EL26-67-000 · 2026-07-28 · Indicated PJM Transmission Owners

Motion for Abeyance of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL26-67-000
MOTION FOR ABEYANCE OF THE INDICATED PJM TRANSMISSION OWNERS
AND REQUEST FOR EXPEDITED ACTION
AND SHORTENED COMMENT PERIOD
Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission’s (“Commission” or “FERC”),1 the Indicated PJM Transmission Owners (“PJM Transmission Owners”)2 respectfully move to hold the deadline to respond in the above- captioned proceeding in abeyance for 90 days, until November 16, 2026.3  Good cause exists to grant this motion because doing so will provide the PJM Transmission Owners adequate time to determine the appropriate additions and revisions to the PJM Open Access Transmission Tariff (“PJM Tariff”) and submit one or more filings pursuant to section 205 of the Federal Power Act

1 18 C.F.R. § 385.212 (2025).
2 The Indicated PJM Transmission Owners are:  American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland Electric Cooperative. 3 See PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,211, at 39 & n.111 (2026) (explaining that the Commission will consider requests for full or partial abeyance of up to 90 days, including requests to hold in abeyance the deadline to respond) (“Show Cause Order”).  November 16 is the first business day after the end of the 90-day abeyance period.

PDF page 2

2
(“FPA”) in response to the Commission’s Show Cause Order.  The PJM Transmission Owners further request a shortened comment period of five (5) days to facilitate the Commission issuing an order granting the motion to hold the deadline to respond in abeyance no later than August 10, 2026.

I. BACKGROUND
On June 18, 2026, the Commission issued a show cause order under section 206 of the FPA to PJM, together with its transmission owners, directing PJM and the PJM Transmission Owners to justify or reform the tariff provisions governing how large loads connect to and receive service from the transmission system.4

The Show Cause Order preliminarily found that the PJM Tariff appeared to be unjust, unreasonable, or unduly discriminatory or preferential because of a lack of sufficiently clear and consistent provisions to address service for large loads and related configurations.5 The Commission therefore directed PJM and its transmission owners, within 60 days, to show cause why the PJM Tariff remains just and reasonable without provisions addressing:  (1) the application process, study procedures, and ongoing operational requirements for Eligible Customers seeking transmission service on behalf of large loads; (2) additional transparency concerning Network Upgrade costs for such service, together with the absence of a pro forma cost recovery agreement and a mechanism to ensure related payments are properly credited to transmission owners’ revenue requirements; (3) transmission service options tailored to flexible large loads willing and able to limit their use of the transmission system under certain conditions; and (4) rates, terms, and conditions applicable to interconnection customers serving “electrically proximate large load” or

4 Show Cause Order at PP 3, 35.
5 Id.

PDF page 3

3
co-located load.6  The Commission directed PJM either to justify the absence of such provisions or to propose PJM Tariff revisions addressing those concerns.7

The Show Cause Order indicated that the Commission would consider requests from PJM and/or transmission owners to hold all or certain aspects of the FPA section 206 proceeding in abeyance, for up to 90 days, including the August 17, 2026, deadline to respond.8  The Commission explained that the purpose of such an abeyance would be to provide PJM and the PJM Transmission Owners time while they work through the stakeholder process to develop FPA section 205 filings to revise the PJM Tariff to address the issues raised in the Show Cause Order.9

II. MOTION TO HOLD DEADLINE TO RESPOND IN ABEYANCE
Consistent with the Commission’s directives in the Show Cause Order,10 the PJM Transmission Owners respectfully request that the Commission hold the deadline to respond in this proceeding in abeyance for a 90-day period, until November 16, 2026.  Good cause exists to grant this motion because doing so will allow the PJM Transmission Owners to address, through one or more FPA section 205 filings, the issues identified by the Commission in the Show Cause Order.  The PJM Transmission Owners anticipate that the FPA section 205 filings submitted by PJM and the PJM Transmission Owners will address the issues identified by the Commission in the Show Cause Order.  The PJM Transmission Owners will submit their FPA section 205 filing(s)

6 Id.
7 Id.
8 Id. at P 39.  Because 60 days from issuance of the Show Cause Order falls on a Saturday, the deadline to respond does not end until the close of business on Monday, August 17.  See 18 C.F.R. § 385.2007(a)(2).
9 Show Cause Order at P 39.
10 Id.

