EL26-69-000 · 2026-08-03 · Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc. and 4 others

Request for Abeyance of the New York Transmission Owners and Request for Expedited Commission Action and Shortened Comment Period

The six New York Transmission Owners request a full 90-day abeyance of the EL26-69 show cause proceeding. They rely on their reserved section 205 filing rights and describe planned tariff work on cost recovery, revenue crediting, rate design, the Facilities Study and operating terms.

Asks FERC to: Hold the proceeding in abeyance for 90 days from August 17, 2026, including the 60-day response deadline, with expedited action and a shortened comment period.

Uses the E-12 order's abeyance option and previews the TO-side section 205 filing on cost recovery, revenue crediting, study procedures and alternative transmission technologies.

E-12 NYISO: Show cause or propose tariff changes in 60 days (p. 5) E-12 NYISO: Cost transparency (P 73, p. 47) E-12 NYISO: Alternative transmission technologies (P 68, p. 79)

Key points

  1. The NYTOs file independently under section 3.10(a) of the NYISO-TO Agreement, which lets each TO file section 205 changes to recover costs and for retail access.
    section 3.10(a) confers upon each Transmission Owner the unilateral right to file with the Commission under FPA section 205 PDF p. 7
  2. They plan a cost recovery mechanism coordinated with the NYPSC, likely a pro forma agreement or tariff provisions.
    The NYTOs intend to incorporate the NYPSC's cost allocation determinations and to file with the Commission a proposed mechanism PDF p. 15
  3. Possible terms include a minimum financial contribution plus security to protect other customers if the load does not take the expected service.
    Such arrangements may include a minimum financial contribution from the large load customer or Eligible Customer, as applicable, toward the Transmission Owner's transmission revenue requirement PDF p. 16
  4. They will provide revenue credits where upgrade costs paid by a large load are also in rates paid by other customers.
    the NYTO will provide for a revenue credit to the extent the NYTO is recovering those Network Upgrade costs. PDF p. 17
  5. NYISO's planned Firm and Non-Firm Withdrawal Service would need changes to billing determinants and cost allocation.
    The different forms of service may require changes in the billing determinants, billing units, demand allocators, and cost allocation mechanisms. PDF p. 20
  6. The NYTOs will address Facilities Study process, timeline and evaluation of alternative transmission technologies in the section 205 filing.
    the NYTOs intend to address whether and how the Facilities Study process should require evaluation of alternative transmission technologies PDF p. 24
Contents · 13 sections
  1. I. BACKGROUND p. 3
  2. A. The Show Cause Order p. 3
  3. B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement p. 6
  4. II. REQUEST FOR ABEYANCE p. 8
  5. III. DESCRIPTION OF ANTICIPATED FPA SECTION 205 FILING p. 11
  6. A. Cost Recovery and Transmission Service Charges p. 13
  7. B. Large Load Interconnection Procedures and Agreements p. 20
  8. C. Operating Terms Applicable to Non-Firm Transmission Withdrawal Service p. 27
  9. IV. REQUEST FOR EXPEDITED COMMISSION ACTION AND SHORTENED p. 28
  10. V. COMMUNICATIONS p. 28
  11. C. Dixon Wallace III p. 29
  12. VI. CONCLUSION p. 29
  13. C. Dixon Wallace III p. 30

Topics in the text: Filing procedure · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

In this case, the Commission did not name NYPA and LIPA as parties in the Show Cause Order and therefore they are not filing parties to this abeyance request.
Read this passage

I. BACKGROUND

printed heading

I.
Read this passage

A. The Show Cause Order

printed heading · Topic match: Filing procedure

Specifically, the Show Cause Order states that:  The Commission will consider requests for abeyance of up to 90 days;  The abeyance period will begin as of the deadline to respond to the Show Cause Order (August 17, 2026);  Abeyance requests must be submitted within 45 days of the issuance of…
Read this passage

B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement

printed heading

The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement The NYTOs file this request independently from the NYISO, in accordance with the rights explicitly reserved in section 3.10(a) of the NYISO-TO Agreement.19 Section 3.10(a) provides, in relevant part, that: Each Transmission Owner…
Read this passage

II. REQUEST FOR ABEYANCE

printed heading · Topic match: Filing procedure

REQUEST FOR ABEYANCE The NYTOs respectfully submit this request for a full 90-day abeyance of the above- captioned show cause proceeding.
Read this passage

III. DESCRIPTION OF ANTICIPATED FPA SECTION 205 FILING

printed heading · Topic match: Filing procedure

DESCRIPTION OF ANTICIPATED FPA SECTION 205 FILING Consistent with the Show Cause Order’s requirement that a successful abeyance request include a robust description of the content of any anticipated FPA section 205 filing, the NYTOs provide the following description of the Tariff revisions they…
Read this passage

A. Cost Recovery and Transmission Service Charges

printed heading · Topic match: Cost allocation

Network Upgrade Cost Recovery The Commission preliminarily found in the Show Cause Order that the NYISO Tariff appears unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers.
Read this passage

B. Large Load Interconnection Procedures and Agreements

printed heading · Topic match: Filing procedure

Large Load Interconnection Procedures and Agreements The Commission preliminarily found in the Show Cause Order that the NYISO and/or NYTOs should modify the NYISO OATT and/or agreements to address: the scope and timing of interconnection studies, including the Facilities Studies; 46 the evaluation…
Read this passage

C. Operating Terms Applicable to Non-Firm Transmission Withdrawal Service

printed heading · Topic match: Connecting load and generation

With potentially large increases in the amount of new large loads on the system, and new non-firm or contract demand services, new operating requirements will be needed, as the Commission recognizes.58 The NYTOs will coordinate with the NYISO to develop operating requirements for loads that have…
Read this passage

IV. REQUEST FOR EXPEDITED COMMISSION ACTION AND SHORTENED

printed heading

REQUEST FOR EXPEDITED COMMISSION ACTION AND SHORTENED COMMENT PERIOD The NYTOs respectfully request that the Commission act on this request on or before August 13, 2026, to provide the NYTOs with certainty regarding the need to file a response to the Show Cause Order and to allow the NYTOs to focus…
Read this passage

V. COMMUNICATIONS

printed heading · Topic match: Filing procedure

COMMUNICATIONS All communications and correspondence regarding this filing should be forwarded to the following individuals, whose names should be placed on the Commission’s service list:61 60 18 C.F.R. § 385.213(d)(1)(i) (“If a motion requests an extension of time or a shortened time period for…
Read this passage

C. Dixon Wallace III

printed heading

Douglas TROUTMAN PEPPER LOCKE LLP 401 9th Street NW, Suite 1000 Washington, DC 20004 (202) 274-2886 william.derasmo@troutman.com dixon.wallace@troutman.com antonia.douglas@troutman.com Marina Chu Regulatory Attorney – Regulatory Affairs Central Hudson Gas & Electric Corporation 284 South Avenue…
Read this passage

VI. CONCLUSION

printed heading · Topic match: Filing procedure

VI.
Read this passage

C. Dixon Wallace III

printed heading

Douglas TROUTMAN PEPPER LOCKE LLP Counsel to the New York Transmission Owners /s/ Marina Chu Marina Chu Central Hudson Gas & Electric Corporation /s/ Phillip D.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Bascus FERC Energy Specialist TROUTMAN PEPPER LOCKE LLP 401 9th Street NW, Suite 1000 Washington, DC 20004 (202) 274-1949 daryl.bascus@troutman.com