EL26-68-000 · 2026-07-22 · Southwest Power Pool, Inc.

Answer of Southwest Power Pool, Inc. in opposition to Motion for the Establishment of Settlement Procedures and Convening of a Settlement Conference, or, in the Alternative, for the Appointment of a Settlement Judge of L.M. Marlowe

SPP answers L.M. Marlowe's motion for a settlement conference or settlement judge in EL26-68 and asks FERC to deny and dismiss it as inconsistent with the regional approach, premature, and tied to the movant's own commercial interests.

Asks FERC to: Accept this answer and deny and dismiss the Marlowe motion.

Defends the E-9 SPP show cause design, in which SPP prepares its response and a 30-day informational report, against a request for nationwide settlement procedures.

E-9 SPP: Show cause or propose tariff changes in 60 days (p. 5) E-9 SPP: 30-day report on serving large loads with adequate generation (p. 7)

Key points

  1. SPP says the motion conflicts with the show cause orders' tailoring to each region.
    Because of the vast regional differences in such things as cost allocation, cost transparency, study processes, network upgrades, and market operations, it would be impossible to resolve all the issues presented by the Commission in the Show Cause Orders in a single settlement proceeding. PDF p. 5
  2. SPP supports the SPP TO Group's answer that the motion is premature.
    SPP supports the SPP TO Group Answer in its request for the Commission to deny the Marlowe Motion as being premature PDF p. 4
  3. SPP argues no controversy exists yet because no tariff revisions or record exist.
    Because no proposed tariff revisions have been filed and no administrative record has been developed, there is presently no concrete controversy suitable for settlement. PDF p. 6
  4. SPP says the movant's own framework can be presented through ordinary comment and stakeholder processes.
    those matters may be presented through the ordinary comment and stakeholder processes available in these proceedings. PDF p. 7
Contents · 5 sections
  1. I. BACKGROUND p. 2
  2. II. ANSWER p. 4
  3. A. The Motion Is Inconsistent with the Commission’s Regional Approach p. 4
  4. B. The Motion is Premature p. 6
  5. II. CONCLUSION p. 7

Read topic-matched comments in EL26-68

Topics in the text: Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) Docket No.
Read this passage

I. BACKGROUND

printed heading

In the Marlowe Motion, the Movant requests that the Commission: (1) establish settlement procedures and convene a settlement conference of the participants pursuant to Rule 601 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.601; or in the alternative, and if the if the…
Read this passage

II. ANSWER

printed heading

II.
Read this passage

A. The Motion Is Inconsistent with the Commission’s Regional Approach

printed heading · Topic match: Cost allocation

Because of the vast regional differences in such things as cost allocation, cost transparency, study processes, network upgrades, and market operations, it would be impossible to resolve all the issues presented by the Commission in the Show Cause Orders in a single settlement proceeding.
Read this passage

B. The Motion is Premature

printed heading

The Motion is Premature The Commission has only recently instituted these proceedings.
Read this passage

II. CONCLUSION

printed heading

CONCLUSION SPP respectfully requests that the Commission accept this Answer and deny and dismiss the Marlowe Motion.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Little Rock, Arkansas, this _________ day of July, 2026. /s/ Cassie Butler Cassie Butler Southwest Power Pool, Inc. 201 Worthen Drive Little Rock, AR 72223-4936 (501) 614-3200 22nd
Read this passage