideration of offers of settlement or the use of alternative dispute resolution procedures.”).
PDF page 7
7
establish that settlement is appropriate before the Commission has received the very responses it directed the regional transmission organizations to prepare. Moreover, to the extent the Motion seeks consideration of the movant's own technical framework, intellectual property, or proposed methodologies, those matters may be presented through the ordinary comment and stakeholder processes available in these proceedings. They do not provide a basis for compelling Commission-supervised settlement involving all participants.
II. CONCLUSION
SPP respectfully requests that the Commission accept this Answer and deny and dismiss the Marlowe Motion.
Respectfully submitted,
/s/ Justin A. Hinton
Justin A. Hinton
Senior Attorney
Meredith Powell
Attorney
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
(501) 482-2468
jhinton@spp.org
Attorney for Southwest Power Pool, Inc.
Dated: __________
July 22, 2026
PDF page 8
CERTIFICATE OF SERVICE
I hereby certify that I have on this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Little Rock, Arkansas, this _________ day of July, 2026.
/s/ Cassie Butler
Cassie Butler
Southwest Power Pool, Inc.
201 Worthen Drive
Little Rock, AR 72223-4936
(501) 614-3200
22nd