EL26-69-000 · 2026-08-03 · Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc. and 4 others
Request for Abeyance of the New York Transmission Owners and Request for Expedited Commission Action and Shortened Comment Period
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
New York Independent System Operator, Inc.
)
)
Central Hudson Gas & Electric Corporation
)
Consolidated Edison Company of New York, Inc. )
Docket No. EL26-69-000
LS Power Grid New York Corporation I
)
New York State Electric & Gas Corporation
)
New York Transco LLC
)
NextEra Energy Transmission New York, Inc.
)
Niagara Mohawk Power Corp.
)
Orange and Rockland Utilities, Inc.
)
Rochester Gas and Electric Corporation
)
REQUEST FOR ABEYANCE OF THE NEW YORK TRANSMISSION OWNERS AND
REQUEST FOR EXPEDITED COMMISSION ACTION AND SHORTENED
COMMENT PERIOD
Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc., New York State Electric & Gas Corporation, Niagara Mohawk Power Corporation d/b/a National Grid, Orange and Rockland Utilities, Inc., and Rochester Gas and Electric Corporation (collectively referred to herein as the “New York Transmission Owners” or “NYTOs”)1 individually and collectively, pursuant to the Federal Energy Regulatory Commission’s (“Commission”) Order Instituting Proceeding Under section 206 of the Federal Power Act (“FPA”)2 issued June 18, 2026,3 hereby respectfully request that the Commission hold in abeyance all aspects of the above-captioned proceeding described below, including the 60-day deadline to
1 New York Power Authority (“NYPA”) and Long Island Power Authority (“LIPA”) are members of the New York Independent System Operator, Inc. (“NYISO”). In this case, the Commission did not name NYPA and LIPA as parties in the Show Cause Order and therefore they are not filing parties to this abeyance request. Nevertheless, as intervenors in this case, NYPA and LIPA generally support this abeyance request to allow for coordination among the NYISO and NYTOs on shared responsibilities and vetting with stakeholders on future FPA section 205 filings.2 16 U.S.C. § 824e. 3 N.Y. Indep. Sys. Operator, Inc., 195 FERC ¶ 61,216 (2026) (“Show Cause Order”).
PDF page 2
2
respond to the Show Cause Order, for a full period of 90 days, commencing as of August 17, 2026. This request is submitted within the 45-day window prescribed by the Show Cause Order and is supported by the substantive description of the anticipated FPA section 2054 filing(s) set forth herein.5
The NYTOs understand that the NYISO is also submitting an abeyance request under separate cover in this docket. The NYTOs support abeyance for the NYISO as well and appreciate the progress that the NYISO has made to date. The NYISO developed an extensive initial proposal that was presented to stakeholders at the July 23 Transmission Planning Advisory Committee/Electric System Planning Working Group meeting.6 While much work remains to be done, and while the NYISO presentation is under review by the NYTOs, the presentation is a promising start. The NYTOs observe that the NYISO has successfully worked cooperatively with stakeholders in developing Order No. 20237 and Order No. 19208 compliance filings, and the NYTOs are confident that the NYISO will be able to do so here. While the NYTOs possess unilateral filing rights for certain issues (as discussed below), if granted an abeyance by the Commission, the NYTOs commit to coordinate closely with the NYISO and stakeholders and may
4
16 U.S.C. § 824d.
5 As explained below, the NYTOs have not yet determined the procedural vehicle for their forthcoming FPA section 205 filing, which may take the form of a companion, NYTO-specific filing, or, if the NYTOs and NYISO mutually agree, a joint NYISO and NYTOs filing. In either case, the NYTOs commit to coordinate closely with the NYISO and stakeholders.6 NYISO, Large Load FERC Show Cause Order (July 23, 2026) (“NYISO Show Cause Order Presentation”), https://www.nyiso.com/documents/20142/58620525/04_FERC%20Large%20Load%20Show%20Cause%2 0Order%20-%20ESPWG.pdf/3b66b965-05ad-51e6-a4c5-c9846eeada4c. 7 Improvements to Generator Interconnection Procs. & Agreements, Order No. 2023, 184 FERC ¶ 61,054, order on reh’g, 185 FERC ¶ 61,063 (2023), order reh’g & clarification, Order No. 2023-A, 186 FERC ¶ 61,199 (2024), petition for review denied sub nom. Advanced Energy United, et al. v. FERC, No. 23-1282 (D.C. Cir. July 31, 2026). 8 Bldg. for the Future Through Elec. Reg’l Transmission Planning and Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068, order on reh’g & clarification, 189 FERC ¶ 61,126 (2024), order on reh’g & clarification, 191 FERC ¶ 61,026 (2025).
PDF page 3
3
submit separate a NYTO-only FPA section 205 filing or, should the NYTOs and NYISO mutually agree, join a single FPA section 205 filing with the NYISO, as appropriate.
I. BACKGROUND
A. The Show Cause Order
On June 18, 2026, the Commission issued the Show Cause Order, instituting a proceeding under FPA section 206 based on the Commission’s preliminary finding that the NYISO’s Open Access Transmission Tariff (“OATT” or “Tariff”)9 appears to be unjust, unreasonable, or unduly discriminatory or preferential.10 The Commission issued the Show Cause Order as part of a suite of six coordinated orders directed to each of the RTO/ISO regions subject to the Commission’s jurisdiction.