PDF page 4

4
by no later than November 16, 2026, which is the date 90 days after the deadline to respond to the Show Cause Order.11

As the Commission has recognized, the PJM Transmission Owners have exclusive and
unilateral rights regarding regional rates and rate design under the PJM Tariff and the cost allocation provisions of Schedule 12 of the PJM Tariff.12  Consistent with this obligation, the PJM Transmission Owners anticipate that their FPA section 205 filing(s) will contain a pro forma cost recovery agreement(s), as well as rates for new transmission services for “flexible large loads” and “electrically proximate large loads or co-located loads.”  The PJM Transmission Owners’ filing(s) would include any financial penalties applied to customers that fail to meet their contractual service limits with respect to any new transmission services.  The PJM Transmission Owners are also considering whether the transparency findings in the Show Cause Order may require modifications to the PJM Transmission Owners’ local planning procedures, such as Attachment M-3 to the PJM Tariff.  These items are discussed in greater detail below.

The PJM Transmission Owners have already begun these efforts in earnest, but a 90-day abeyance is necessary to allow the PJM Transmission Owners sufficient time not only to develop these PJM Tariff provisions, but to also provide PJM and PJM stakeholders an adequate opportunity to review these provisions, and for the PJM Transmission Owners to consider any

11 See id. (“The Commission will consider requests from PJM and/or the Transmission Owners to hold, for up to 90 days, all or certain aspects of this FPA section 206 proceeding in abeyance, including the deadline to respond to this order.”) (emphasis added).
12 See Pa.-N.J.-Md. Interconnection, 105 FERC ¶ 61,294 (2003), order on compliance, 108 FERC ¶ 61,033 (2004) (approving Settlement Agreement, Docket Nos. OA97-261-006, et al. (filed Oct. 3, 2003), as modified, Modification of Settlement Agreement, Docket Nos. OA97-261-009, et al., §§ 3.2, 4.2(B); 4.3, 4.5 (filed Jan. 20, 2004 and corrected Jan. 23, 2004)).  The Settlement Agreement is incorporated into PJM OATT, § 9 and the Consolidated Transmission Owners Agreement (“CTOA”) at § 7.3.1, PJM Interconnection, L.L.C., Rate Schedules, TOA, TOA-42 Rate Schedule FERC No. 42 (1.0.0).

PDF page 5

5
feedback received.13  Moreover, the PJM Transmission Owners will be actively working with PJM during this time on the development of non-rate terms and conditions of the new services and processes addressed in the Show Cause Order.

A. Development of a Pro Forma Cost Recovery Agreement
In the Show Cause Order, the Commission preliminarily found that PJM’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers.14  The Commission indicated it was concerned about the apparent lack of a pro forma cost recovery agreement to help ensure that Eligible Customers taking transmission service on behalf of large loads bear the risk and are ultimately responsible for costs incurred to provide transmission service, including the cost of Network Upgrades.15 The Commission noted that such an agreement would require “the Eligible Customer to make a minimum contribution toward the transmission owner’s transmission revenue requirement, if the Eligible Customer ultimately takes less transmission service than anticipated because the large load does not materialize as planned or is not developed at all.”16  The Commission stated its finding is not intended to alter or call into question existing regional cost allocation methods for Network Upgrades, but instead is focused on helping to prevent cost shifting among transmission customers.17

13 The PJM Transmission Owners have a contractual obligation to engage in coordination and consultation with PJM and the PJM Members Committee with respect to changes to the PJM Tariff.  See CTOA at § 7.5.1.
14 Show Cause Order at P 66.
15 Id. at P 66.
16 Id. at P 81.
17 Id.

