EL26-70-000 · 2026-07-28 · Wabash Valley Power Association, Inc.
Motion of Wabash Valley Power Association, Inc. for Request for Issuance of an Errata of the 06/18/2026 Order Instituting Proceedings Under Section 206 of the Federal Power Act
PDF page 1
7607303
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent Independent System Operator, Inc.
AEP Indiana Michigan Transmission Company, Inc. ALLETE, Inc.
Ameren Illinois Company
Ameren Transmission Company of Illinois American Transmission Company, LLC
Cleco Power LLC
Duke Energy Indiana, LLC
Entergy Arkansas, LLC
Entergy Louisiana, LLC
Entergy Mississippi, LLC
Entergy New Orleans, LLC
Entergy Texas, Inc.
GridLiance Heartland LLC
Indianapolis Power & Light Company
International Transmission Company
ITC Midwest LLC
Michigan Electric Transmission Company, LLC MidAmerican Energy Company
Montana-Dakota Utilities Company
Northern Indiana Public Service Company LLC Northern States Power Company, a Minnesota Corporation
Northern States Power Company, a Wisconsin Corporation
Northwestern Wisconsin Electric Company Otter Tail Power Company
Pioneer Transmission, LLC
Republic Transmission, LLC
Southern Indiana Gas & Electric Company Union Electric Company
Wabash Valley Power Association, Inc. Wolverine Power Supply Cooperative, Inc.
Docket No. EL26-70-000
PDF page 2
27607303
WABASH VALLEY POWER ASSOCIATION, INC.
REQUEST FOR ISSUANCE OF AN ERRATA
To the Commission:
On June 18, 2026, the Commission issued its “Order Instituting Proceeding Under Section 206 of the Federal Power Act” in this above captioned proceeding.1 In its Order, the Commission found that Midcontinent Independent System Operator Inc.’s (“MISO”) existing Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”) appears to be unjust, unreasonable, or unduly discriminatory or preferential and thereafter directed MISO and thirty (30) Participating Transmission Owners (“PTOs”) within MISO to show cause with respect to a variety of concerns related to large load or co-located load transmission and interconnection within sixty (60) days of the date of its Order.2 Wabash Valley Power Association, Inc. (“WVPA”) has identified a procedural issue with the Order and respectfully requests that the Commission issue an errata as soon as practicable.
Before addressing the procedural issue presented below, WVPA desires to clarify that it does not dispute the need for the Commission to address issues surrounding service to large load and co-located load within organized markets and elsewhere. Further, WVPA acknowledges the Commission’s existing precedent regarding non-jurisdictional entities
1 Midcontinent Independent System Operator, Inc., et al, 195 FERC ¶ 61,212 (June 18, 2026) (the “Order”).2 Id. at P 3.
PDF page 3
37607303
with certain rate schedules within a jurisdictional RTO or ISO. The Commission included WVPA as one of the PTOs in the caption of the Order. However, at footnote 11 of the Order, the Commission described which PTOs it intended to include in the caption and made clear:
Transmission Owners refers to the entities listed in the caption of this order. We recognize that MISO’s transmission owners include entities that are not subject to the Commission’s jurisdiction because they are not public utilities pursuant to section 201(f) of the FPA. See 16 U.S.C. § 824(f); Sw. Power Pool, Inc., 180 FERC ¶ 61,022, at PP 44-45 (2022). Accordingly, the Commission has not included 1803 Electric Cooperative, Inc.; Ames Municipal Electric System; Arkansas Electric Cooperative Corporation; Big Rivers Electric Corporation; Board of Water, Electric and Communications Trustees of the City of Muscatine, Iowa; Central Minnesota Municipal Power Agency; Citizens Electric Corporation; City of Alexandria, Louisiana; City of Columbia, Missouri, Water & Light Department; City of Henderson, Kentucky, Utility Commission; City Water, Light and Power - City of Springfield, Illinois City Water and Light Plant of the City of Jonesboro;
Cooperative
Energy;
Dairyland
Power
Cooperative; East Texas Electric Cooperative, Inc.; Great River Energy; Hoosier Energy Rural Electric Cooperative, Inc.; Indiana Municipal Power Agency; Lafayette City-Parish Consolidated Government; Michigan Public Power Agency; Michigan South Central Power Agency; Minnesota Municipal Power Agency; Missouri Joint Municipal Electric Utility Commission; Missouri River Energy Services; Municipal Electric Utility of the City of Cedar Falls, Iowa; Municipal Energy Agency of Nebraska; Prairie Power, Inc.; Rochester Public Utilities; Sam Houston Electric Cooperative, Inc.; Southern Illinois Power Cooperative; Southern Minnesota Municipal Power Agency; Willmar Municipal Utilities; and WPPI Energy here as Transmission Owners that must respond to this order to show cause. Nonetheless, the Commission retains the authority to review each entity’s formula rates as a component of MISO’s Tariff in an order to show cause directed towards MISO, and MISO must respond to this order regarding the non-public utilities’ MISO Tariff provisions on file with