The Show Cause Order includes preliminary findings that the NYISO’s Tariff appears unjust and unreasonable in five principal respects:
1. Transmission Service Study Process for Large Loads. The Commission
preliminarily found that the NYISO’s Tariff lacks sufficiently clear and consistent provisions addressing: (a) a definition of large load as a distinct category of load; (b) a mandatory application process, readiness requirements, and study procedures for Eligible Customers seeking transmission service on behalf of large loads; (c) study timelines of no more than 60-90 calendar days; (d) ongoing operational requirements – including telemetry, data reporting, remote disconnect capability, ramp rate and ride-through requirements, and protection systems – for transmission customers serving large loads; (e) evaluation of alternative transmission technologies
9 Capitalized terms not otherwise defined herein have the meanings set forth in the NYISO OATT or Market Administration and Control Area Services Tariff, as applicable.10 Show Cause Order at P 3.
PDF page 4
4
as potential solutions in lieu of or in addition to traditional Network Upgrades; and (f) pro forma provisions in transmission service agreements to memorialize operational requirements.11
2. Cost Transparency and Cost Recovery. The Commission preliminarily found that the NYISO Tariff lacks: (a) robust, centralized, publicly accessible data on its website regarding the Network Upgrades and associated costs needed to provide transmission service to Eligible Customers on behalf of large loads; and (b) a pro forma cost recovery agreement between the NYISO, the relevant Transmission Owner, and the Eligible Customer taking transmission service on behalf of a large load, with a minimum financial contribution and credit support requirement sufficient to mitigate the risk of cost shifting among transmission customers.12
3. Co-Location Arrangements and Behind-the-Meter Generation. The Commission
preliminarily found that the NYISO’s Tariff lacks: (a) a definition of co-located load; (b) sufficiently clear and consistent provisions governing the rates, terms, and conditions of service applicable to interconnection customers serving co-located load, including required ancillary service charges (regulation and black start service on a gross demand basis); and (c) provisions addressing netting of behind-the-meter generation from gross load for purposes of calculating applicable Transmission Service Charges in a manner consistent with the cost causation principle.13
4. New Transmission Services for Eligible Load and Flexible Large Loads. The
Commission preliminarily found that the NYISO’s Tariff lacks transmission services that reflect
11 Show Cause Order at PP 56-71.12 Id. PP 77-91.13 Id. PP 101-110. See, e.g., Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858, 868-69 (D.C. Cir. 2024) (“[T]he cost causation principle requires that ‘all approved rates reflect to some degree the costs actually caused by the customer who must pay them.’”) (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 88 (D.C. Cir. 2014)).
PDF page 5
5
the operational capabilities of Eligible Customers taking transmission service on behalf of Eligible Load (co-located load and load with behind-the-meter generation) and flexible large loads that are willing and able to limit their energy withdrawals from the transmission system under certain conditions, specifically: (a) an interim non-firm network transmission service (“Interim NITS”) available while Network Upgrades are being constructed; and (b) permanent firm and non-firm contract demand transmission services.14
5. Generator Interconnection for Electrically Proximate Large Load and Co-Located Load. The Commission preliminarily found that the NYISO’s Tariff lacks generator interconnection study procedures and generator interconnection services tailored to reflect an interconnection customer’s commitment to limit a generating facility’s output to match the hourly forecast of an electrically proximate large load or large co-located load, thereby potentially reducing the need for Network Upgrades and accelerating the interconnection process.15 The Show Cause Order directs the NYISO and the named Transmission Owners, within 60 days of issuance (i.e., by August 17, 2026), to either: (1) show cause as to why the Tariff remains just and reasonable and not unduly discriminatory or preferential without provisions addressing the foregoing concerns; or (2) explain what Tariff changes would remedy those concerns were the Commission to determine that the Tariff is in fact unjust and unreasonable and to establish a replacement Tariff.16 The Commission separately directed the NYISO to submit, within 30 days of issuance (i.e., by July 18, 2026), an informational report on its plans to ensure adequate generation to serve existing and new large loads.1714 Id. PP 109, 112-113.15 Id. PP 121-127.16 E.g., id. P 3.17 Id. PP 128-129.
PDF page 6
6
The Show Cause Order also provides the NYISO and/or the Transmission Owners the opportunity to seek to hold all or certain aspects of the proceeding in abeyance while they develop FPA section 205 filings to address the Commission’s concerns. Specifically, the Show Cause Order states that:
The Commission will consider requests for abeyance of up to 90 days; The abeyance period will begin as of the deadline to respond to the Show Cause Order (August 17, 2026);
Abeyance requests must be submitted within 45 days of the issuance of the Show Cause Order (i.e., by August 3, 2026);
The Commission will not grant abeyances reflexively, and will look with great disfavor toward requests to extend the abeyance period beyond 90 days; and Successful abeyance requests must include both: (1) a robust description of the content of a potential future FPA section 205 filing; and (2) a reasoned and specific explanation of when such a filing is expected to be made.18
The NYTOs submit this filing on August 3, 2026, within the 45-day window, and it includes a detailed description of the NYTOs’ plans to coordinate with the NYISO and stakeholders to address the issues identified in the Show Cause Order.
B. The NYTOs’ Independent Filing Rights Under the NYISO-TO Agreement The NYTOs file this request independently from the NYISO, in accordance with the rights explicitly reserved in section 3.10(a) of the NYISO-TO Agreement.19 Section 3.10(a) provides, in relevant part, that:
Each Transmission Owner shall have the right at any time
unilaterally to file pursuant to Section 205 of the Federal Power Act to change the ISO OATT, a Service Agreement under the ISO
OATT, or the ISO Agreement to the extent necessary: (i) to recover
all of its reasonably incurred costs, plus a reasonable return on
investment related to services under the ISO OATT and (ii) to
18 Id. P 42.19 NYISO, Foundation Agreements, Agreement Between New York Independent System Operator and Transmission Owners (0.0.0) (“NYISO-TO Agreement”).
