EL26-67-000 · 2026-07-28 · Wabash Valley Power Association, Inc.

Wabash Valley Power Association, Inc. submits Request for Issuance of an Errata to the 06/18/2026 Order Instituting Proceedings Under Section 206 of the Federal Power Act

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.

AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Appalachian Power Company

Atlantic City Electric Company
Baltimore Gas and Electric Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. Dayton Power and Light Company

Delmarva Power & Light Company
Duke Energy Kentucky, Inc.
Duke Energy Ohio, Inc.
Duquesne Light Company
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Indiana Michigan Power Company
Jersey Central Power & Light Company Kentucky Power Company

Keystone Appalachian Transmission Company Kingsport Power Company

Linden VFT, LLC
Mid-Atlantic Interstate Transmission, LLC Monongahela Power Company

Neptune Regional Transmission System, LLC NextEra Energy Transmission MidAtlantic Indiana, Inc. Ohio Power Company

Ohio Valley Electric Corporation
Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
The Potomac Edison Company
Potomac Electric Power Company
       Docket No. EL26-67-000

PDF page 2

2
Public Service Electric and Gas Company
Rockland Electric Company
Silver Run Electric, LLC
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Virginia Electric and Power Company
Wabash Valley Power Association, Inc.
Wheeling Power Company
WABASH VALLEY POWER ASSOCIATION, INC.
REQUEST FOR ISSUANCE OF AN ERRATA
To the Commission:
On June 18, 2026, the Commission issued its “Order Instituting Proceeding Under Section 206 of the Federal Power Act” in this above captioned proceeding.1  In its Order, the Commission found that PJM Interconnection, L.L.C.’s (“PJM”) existing Open Access Transmission Tariff (“Tariff”) appears to be unjust, unreasonable, or unduly discriminatory or preferential and thereafter directed PJM and forty-five (45) Participating Transmission Owners (“PTOs”) within PJM to show cause with respect to a variety of concerns related to large load or co-located load transmission and interconnection within sixty (60) days of the date of its Order.2 Wabash Valley Power Association, Inc. (“WVPA”) has identified a procedural issue with the Order and respectfully requests that the Commission issue an errata as soon as practicable.

1 PJM Interconnection, L.L.C., et al, 195 FERC ¶ 61,211 (June 18, 2026) (the “Order”).
2 Id. at P 3.

PDF page 3

3
Before addressing the procedural issue presented below, WVPA desires to clarify that it does not dispute the need for the Commission to address issues surrounding service to large load and co-located load within organized markets and elsewhere.  Further, WVPA acknowledges the Commission’s existing precedent regarding non-jurisdictional entities with certain rate schedules within a jurisdictional RTO or ISO.

The Commission included WVPA as one of the PTOs in the caption of the Order. However, at footnote 13 of the Order, the Commission described which PTOs it intended to include in the caption and made clear:

Transmission Owners refers to the entities listed in the caption
of this order. We recognize that PJM’s transmission owners
include entities that are not subject to the Commission’s
jurisdiction because they are not public utilities pursuant to
section 201(f) of the FPA. See 16 U.S.C. § 824(f); Sw. Power
Pool, Inc., 180 FERC ¶ 61,022, at PP 44-45 (2022).
Accordingly, the Commission has not included AMP
Transmission, LLC; City of Hamilton, OH; East Kentucky
Power Cooperative, Inc.; and Southern Maryland Electric
Cooperative, Inc. here as Transmission Owners that must
respond to this order to show cause. Nonetheless, the
Commission retains the authority to review each entity’s
formula rates as a component of PJM’s Tariff in an order to
show cause directed towards PJM, and PJM must respond to
this order regarding the non-public utilities’ PJM Tariff
provisions on file with the Commission. See Sw. Power Pool,
Inc., 180 FERC ¶ 61,022 at P 40.[3]
Like each of the PTO entities listed in footnote 13, WVPA is not a public utility pursuant to section 201(f) of the FPA.  In January 2025 WVPA informed the Commission that as a result of the termination of one of its members, it ceased to be a public utility on 3 Id. at fn. 13.