PDF page 6

6
As explained in their comments in the ANOPR proceeding,18 and acknowledged by the Commission in the Show Cause Order,19 a number of PJM Transmission Owners have already been active in developing bilateral retail and FERC-jurisdictional agreements with large load customers that include protections against cost shifting.20  Nevertheless, the PJM Transmission Owners acknowledge and appreciate the concerns raised by the Commission in the Show Cause Order regarding the need to ensure that costs are not inappropriately shifted from large load customers to other transmission customers.  To that end, the PJM Transmission Owners intend to develop and file a agreement or agreements to mitigate the risk of cost shifting among transmission customers and ensure eligible large load customers pay their share of system upgrades.  As the Show Cause Order recognizes, however, this involves working through and resolving a number of important issues, such as the interaction with and potential overlap between a pro forma cost recovery agreement and bilateral cost recovery agreements between utilities and retail customers, as well as the specific mechanism for determining each Eligible Customer’s required minimum contribution.  The PJM Transmission Owners are also considering the extent to which changes will be needed to each transmission owner’s individual transmission rates and/or other tariff provisions, such as the formula rates set forth in Attachment H to the PJM Tariff.

18 See Interconnection of Large Loads to the Interstate Transmission System, Advance Notice of Proposed Rulemaking, Docket No. RM26-4-000 (dated Oct. 23, 2025) (“ANOPR”); see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy, Docket No. RM26-4-000 (dated Oct. 23, 2025).
19 Show Cause Order at P 82 & n.159.
20 See e.g., PECO Energy Co., 195 FERC ¶ 61,074 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,181 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,183 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,184 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,185 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,106 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,109 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,110 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,113 (2026); PECO Energy Co., 193 FERC ¶ 61,148 (2025).

PDF page 7

7
B. Rate Design Related to Transmission Services for Large Loads
In the Show Cause Order, the Commission preliminarily found that the PJM Tariff appears to be unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking transmission service on behalf of “flexible large loads” that are willing and able to limit their use of the transmission system under certain conditions.21 The Commission preliminarily found that new transmission services should be available to “flexible large loads” willing and able to limit their withdrawals, specifically the three new services it required for co- located loads:  (1) Interim Network Integration Transmission Service, (2) Firm Contract Demand, and (3) Non-Firm Contract Demand.22  The Commission also preliminarily found that the PJM Tariff appears to be unjust and unreasonable because it does not contain provisions allowing a generator interconnection customer to seek interconnection service(s) that reflect the operational dynamics of serving either:  (1) an “electrically proximate large load,” or (2) a co-located load.23 Because the PJM Transmission Owners have the FPA section 205 filing rights with respect to regional rates and rate design under the PJM Tariff, the PJM Transmission Owners’ section 205 filing(s) made in response to the Show Cause Order will include the rate-related provisions for any new transmission services that PJM offers to “flexible large load,” as well as any services applicable to “electrically proximate large load.”  The PJM Transmission Owners will also work to coordinate any proposal with the rate design proposals at issue in the PJM Co-Located Load proceeding24 for these new services, subject to the Commission’s directives on compliance set

21 Show Cause Order at P 86.
22 Id.
23 Id. at P 95.
24 See, e.g., Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions, Docket Nos. EL25-49-000, et al. (filed Feb. 23, 2026).

PDF page 8

8
forth in its June 18, 2026, order in that proceeding.25  However, even assuming this is the case, the PJM Transmission Owners will need sufficient time to carefully consider, in coordination with PJM and other interested stakeholders, what additions and modifications are necessary to adapt those rate proposals to new services available to Eligible Customers taking transmissions service on behalf of “flexible large loads” and/or “electrically proximate large loads.” In addition to the rates for new transmission services applicable to large loads, the PJM Transmission Owners will also be considering whether to propose financial penalties applicable to customers taking one or more of the new transmission services that fail to comply with their contractual withdrawal limits.  Again, the PJM Transmission Owners anticipate that they will be able to utilize much of the work done to develop the financial penalty proposal they filed in the PJM Co-Located Load proceeding, but similarly will need to work through the details of how that proposal will apply to other types of large load customers.