PDF page 7
7
accommodate implementation of, and changes to, a Transmission
Owner’s retail access program.20
Critically, section 3.10(a) confers upon each Transmission Owner the unilateral right to file with the Commission under FPA section 205 – independent of the NYISO’s concurrence – to the extent necessary to recover reasonably incurred costs associated with services provided under the NYISO OATT and to accommodate changes to the NYTOs’ retail access programs.21
The Show Cause Order expressly recognizes this allocation of rights and
responsibilities. Indeed, the Commission acknowledged that “the Transmission Owners may be partially responsible for conducting the studies that (1) evaluate whether a large load may be interconnected to the transmission system and served by the Eligible Customer and (2) determine whether Network Upgrades are necessary to provide transmission service.”22 The Commission further explained that it “appreciate[s] that this role may stem from how NYISO and the Transmission Owners allocated rights and responsibilities in the governing documents establishing NYISO” and “does not seek to alter that allocation of rights and responsibilities.”23
Several matters addressed in the Show Cause Order directly implicate the NYTOs’ ability to recover their reasonably incurred costs through Commission-jurisdictional transmission rates. As the Commission itself acknowledges, the costs of Network
20 Id. § 3.10(a).21 See id. § 3.03 (providing that “[n]otwithstanding any other provision in this Agreement except for the provisions of Section 3.10,” proposed OATT revisions are subject to certain stakeholder and NYISO governance procedures (including review by the NYISO Board of Directors) before being filed at FERC) (emphasis added).22 Show Cause Order at P 58.23 Id.
PDF page 8
8
Upgrades needed to provide transmission service to Eligible Customers on behalf of large loads are inputs to jurisdictional transmission rates and are recovered through each Transmission Owner’s Annual Transmission Revenue Requirement.24 Accordingly, the NYTOs’ independent filing rights under section 3.10(a) of the NYISO-TO Agreement are squarely implicated with respect to key issues identified below.
Section 3.10(a) also provides an independent, second basis for the NYTOs’ unilateral FPA section 205 filing rights that is equally applicable to certain key issues identified below: the right to file “to accommodate implementation of, and changes to, a Transmission Owner’s retail access program.” The Show Cause Order’s directives directly implicate the NYTOs’ retail access obligations. Specifically, any cost transparency requirements, cost recovery agreements, and study process reforms at issue would directly affect how large loads – including retail transmission service customers that qualify as Eligible Customers under the transmission provider and/or Transmission Owner tariffs – are interconnected and served under each NYTO’s retail access program. Thus, the Tariff reforms at issue here will necessarily affect each NYTO’s retail access obligations, engaging the retail access prong of section 3.10(a) as an additional, independent basis for the NYTOs’ filing authority.
II. REQUEST FOR ABEYANCE
The NYTOs respectfully submit this request for a full 90-day abeyance of the above- captioned show cause proceeding. The NYTOs recognize the urgency of the Commission’s concerns regarding the integration of large and co-located loads onto the New York transmission
24 Id. PP 20, 85.
PDF page 9
9
system and are committed to working with the NYISO to develop comprehensive, regionally- tailored solutions.
As detailed below, the NYTOs have already begun the processes, which are directly responsive to the Commission’s concerns. Granting a full 90-day abeyance will allow those processes to advance to the point at which the NYTOs can propose – either in a potential joint FPA section 205 filing with the NYISO or in a companion FPA section 205, NYTO-only filing – Tariff revisions addressing the full scope of the Commission’s preliminary findings that are within the purview of the NYTOs. Indeed, the Commission expressly recognized that the Transmission Owners “may elect to address some or all of the issues discussed in this order by proposing revisions to the Tariff pursuant to their applicable FPA section 205 filing rights” and stated that it “strongly encourage[s]” the NYISO and/or NYTOs to submit FPA section 205 filings.25 Proceeding through an FPA section 205 filing that is developed in coordination with NYISO, the New York Public Service Commission (“NYPSC”), and other stakeholders rather than through FPA section 206 litigation will produce more targeted, operationally sound proposals that are better calibrated to NYISO’s unique market structure, resource adequacy construct, and existing Tariff framework.
Consistent with section 3.10(a) and the Commission’s own recognition of the NYTOs’ independent role described above, the instant proceeding falls squarely within the scope of the NYTOs’ unilateral filing rights, which extend to matters that directly affect their ability to recover reasonably incurred costs through Commission-jurisdictional transmission rates and to modifications to their retail access programs. The Show Cause Order raises important questions about the adequacy of the NYISO’s Tariff provisions relating to: (1) the study process for
25 Id. P 41.
PDF page 10
10
transmission service requests on behalf of large loads, the results of which directly determine what Network Upgrades are required and the associated costs that flow into each NYTO’s transmission rates, including potentially a pro forma interconnection agreement that memorializes the results of that study process; (2) cost recovery agreements that would require Eligible Customers to bear the risk of costs incurred to provide transmission service, including Network Upgrade costs; (3) revenue crediting mechanisms to ensure that payments made pursuant to such cost recovery agreements are appropriately reflected in, and do not result in double recovery through, each NYTO’s transmission rates applicable to other FERC-jurisdictional customers; (4) transmission service charges and new transmission service products – including firm and non-firm withdrawal service and contract demand-based service – needed to reflect the operational characteristics of large loads and co-located loads; (5) cost transparency mechanisms that will directly affect the public visibility of each NYTO’s transmission-related costs; and (6) operating requirements applicable to non-firm transmission withdrawal service and paired or behind-the-meter generation supplies. Each of these issues is inextricably linked to the NYTOs’ ability to recover their reasonably incurred costs under the Tariff and to changes to the manner in which the NYTOs provide retail transmission services – the precise subject matter of the independent filing rights preserved under section 3.10(a) of the NYISO-TO Agreement.