PDF page 4

4

January 1, 2025 because it became exempt from the Federal Power Act as a result of being wholly owned by exempt entities.  As of January 1, 2025, WVPA has been wholly owned by twenty-one electric cooperatives that receive financing under the Rural Electrification Act of 1936 or sell less than four (4) million megawatt hours annually and by one additional member, which is wholly owned by WVPA.  The Commission subsequently acknowledged WVPA’s acceptance of its withdrawal of jurisdictional rate schedules based on the change in status.4

As of today, WVPA is still wholly owned by electric cooperatives that receive financing under the Rural Electrification Act of 1936 or sell less than four (4) million megawatt hours annually and by the additional member it wholly owns.  In fact, WVPA is itself in the process of receiving financing under the Rural Electrification Act of 1936. WVPA is a PTO within PJM, however, it is a PTO that is similarly situated to all of the other non-jurisdictional entities listed in footnote 13 of the Order.  WVPA respectfully submits that it is unaware of any basis, stated within the Order or any facts external to the Order, to treat WVPA any different.  WVPA believes that the Order inadvertently identified it based on its prior status as a public utility.

In addition, WVPA believes the Commission did not intend to include it as a named respondent. In the Show Cause Order issued to the California Independent System Operator (“CAISO”) and its transmission owners in Docket No. EL26-71-000, non-jurisdictional

4 Wabash Valley Power Ass’n, Inc., Docket No. ER25-838-000, (Feb. 12, 2025) (delegated order); Wabash Valley Power Ass’n, Inc., Docket No. ER25-842-000, (Feb. 12, 2025) (delegated order).

PDF page 5

5
utilities were purposefully included as respondents “because their Transmission Owner Tariffs on file with the Commission detail the wholesale load interconnection process in CAISO.”5  The Commission explained that “[i]f a non-public utility wishes to be removed from this proceeding, we will rescind the show cause order against them at their request, and we expect CAISO to respond to this order regarding the non-public utility’s CAISO Tariff provisions on file with the Commission.”6  The Commission did not express a similar concern with respect to PJM’s non-jurisdictional transmission owners.

As the Commission’s interests are in modifying the terms and conditions of the PJM Tariff, an errata to the Order affecting PJM would not impact or diminish the Commission’s stated show cause goals. Further, an errata to the Order would be consistent with the Commission’s treatment of a request from a similarly situated non-jurisdictional entity in Docket No. EL26-72-000 regarding the Show Cause Order issued to ISO New England Inc.7  Based on these facts, WVPA respectfully requests that the Commission issue an errata to the Order that:

(1) removes WVPA from the caption of Docket No. EL26-67-000, which
intended to identify only PJM and jurisdictional PTOs; and
(2) adds WVPA in the list of non-jurisdictional PTO entities in footnote 13. If the Commission determines that the requested corrections exceed the scope of

5 Cal. Indep. Sys. Op, Inc., et al, 195 FERC ¶ 61,214 at fn. 9 (2026) (“CAISO Order”).
6 Id., citing Sw. Power Pool, Inc., 180 FERC ¶ 61,022 at P 40 (2022).
7 ISO New England Inc., 195 FERC ¶ 61,215 (2026), errata notice, FERC Docket No. EL26-72-000 (July 9, 2026).

PDF page 6

6
an errata, WVPA respectfully requests in the alternative that the Commission rescind the Order with respect to WVPA as described in the CAISO Order precedent, as set forth above.

       Respectfully submitted,
/s/ Jeremy L. Fetty
Jeremy L. Fetty
L. Robyn Zoccola
Parr Richey Frandsen Patterson Kruse LLP
c/o Wabash Valley Power Association
6702 Intech Boulevard
Indianapolis, IN 46278
Telephone: (317) 481-2815
Email: jfetty@parrlaw.com
rzoccola@parrlaw.com
Counsel
for
Wabash
Valley
Power
Association, Inc.
Dated: July 28, 2026

PDF page 7

7
CERTIFICATE OF SERVICE
I hereby certify that on this 28th day of July 2026, I have served a copy of the foregoing document on the official service list compiled by the Office of the Secretary for the above-referenced proceeding.

/s/ Jeremy L. Fetty