C. Transparency Obligations Related to Network Upgrades Needed for Large
Load Customers
In the Show Cause Order, the Commission preliminarily found that the PJM Tariff appears to be unjust and unreasonable because it does not contain provisions requiring the provision of data on PJM’s website:

in a single location, and in an easily accessible format that is searchable and allows users to filter the data, on transmission service requested by Eligible Customers on behalf of large loads, for Network Upgrades evaluated in the local transmission planning process that are needed to provide transmission service to Eligible Customers on behalf of those large loads, and the costs for those Network

Upgrades.26
25 PJM Interconnection, L.L.C., et al., 195 FERC ¶ 61,209 (2026).
26 Show Cause Order at P 71.

PDF page 9

9
The Commission preliminarily found cost transparency measures are needed to provide stakeholders with sufficient information and visibility regarding the Network Upgrades, and their associated costs, needed to provide transmission service to Eligible Customers on behalf of large loads.27

There are two workstreams here relevant to the PJM Transmission Owners.  First, the PJM Transmission Owners will be working closely with PJM to develop appropriate provisions to provide the level of transparency anticipated in the Show Cause Order.  The PJM Transmission Owners’ role here is key because they will be designing, developing, and constructing many of the Network Upgrades necessary to accommodate the interconnection of new large loads to the transmission system.  This effort will involve working through a number of important issues, including ensuring appropriate confidentiality protections, compliance with anti-trust laws, and updating, where applicable, websites and databases to house such information.28 Second, the PJM Transmission Owners are considering what, if any, PJM Tariff

modifications they will need to include in their own FPA section 205 filing(s) relating to transparency enhancements.  Under the CTOA, the PJM Transmission Owners retain their rights with respect to local transmission planning matters.29  If the PJM Transmission Owners determine that revisions to the PJM Tariff are needed with respect to local planning matters, such as the provisions of PJM Attachment M-3, the PJM Transmission Owners will include such provisions in their FPA section 205 filing(s) made in response to the Show Cause Order.

27 Id.
28 See, e.g., PJM, Project Status & Cost Allocation, https://www.pjm.com/planning/m/project-construction (last visited July 28, 2026).
29 See CTOA at §§ 5.2, 5.6.

PDF page 10

10
III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED
COMMENT PERIOD
The PJM Transmission Owners respectfully request expedited consideration of this motion for abeyance and request that the Commission issue an order granting the motion no later than August 10, 2026.  Expedited consideration and the issuance of order by that date will provide the PJM Transmission Owners sufficient assurance that they will have adequate time to develop and submit one or more FPA section 205 filings necessary to implement the rates, terms, and conditions necessary to address the Show Cause Order, as discussed above.  Expedited consideration will also allow the PJM Transmission Owners to focus their efforts on developing their FPA section 205 filing(s) rather than spending critical time preparing separate responses to the Show Cause Order. Consistent with this request, the PJM Transmission Owners also seek a shortened comment period on this motion for abeyance.  Specifically, the PJM Transmission Owners request that the Commission establish a comment period of five (5) days.  Good cause exists to grant a shortened comment period for the reasons set forth above.  Moreover, no party will be prejudiced as a result of granting a five (5) day comment period, as the additional time and certainty afforded by an expedited order will accrue to the benefit of stakeholders by providing the PJM Transmission Owners sufficient time to solicit and consider stakeholder feedback on their proposals.

PDF page 11

11
IV. CONCLUSION
For the reasons set forth above, the PJM Transmission Owners’ request that the Commission establish a five (5) day comment period for answers to this motion and issue, on or before August 10, 2026, an order granting the PJM Transmission Owners’ request to hold the deadline to respond in this proceeding in abeyance for 90 days, until November 16, 2026. Respectfully submitted,

/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling

Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
  Companies
On behalf of the Indicated PJM
  Transmission Owners
Dated:  July 28, 2026

PDF page 12

CERTIFICATE OF SERVICE
Under Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., this 28th day of July 2026.

/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005