A full 90-day abeyance is warranted here. The issues identified in the Show Cause Order are substantial in scope and technical complexity, encompassing potential new large load study processes, cost recovery and transparency mechanisms, co-location Tariff provisions, new transmission service products, and new generator interconnection services. Creating thorough and technically valid Tariff proposals to address the Commission’s concerns, including those areas within the NYTOs’ scope of reserved rights, requires sufficient time for active collaboration
PDF page 11
11
between the NYTOs, the NYISO, and other parties listed in the Show Cause Order, and also for adequate consultation with subject matter experts. The 90-day abeyance period is the minimum time necessary to responsibly advance this work and to vet with stakeholders, coordinate with the NYISO, and deliver proposals of the quality and comprehensiveness the Commission has invited. The NYTOs are committed to using the abeyance period efficiently and anticipate making an FPA section 205 filing (either in a potential joint filing with the NYISO or in a companion NYTO-only standalone filing) to address the issues raised in the Show Cause Order that fall within the NYTOs’ purview.
III. DESCRIPTION OF ANTICIPATED FPA SECTION 205 FILING
Consistent with the Show Cause Order’s requirement that a successful abeyance request include a robust description of the content of any anticipated FPA section 205 filing, the NYTOs provide the following description of the Tariff revisions they anticipate proposing in coordination with the NYISO and stakeholders. Specifically, NYTOs have identified the following areas that fall within the purview of their independent, unilateral FPA section 205 filing rights pursuant to section 3.10(a) of the NYISO-TO Agreement: (1) cost allocation and recovery; (2) mechanisms to ensure that payments made by Eligible Customers pursuant to cost recovery agreements or Tariff provisions are appropriately credited toward each NYTO’s transmission revenue requirement to the extent such costs are included in such revenue requirements consistent with the Commission’s cost-of-service regulations; (3) rate design issues concerning new transmission services reflecting the operational characteristics of large loads, co-located loads, and flexible large loads willing and able to limit their use of the transmission system;26 (4) aspects of the load interconnection study
26 The preservation of the tax exempt status for certain NYTOs as well as for local furnishing bonds will need to be preserved as well.
PDF page 12
12
process for which the NYTOs will be responsible (including the Facilities Study); and (5) certain operational requirements for Eligible Customers taking service on behalf of large loads, along with any necessary agreements and Tariff changes to implement the foregoing.27
The NYTOs note that, under their unilateral filing rights found in section 3.10(a) of the NYISO-TO Agreement, they are not required to seek approval of their proposed FPA section 205 filing through the NYISO stakeholder process. However, the NYTOs commit to sharing their proposals with the NYISO and stakeholders during the abeyance period to seek feedback, and note that, as a result, the specific scope and provisions of the anticipated filing described below may be further refined and altered.
The NYISO has indicated that, if the Commission grants an abeyance in this proceeding, the NYISO will present elements of an FPA section 205 filing during meetings with the NYTOs and stakeholders scheduled to occur as frequently as weekly through November 16, 2026. The NYTOs will be primarily responsible for certain key functions and, as such, will reserve time at those meetings to present the proposals for stakeholder feedback. In parallel, the NYTOs and the NYISO will allocate responsibility for drafting Tariff provisions and agreements to revise the relevant large load interconnection and cost allocation and recovery procedures as appropriate. At this stage, the NYTOs do not know if they will (i) join with the NYISO an FPA section 205 filing that addresses all issues raised in the Show Cause Order or (ii) submit a companion, NYTO-only filing that addresses the issues within the NYTOs’ unilateral FPA section 205 filing rights. In either case, however, the NYTOs will coordinate closely with the NYISO and other stakeholders.
27 This is not intended to be an exclusive list of the items within the NYTOs’ unilateral FPA section 205 filing right and does not constitute a waiver of any NYTO filing right.
PDF page 13
13
A. Cost Recovery and Transmission Service Charges
1. Network Upgrade Cost Recovery
The Commission preliminarily found in the Show Cause Order that the NYISO Tariff appears unjust and unreasonable because it lacks adequate mechanisms to mitigate the risk of cost shifting among transmission customers. First, the Commission noted the lack of Tariff provisions requiring NYISO to post in a single location on the NYISO website certain Network Upgrade and cost data and other related information.28 Second, the Commission pointed to the absence of a pro forma cost recovery agreement between NYISO, the relevant Transmission Owner, and the Eligible Customer taking transmission service on behalf of large loads that helps ensure that Eligible Customers bear the risk and are ultimately responsible for costs incurred to provide transmission service, including Network Upgrade costs.29 The Commission also contemplated the possibility of Transmission Owners entering into cost recovery agreements with large load customers themselves rather than the corresponding Eligible Customers.30
The NYTOs plan to coordinate with NYISO, NYPSC, the New York Department of Public Service (“DPS”),31 and other interested stakeholders to develop a process for the Transmission Owner to recover from the Eligible Customer or large load customer, as applicable, an allocable share of the cost of Transmission Owner Interconnection Facilities and Network Upgrades. In a single-state ISO like the NYISO, a state public utility commission is in a good position to address cost allocation issues associated with upgrades to accommodate large loads. Among other factors, the NYPSC will be in a good position to balance various benefits provided by
28 Id. P 77.29 Id. P 83.30 Id. P 88.31 The NYPSC is housed within the DPS. N.Y. Pub. Serv. Law § 4 (McKinney 2024).
PDF page 14
14
upgrades in terms of reliability, public policy, and economic benefits for all loads. The NYPSC and NYISO have a highly coordinated transmission planning process, which integrates the NYPSC’s Comprehensive Grid Planning Process and the NYISO’s long-term planning process developed pursuant to Order No. 1920. In addition, each NYTO has bundled retail rates covering transmission and distribution revenue requirements established by the NYPSC.