PDF page 4
47607303
the Commission. See Sw. Power Pool, Inc., 180 FERC ¶
61,022 at P 40.[3]
Like each of the PTO entities listed in footnote 11, WVPA is not a public utility pursuant to section 201(f) of the FPA. In January 2025 WVPA informed the Commission that as a result of the termination of one of its members, it ceased to be a public utility on January 1, 2025 because it became exempt from the Federal Power Act as a result of being wholly owned by exempt entities. As of January 1, 2025, WVPA has been wholly owned by twenty-one electric cooperatives that receive financing under the Rural Electrification Act of 1936 or sell less than four (4) million megawatt hours annually and by one additional member which is wholly owned by WVPA. The Commission subsequently acknowledged WVPA’s acceptance of its withdrawal of jurisdictional rate schedules based on the change in status.4
As of today, WVPA is still wholly owned by electric cooperatives that receive financing under the Rural Electrification Act of 1936 or sell less than four (4) million megawatt hours annually and by the additional member it wholly owns. In fact, WVPA is itself in the process of receiving financing under the Rural Electrification Act of 1936. WVPA is a PTO within MISO, however, it is a PTO that is similarly situated to all of the other non-jurisdictional entities listed in footnote 11 of the Order. WVPA respectfully submits that it is unaware of any basis, stated within the Order or any facts external to the
3 Id. at fn. 11.
4 Wabash Valley Power Ass’n, Inc., Docket No. ER25-838-000, (Feb. 12, 2025) (delegated order); Wabash Valley Power Ass’n, Inc., Docket No. ER25-842-000, (Feb. 12, 2025) (delegated order).
PDF page 5
57607303
Order, to treat WVPA any different. WVPA believes that the Order inadvertently identified it based on its prior status as a public utility.
In addition, WVPA believes the Commission did not intend to include it as a named respondent. In the Show Cause Order issued to the California Independent System Operator (“CAISO”) and its transmission owners in Docket No. EL26-71-000, non-jurisdictional utilities were purposefully included as respondents “because their Transmission Owner Tariffs on file with the Commission detail the wholesale load interconnection process in CAISO.”5 The Commission explained that “[i]f a non-public utility wishes to be removed from this proceeding, we will rescind the show cause order against them at their request, and we expect CAISO to respond to this order regarding the non-public utility’s CAISO Tariff provisions on file with the Commission.”6 The Commission did not express a similar concern with respect to MISO’s non-jurisdictional transmission owners.
As the Commission’s interests are in modifying the terms and conditions of the MISO Tariff, an errata to the Order affecting MISO would not impact or diminish the Commission’s stated show cause goals. Further, an errata to the Order would be consistent with the Commission’s treatment of a request from a similarly situated non-jurisdictional entity in Docket No. EL26-72-000 regarding the Show Cause Order issued to ISO New England Inc.7 Based on these facts, WVPA respectfully requests that the Commission
5 Cal. Indep. Sys. Op, Inc., et al, 195 FERC ¶ 61,214 at fn. 9 (2026) (“CAISO Order”).6 Id., citing Sw. Power Pool, Inc., 180 FERC ¶ 61,022 at P 40 (2022).7 ISO New England Inc., 195 FERC ¶ 61,215 (2026), errata notice, FERC Docket No. EL26-72-000 (July 9, 2026).
PDF page 6
67607303
issue an errata to the Order that:
(1) removes WVPA from the caption of Docket No. EL26-70-000, which intended to identify only MISO and jurisdictional PTOs; and
(2) adds WVPA in the list of non-jurisdictional PTO entities in footnote 11.
If the Commission determines that the requested corrections exceed the scope of an errata, WVPA respectfully requests in the alternative that the Commission rescind the Order with respect to WVPA as described in the CAISO Order precedent, as set forth above.
Respectfully submitted,
/s/ Jeremy L. Fetty
Jeremy L. Fetty
L. Robyn Zoccola
Parr Richey Frandsen Patterson Kruse LLP
c/o Wabash Valley Power Association
6702 Intech Boulevard
Indianapolis, IN 46278
Telephone: (317) 481-2815
Email: jfetty@parrlaw.com
rzoccola@parrlaw.com
Counsel
for
Wabash
Valley
Power
Association, Inc.
Dated: July 28, 2026
PDF page 7
7607303
CERTIFICATE OF SERVICE
I hereby certify that on this 28th day of July 2026, I have served a copy of the foregoing document on the official service list compiled by the Office of the Secretary for the above-referenced proceeding.
/s/ Jeremy L. Fetty