EL26-70-000 · 2026-07-28 · Wabash Valley Power Association, Inc.

Motion of Wabash Valley Power Association, Inc. for Request for Issuance of an Errata of the 06/18/2026 Order Instituting Proceedings Under Section 206 of the Federal Power Act

Wabash Valley Power Association asks FERC to correct the E-8 order by removing it from the caption and listing it with the non-jurisdictional transmission owners in footnote 11, because it ceased to be a public utility on January 1, 2025.

Asks FERC to: Issue an errata removing Wabash from the caption and adding it to footnote 11, or alternatively rescind the show cause order as to Wabash.

Seeks correction of who is a named respondent to the E-8 show cause order; FERC granted it in the August 13, 2026 errata notice.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. Wabash says it does not dispute the need to address large and co-located load service.
    WVPA desires to clarify that it does not dispute the need for the Commission to address issues surrounding service to large load and co-located load PDF p. 2
  2. Wabash says it left public utility status on January 1, 2025, as an entity owned by exempt cooperatives.
    it ceased to be a public utility on January 1, 2025 because it became exempt from the Federal Power Act PDF p. 4
  3. Wabash says it is similarly situated to the non-jurisdictional owners listed in footnote 11.
    WVPA is a PTO within MISO, however, it is a PTO that is similarly situated to all of the other non-jurisdictional entities listed in footnote 11 of the Order. PDF p. 4
  4. Wabash cites FERC's treatment of a similar ISO-NE request and its CAISO rescission precedent.
    an errata to the Order would be consistent with the Commission’s treatment of a request from a similarly situated non-jurisdictional entity in Docket No. EL26-72-000 PDF p. 5
  5. Wabash asks for the two corrections and, alternatively, rescission as to Wabash.
    removes WVPA from the caption of Docket No. EL26-70-000, which intended to identify only MISO and jurisdictional PTOs; and (2) adds WVPA in the list of non-jurisdictional PTO entities in footnote 11. PDF p. 6

Read topic-matched comments in EL26-70

Topics in the text: Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Nonetheless, the Commission retains the authority to review each entity’s formula rates as a component of MISO’s Tariff in an order to show cause directed towards MISO, and MISO must respond to this order regarding the non-public utilities’ MISO Tariff provisions on file with 4 7607303 the…