The NYPSC is also currently presiding over a proceeding to address cost allocation and issues associated with large load interconnections.32 A July 14, 2026 Executive Order issued by New York Governor Kathy Hochul similarly directed the DPS to take certain action “to identify and resolve issues related to the interconnection of data centers, and other large loads, in order to support efficient interconnection of large new customers and the faithful compliance of ‘beneficiary pays’ principles as related to network upgrade and resource adequacy costs.”33 The July 14, 2026 Executive Order and Show Cause Order appear to be driven by similar or shared concerns. The cost allocation framework that the NYTOs ultimately include in a cost recovery agreement that they will submit for FERC review in a subsequent FPA section 205 filing will thus need to be developed in close coordination with DPS.
Specifically, the NYTOs will file under FPA section 205 a mechanism by which each Connecting Transmission Owner or Affected Transmission Owner, as applicable, will recover an allocable share of the cost of Transmission Owner Interconnection Facilities and Network Upgrades. Cost recovery will be obtained from the Eligible Customer taking transmission service on behalf of the large load or, where the Transmission Owner or Affected Transmission Owner
32 NYPSC Case No. 26-E-0045, Proceeding on Motion of the Commission to Address Interconnection Reforms for Large Loads, Order Instituting Proceeding and Soliciting Comments (Feb. 12, 2026).33 Exec. Order 62: Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Higher Standards for Data Center Development and Benefits Blueprint to Support Localities (July 14, 2026), https://www.governor.ny.gov/sites/default/files/2026-07/EO_62.pdf.
PDF page 15
15
and the large load customer enter into a cost recovery agreement directly, from the large load customer. The NYTOs intend to incorporate the NYPSC’s cost allocation determinations and to file with the Commission a proposed mechanism – likely in the form of a pro forma agreement and/or Tariff provisions – consistent with the Commission’s jurisdiction. In some cases, costs from upgrades may be shared among more than one Eligible Customer or large load customer in a load interconnection cluster. The NYTOs will also describe the security posting requirements as part of the rates, terms, and conditions applicable to large loads to address situations in which a large load triggers substantial investments in upgrades. The NYTOs intend to include these requirements in a legally enforceable framework set forth in a pro forma cost recovery agreement and/or Tariff provisions applicable to Eligible Customers or large load customers. Moreover, the NYTOs will provide for “head room adjustments” so that when a future Eligible Customer or large load customer, as appropriate, utilizes head room created by a Network Upgrade for which an earlier Eligible Customer or large load customer is paying charges to the Connecting Transmission Owner or Affected Transmission Owner, the earlier Eligible Customer’s or large load customer’s costs are reduced based on the cost responsibility allocated to the new Eligible Customer or large load customer.
NYISO commenced operations in 1999. The NYPSC has been regulating all aspects of Transmission Owner retail access programs including, in some cases, bundled retail transmission and distribution rates since 1996, when the NYPSC issued its landmark Opinion No. 96-12 directing utilities in New York to file, inter alia, “a schedule for the introduction of retail access” to the utilities’ customers.34 The NYPSC has also regulated cost allocation, rate design, and cost
34 In the Matter of Competitive Opportunities Regarding Electric Service, Case 94-E-0952, et al., Opinion No. 96-12 at 82 (1996).
PDF page 16
16
recovery associated with upgrade costs for all retail customers, including large retail access customers. The NYTOs intend to work collaboratively with NYPSC to establish transmission upgrade cost allocation, which would then be implemented through pro forma agreements and/or Tariff provisions to be submitted in the forthcoming FPA section 205 filing.35 In developing this mechanism, the NYTOs will consider structural approaches similar to the novel cost recovery arrangements the Commission has previously accepted.36 Such arrangements may include a minimum financial contribution from the large load customer or Eligible Customer, as applicable, toward the Transmission Owner’s transmission revenue requirement, coupled with a credit support or other financial security requirement sufficient to protect other transmission customers if the large load does not ultimately take the anticipated level of transmission service.
2. Revenue Crediting
The Commission also preliminarily found in the Show Cause Order that any payments made by an Eligible Customer (or by a large load) to a Transmission Owner pursuant to a cost recovery agreement should be appropriately credited toward the Transmission Owner’s transmission revenue requirements consistent with the Commission’s cost-of-service regulations37 if the costs allocated to the Eligible Customer were otherwise being recovered in FERC- jurisdictional rates. On this issue, the Commission noted that “it appears reasonable for filers of formula rates to provide a separate workpaper in the annual informational filing describing how
35 If the NYTOs propose in the forthcoming FPA section 205 filing – and the Commission accepts – a pro forma agreement, any non-conforming iterations of that agreement will be filed with FERC moving forward.36 See, e.g., Show Cause Order at P 75 & n.181 (citing Commonwealth Edison Co., 194 FERC ¶ 61,106 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,109 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,110 (2026); Commonwealth Edison Co., 194 FERC ¶ 61,113 (2026); PECO Energy Co., 193 FERC ¶ 61,148 (2025); Dayton Power & Light Co., 192 FERC ¶ 61,103 (2025); Dayton Power & Light Co., 189 FERC ¶ 61,220 (2024)).37 Id. P 91.
