EL26-67-000 · 2026-07-22 · Allegheny Electric Cooperative, Inc.

Motion to Rescind Show Cause Order of Allegheny Electric Cooperative, Inc

Allegheny Electric Cooperative, a non-profit G&T cooperative and PJM transmission owner, moves FERC to rescind the E-7 show cause order as to it because it is not a public utility under FPA section 201(f).

Asks FERC to: Rescind the PJM show cause order against Allegheny as a non-public utility and waive any notice and comment periods.

Seeks removal of one non-jurisdictional transmission owner from the E-7 show cause order's list of respondents, the same issue FERC fixed in its August 13 errata.

E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7)

Key points

  1. Allegheny says it is owned by its members and is not a public utility subject to FERC jurisdiction.
    Allegheny is not a public utility subject to FERC jurisdiction, pursuant to Section 201(f) of the Federal Power Act. PDF p. 3
  2. FERC exempted other non-public-utility owners from the order while keeping authority over their tariff provisions through PJM.
    it retains the authority to review each of these entities’ tariff provisions as a component of PJM’s Tariff in an order to show cause directed towards PJM PDF p. 4
  3. Allegheny cites the CAISO order's offer to rescind at a non-public utility's request and notes its PJM tariff portions contain no interconnection processes.
    we will rescind the show cause order against them at their request PDF p. 4
  4. Allegheny asks for rescission and a waiver of notice and comment periods.
    respectfully requests that the Commission rescind the PJM Show Cause Order against it, as a non-public utility PDF p. 5
Contents · 4 sections
  1. I. DESCRIPTION OF ALLEGHENY p. 2
  2. II. RELEVANT BACKGROUND p. 3
  3. III. JUSTIFICATION FOR RESCISSION p. 3
  4. IV. CONCLUSION p. 5

Read topic-matched comments in EL26-67

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. DESCRIPTION OF ALLEGHENY

printed heading

DESCRIPTION OF ALLEGHENY Allegheny, the owner of transmission facilities turned over to the operational control of PJM Interconnection, L.L.C. (“PJM”) and thus a PJM transmission owner (“PJM TO”), is a non-profit electric generation and transmission cooperative (“G&T Cooperative”) corporation,…
Read this passage

II. RELEVANT BACKGROUND

printed heading

RELEVANT BACKGROUND On June 18, 2026, the Commission issued the PJM Show Cause Order, thereby initiating a proceeding under Section 206 of the Federal Power Act.
Read this passage

III. JUSTIFICATION FOR RESCISSION

printed heading

In requesting rescission of the Show Cause Order as to it, Allegheny acknowledges the Commission’s authority to review the Allegheny-specific provisions of the Tariff and pledges to cooperate with PJM, to the extent that PJM requests assistance from Allegheny, in crafting its response.
Read this passage

IV. CONCLUSION

printed heading

CONCLUSION For the reasons indicated above, Allegheny respectfully requests that the Commission rescind the PJM Show Cause Order against it, as a non-public utility, and asks that the Commission waive any notice and comment periods that might be applicable to this motion.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, DC, this 22nd day of July, 2026. /s/ Joshua E.