EL26-67-000 · 2026-07-28 · Indicated PJM Transmission Owners

Motion for Abeyance of the Indicated PJM Transmission Owners and Request for Expedited Action and Shortened Comment Period

The Indicated PJM Transmission Owners move to hold their response deadline in the E-7 show cause proceeding in abeyance for 90 days, to November 16, 2026, so they can prepare section 205 filings on cost recovery agreements, new service rates and transparency.

Asks FERC to: Hold the deadline to respond in abeyance until November 16, 2026, shorten the comment period to five days, and rule by August 10, 2026.

Seeks to move the E-7 60-day show cause deadline to November 16, 2026; FERC granted it on August 14. Describes the cost recovery, rate and transparency filings the Transmission Owners plan.

E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Cost-recovery agreement (P 77, p. 28) E-7 PJM: Cost transparency (P 71, p. 51) E-7 PJM: Service for flexible loads (P 85, p. 56)

Key points

  1. The Transmission Owners ask for a 90-day abeyance to November 16, 2026 to develop section 205 filings.
    respectfully move to hold the deadline to respond in the above- captioned proceeding in abeyance for 90 days, until November 16, 2026. PDF p. 1
  2. They expect to file a pro forma cost recovery agreement and rates for flexible and electrically proximate large load services, with penalties for exceeding contractual limits.
    will contain a pro forma cost recovery agreement(s), as well as rates for new transmission services for “flexible large loads” and “electrically proximate large loads or co-located loads.” PDF p. 4
  3. They say a cost recovery agreement raises open issues, including overlap with bilateral retail agreements and how to set each customer's minimum contribution.
    the specific mechanism for determining each Eligible Customer’s required minimum contribution. PDF p. 6
  4. They may revise local planning procedures such as Attachment M-3 to meet the order's transparency findings on Network Upgrade costs.
    considering what, if any, PJM Tariff modifications they will need to include in their own FPA section 205 filing(s) relating to transparency enhancements. PDF p. 9
  5. They ask FERC to rule by August 10 with a five-day comment period.
    request that the Commission establish a comment period of five (5) days. PDF p. 10
Contents · 7 sections
  1. I. BACKGROUND p. 2
  2. II. MOTION TO HOLD DEADLINE TO RESPOND IN ABEYANCE p. 3
  3. A. Development of a Pro Forma Cost Recovery Agreement p. 5
  4. B. Rate Design Related to Transmission Services for Large Loads p. 7
  5. C. Transparency Obligations Related to Network Upgrades Needed for Large p. 8
  6. III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED p. 10
  7. IV. CONCLUSION p. 11

Read topic-matched comments in EL26-67

Topics in the text: Filing procedure · Cost allocation · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

EL26-67-000 MOTION FOR ABEYANCE OF THE INDICATED PJM TRANSMISSION OWNERS AND REQUEST FOR EXPEDITED ACTION AND SHORTENED COMMENT PERIOD Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission’s (“Commission” or “FERC”),1 the Indicated PJM Transmission…
Read this passage

I. BACKGROUND

printed heading · Topic match: Filing procedure

BACKGROUND On June 18, 2026, the Commission issued a show cause order under section 206 of the FPA to PJM, together with its transmission owners, directing PJM and the PJM Transmission Owners to justify or reform the tariff provisions governing how large loads connect to and receive service from…
Read this passage Filed comments: Connecting load and generation

II. MOTION TO HOLD DEADLINE TO RESPOND IN ABEYANCE

printed heading · Topic match: Filing procedure

The PJM Transmission Owners have already begun these efforts in earnest, but a 90-day abeyance is necessary to allow the PJM Transmission Owners sufficient time not only to develop these PJM Tariff provisions, but to also provide PJM and PJM stakeholders an adequate opportunity to review these…
Read this passage

A. Development of a Pro Forma Cost Recovery Agreement

printed heading · Topic match: Cost allocation

Development of a Pro Forma Cost Recovery Agreement In the Show Cause Order, the Commission preliminarily found that PJM’s Tariff appears to be unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers.14 The Commission indicated…
Read this passage Filed comments: Cost allocation

B. Rate Design Related to Transmission Services for Large Loads

printed heading · Topic match: Connecting load and generation

Rate Design Related to Transmission Services for Large Loads In the Show Cause Order, the Commission preliminarily found that the PJM Tariff appears to be unjust and unreasonable because it does not include transmission services that reflect Eligible Customers taking transmission service on behalf…
Read this passage Filed comments: Connecting load and generation

C. Transparency Obligations Related to Network Upgrades Needed for Large

printed heading · Topic match: Cost allocation

Under the CTOA, the PJM Transmission Owners retain their rights with respect to local transmission planning matters.29 If the PJM Transmission Owners determine that revisions to the PJM Tariff are needed with respect to local planning matters, such as the provisions of PJM Attachment M-3, the PJM…
Read this passage Filed comments: Cost allocation

III. REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED

printed heading · Topic match: Filing procedure

REQUEST FOR EXPEDITED CONSIDERATION AND SHORTENED COMMENT PERIOD The PJM Transmission Owners respectfully request expedited consideration of this motion for abeyance and request that the Commission issue an order granting the motion no later than August 10, 2026.
Read this passage

IV. CONCLUSION

printed heading · Topic match: Filing procedure

CONCLUSION For the reasons set forth above, the PJM Transmission Owners’ request that the Commission establish a five (5) day comment period for answers to this motion and issue, on or before August 10, 2026, an order granting the PJM Transmission Owners’ request to hold the deadline to respond in…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 28th day of July 2026. /s/ Daniel Klein Daniel Klein Davis Wright Tremaine LLP 1301 K Street NW Suite 500 East Washington, DC 20005