PDF page 17
17
any payments made pursuant to a cost recovery agreement are reflected in the transmission owner’s transmission formula rate.”38
In a forthcoming FPA section 205 filing, the NYTOs will provide for periodic NYTO- specific filings with the Commission describing whether the applicable NYTO has included costs of Network Upgrades allocated to one or more Eligible Customers or large load customers, as applicable, in the NYTO’s rate base in Commission-jurisdictional rates applicable to other transmission customers. Specifically, if a NYTO has included any such Network Upgrade costs in its FERC-jurisdictional rates applicable to other Eligible Customers or large load customers, the NYTO will provide for a revenue credit to the extent the NYTO is recovering those Network Upgrade costs. Alternatively, the NYTO may include in a Commission filing with its next update in the formula rate applicable to FERC-jurisdictional transmission service a statement that the NYTO has not included Network Upgrade costs allocated to specified Eligible Customers or large load customers in the NYTO’s rate base for FERC-jurisdictional rates paid by other transmission customers or that the NYTO has included only an allocable share of such costs and an explanation for the allocation.
3. Transmission Service Charges
In the Show Cause Order, the Commission preliminarily found that NYISO’s Tariff is unjust and unreasonable because it lacks transmission services reflecting Eligible Customers’ taking service on behalf of: (1) co-located load and/or load with behind-the-meter generation and
(2) flexible large loads that are willing and able to limit energy withdrawals from the transmission system under certain conditions.39 Among other things, the Commission directed the NYISO
38 Id.39 Show Cause Order at PP 101-110, 112-113.
PDF page 18
18
either to (1) explain whether the Tariff remains just and reasonable without an interim non-firm network transmission service while Network Upgrades are being constructed (i.e., Interim NITS) and without permanent firm and non-firm contract demand transmission services (transmission service up to a specified MW quantity, i.e., the contract level, on a firm or non-firm basis) or (2) propose Tariff revisions.40
The NYISO has indicated that, to address the Commission’s concerns, it intends to provide “Firm Withdrawal Service” for large loads that do not cause resource adequacy or transmission security adverse impacts or have completed all necessary resource adequacy supply and transmission security Network Upgrades as needed.41 For other large loads, NYISO will offer “Non-Firm Withdrawal Service.”42 NYISO has explained that large loads taking Firm Withdrawal Service “will be treated the same as other customers taking firm service, including having the same curtailment priority,” while large loads that take Non-Firm Withdrawal Service “will have a lower curtailment priority than NYISO’s firm transmission service, including Firm Withdrawal Service.”43
The NYTOs appreciate the NYISO’s efforts thus far and intend to collaborate closely with the NYISO to develop the constructs further. The NYTOs intend to work with the NYISO to ensure that the rates reflected in the charges associated with such new transmission services accord with the cost causation principle44 but reserve the right to utilize the NYTOs’ independent and
40 Id. PP 109, 113.41 NYISO Show Cause Order Presentation, supra note 6, at 32.42 Id.43 Id.44 See supra note 13.
PDF page 19
19
unilateral FPA section 205 filing rights under section 3.10(a) of the NYISO-TO Agreement if necessary.
Specifically, the NYISO has indicated it will settle with large loads or Eligible Customers taking service on behalf of large loads for certain charges under the NYISO OATT and Market Administration and Control Area Services Tariff, including applicable locational-based marginal prices at the Point of Withdrawal, which cover the transmission charges for congestion and marginal losses, and applicable ancillary service charges. These charges, however, do not address each NYTO’s embedded costs of transmission. Since the NYISO’s inception in 1999, the NYTOs have used a “license plate” rate design. Each NYTO uses an embedded cost formula rate, the Wholesale Transmission Service Charge (“TSC”), for “wheel through” and “export” transactions that exit the New York Control Area.45 In addition, as noted above, each NYTO has bundled retail rates covering transmission and distribution revenue requirements established by the NYPSC. Such NYPSC-established retail rates also include System Benefits Charges to support entry of new electric supplies, retention of nuclear resources, and other public policies. It is essential that rates applicable to large loads or Eligible Customers taking service on behalf of large loads reflect appropriate allocations of such System Benefits Charges as the NYPSC determines appropriate based on its consideration of all retail loads in the State.
The NYPSC also accounts for Wholesale TSC revenues, Transmission Congestion
Contract (“TCC”) auction revenues, congestion rents, and grandfathered transmission contract revenues that each NYTO receives or pays so that retail customers receive the benefits of transmission-related revenues and pay their allocable share of costs. This balancing of revenues,
45 See NYISO OATT Attach. H, § 14.1.
PDF page 20
20
demand, and costs is part of the development of the rates applicable to retail customers in New York, including large loads.
Each NYTO also has retail TSCs that are established by the NYPSC, including charges applicable to large load customers. Historically, each NYTO has referenced a state-approved retail service classification for such loads as provided for in the Retail Transmission section of the OATT (section 5). The NYTOs plan to continue this practice and will develop tariff provisions for submission to the NYPSC and NYISO OATT provisions for submission to FERC to identify how rates are established and updated from time to time. As is the case today, the applicable jurisdictional rates will be referenced in section 5 of the OATT and remain subject to FERC review.
The NYTOs will include in a forthcoming FPA section 205 filing any changes in rates deemed necessary in order to accommodate Firm Withdrawal Service and Non-Firm Withdrawal Service. The different forms of service may require changes in the billing determinants, billing units, demand allocators, and cost allocation mechanisms. The NYTOs are working on these issues and will consult the NYISO, NYPSC, DPS, and other stakeholders in advance of the FPA section 205 filing.
B. Large Load Interconnection Procedures and Agreements
The Commission preliminarily found in the Show Cause Order that the NYISO and/or NYTOs should modify the NYISO OATT and/or agreements to address: the scope and timing of interconnection studies, including the Facilities Studies; 46 the evaluation of transmission service requests for large loads;47 Eligible Customer or large load operational requirements – including
46
Show Cause Order at PP 65, 69.
47 Id. PP 65-66.
PDF page 21
21
dispatch, curtailment, and disconnection provisions that are subject to rights held by both the NYISO and the Connecting Transmission Owner and/or Affected Transmission Owner;48 information requirements, study deposits, and study assumptions and procedures;49 Facilities Study procedures;50 and interconnection agreement terms, conditions, and transparency.
1. Interconnection Study Provisions
The NYTOs are responsible for significant interconnection and transmission service study work associated with large loads. This work must be conducted in close coordination with the NYISO because of the bifurcated nature of the study process. Accordingly, without waiving any rights, the NYTOs intend to develop coordinated study processes with the NYISO and anticipate a unified set of terms and conditions that will be part of a NYISO or a potential joint NYISO- NYTO FPA section 205 filing.
The Commission acknowledged that the NYTOs bear a distinct and independent role in this process. Specifically, the Commission recognized that “the Transmission Owners may be partially responsible for conducting the studies that (1) evaluate whether a large load may be interconnected to the transmission system and served by the Eligible Customer and (2) determine whether Network Upgrades are necessary to provide transmission service.”51 The Commission further stated that it “appreciate[s] that this role may stem from how NYISO and the Transmission Owners allocated rights and responsibilities in the governing documents establishing NYISO” and expressly confirmed that it “do[es] not seek to alter that allocation of rights and responsibilities.”5248 Id. P 70.49 Id. P 46.50 Id. P 90.51 Id. P 58.52 Id.
PDF page 22
22
This acknowledgment is significant as it confirms that the NYTOs’ role in the study process is not merely derivative of NYISO’s obligations under the Tariff, but rather reflects an independent allocation of responsibilities that the Commission has expressly declined to disturb. The NYTOs are committed to working with the NYISO and stakeholders to address the Commission’s preliminary guidance. Consistent with the large load interconnection process improvements under development with the NYISO, the NYISO would continue to perform Load System Impact Studies (“Load SIS”) with improvements to make results more valuable. Following the Load SIS, as proposed by the NYISO, the NYISO and the Connecting Transmission Owner would engage in an alternate evaluation process in which NYISO identifies the bulk power system violations that must be addressed on a more granular level, and the Connecting Transmission Owner identifies the non-bulk system violations and proposed solutions for all of those violations in the Facilities Study.
As part of the Facilities Study, the NYISO would review the proposed solutions for their adequacy to resolve the identified bulk power system violations. This process entails a number of important handoffs and integrated coordination between the NYISO and the Connecting Transmission Owner. Certain aspects of the Facilities Study process thus may be best addressed through a coordinated FPA section 205 filing with the NYISO, rather than through unilateral action by the NYTOs. Accordingly, without waiving their section 205 rights, the NYTOs intend to work with the NYISO and stakeholders toward a coordinated FPA section 205 filing addressing the load interconnection and service processes because the NYTOs believe this will produce the most efficient results on a necessarily coordinated process. The NYTOs have a strong track record of working with the NYISO on shared responsibility for interconnection and transmission planning, as evidenced by the recent Order Nos. 2023 and 1920 compliance filings. The NYTOs anticipate
PDF page 23
23
working through the coordinated process with the NYISO to develop improved large load interconnection processes as well.
The NYTOs will work with the NYISO and stakeholders to address the following key elements with respect to the interconnection study provisions in the anticipated FPA section 205 filing:
First, the NYTOs will work with the NYISO and stakeholders to develop Tariff provisions governing the Facilities Study process for large load interconnections. Consistent with the coordinated approach described above, the NYTOs anticipate working with the NYISO and stakeholders toward Tariff provisions addressing, among other things, (1) the steps and process for conducting the Facilities Study, (2) the additional information the Eligible Customer or large load customer, as appropriate, must provide to the Connecting Transmission Owner in connection with the Facilities Study, and (3) the outputs of the Facilities Study, including the scope and form of the cost estimates and study report delivered to the Eligible Customer. Because the NYTOs bear primary responsibility for the Facilities Study due in part to the financial and operational risk associated with facilities needed to interconnect large load customers, the NYTOs are well- positioned to help develop these provisions.
Second, the NYTOs will work with the NYISO and stakeholders on the scope of the Load SIS, including modifications to account for the unique characteristics of certain large loads. Specifically, for large loads with unique load characteristics – such as those with arcuate or non- linear load profiles – the standard Load SIS scope might not be enough to thoroughly assess interconnection impacts. Additional specialized screenings may be required at an early stage of the study process – for example, unit interaction factor analysis – to determine whether a large load can interconnect to the transmission system without requiring Network Upgrades. The FPA
PDF page 24
24
section 205 filing will address whether such SIS scope modifications should be: (a) identified and applied at the Load SIS stage; or (b) addressed in the second phase of the study process, during which alternative upgrade evaluations are conducted. The NYTOs intend to develop this proposal further during the abeyance period in consultation with the NYISO and the other parties. Third, the NYTOs intend to address an appropriate timeline for the Facilities Study process, including provisions addressing the timeline within which the Connecting Transmission Owner would complete the Facilities Study and deliver the study report and cost estimates to the Eligible Customer, as well as milestones and readiness requirements applicable to the Eligible Customer or large load customer, as applicable, during the Facilities Study process. The NYTOs intend to develop the specific timeline provisions in consultation with the NYISO and stakeholders during the abeyance period.
Fourth, the NYTOs intend to address whether and how the Facilities Study process should require evaluation of alternative transmission technologies as a potential substitute for traditional Network Upgrades identified to accommodate a large load interconnection. Because the Connecting Transmission Owner develops the cost estimates and study report delivered to the Eligible Customer as part of the Facilities Study, the NYTOs are well-positioned to propose Tariff provisions requiring such an evaluation and, where traditional Network Upgrades are proposed instead, a clear explanation in the study report of why alternative transmission technologies were not selected.53
As with the generator interconnection process, these Facilities Study provisions require significant collaboration, handoffs, and coordination among the NYTOs and NYISO. While the substance of a Connecting Transmission Owner’s Facilities Study is primarily for the Connecting
53 Id. PP 67-68.
PDF page 25
25
Transmission Owner to determine, the NYTOs recognize that, as a practical matter, they will depend on certain NYISO inputs before the NYTOs can proceed with particular aspects of the Facilities Study. Such inputs include the development of base cases, identification of bulk system violations, and the results of the alternate evaluation process described. Close coordination on the timing of those inputs is essential, and the NYTOs accordingly intend to work closely with the NYISO to establish coordinated timelines and information-sharing protocols that account for this interdependency.
2. Pro Forma Interconnection Agreement
The Commission observed that the large load interconnection agreement is not included in the NYISO Tariff and is not subject to sufficiently clear or consistent pro forma provisions.54 As the Commission has recognized,55 the absence of pro forma provisions in the interconnection agreement between the Transmission Owner and the Eligible Customer undermines the Transmission Owner’s ability to enforce the operational and cost-recovery requirements that arise from the study process. The Transmission Owner – not NYISO – is the counterparty to the load interconnection agreement, and it is the Transmission Owner and its customers that bear the direct financial exposure to cost-shifting risk if the terms of that agreement are not standardized and clearly specified.
As noted, the NYPSC commenced a proceeding to review large load interconnection and related service requirements and cost allocation. Ideally, the NYPSC-developed requirements will be acceptable to the Commission for implementation without having to address any conflicts and jurisdictional or preemption issues. Subject to consultation with NYISO and DPS, the NYTOs
54 Id. PP 29, 90.55 Id. P 90.
PDF page 26
26
will develop pro forma terms and conditions that mirror terms approved by the NYPSC and are otherwise consistent across the state and federal levels.
The NYTOs anticipate that the FPA section 205 filing will propose pro forma agreement and/or Tariff provisions to create a legally enforceable framework that addresses the operational rights and obligations of all relevant parties with respect to the large load. Regardless of the ultimate form of the agreement(s) or Tariff provisions adopted, the NYTOs will work with the NYISO on an FPA section 205 filing to address, inter alia, the following rights and obligations:
(a) the NYISO’s and Connecting Transmission Owner’s rights to curtail, ramp down, and interrupt the large load; (b) the same rights of any Affected Transmission Owner, where applicable; and (c) a binding commitment of the large load to comply with all applicable operational requirements. The ultimate agreement should be designed to ensure that all parties with a need to (i.e., the NYISO, the Connecting Transmission Owner, and/or the Affected Transmission Owner) can enforce these rights and large load customer obligations.
The NYTOs also intend to address the structure of the interconnection agreement or agreements that will govern the relationship among the NYISO, the Connecting Transmission Owner, and the large load. The precise form of the agreement, agreements, or other Tariff changes has not yet been determined and will be the subject of further consultation between the NYTOs and NYISO during the abeyance period. The NYTOs commit to working with the NYISO and stakeholders on a legally enforceable framework addressing the rights and obligations of the parties with respect to these important matters.
PDF page 27
27
C. Operating Terms Applicable to Non-Firm Transmission Withdrawal Service
and Paired or Behind-the-Meter Generation Supplies
The NYISO is responsible for the reliability of the New York bulk power system.56 The NYTOs are responsible for the reliable operation of their systems, including local (non-bulk) transmission and distribution systems.57 The NYTOs also have certain obligations under New York State law concerning the reliable operation of their systems. With potentially large increases in the amount of new large loads on the system, and new non-firm or contract demand services, new operating requirements will be needed, as the Commission recognizes.58 The NYTOs will coordinate with the NYISO to develop operating requirements for loads that have chosen Non- Firm Transmission Withdrawal Service where the service level is less than the maximum potential withdrawal of the load and for supply paired with load, or that is behind-the-meter generation and requests Energy Resource Interconnection Service (“ERIS”) and/or Capacity Resource Interconnection Service (“CRIS”) at a level below the maximum potential injection. Associated large load customers and suppliers will be required to satisfy operating requirements allowing for dispatch, ramping, curtailment, interruption, and/or disconnection on an automated, NYISO- controlled or Connecting Transmission Owner/Affected Transmission Owner-controlled, and remote basis, depending on the circumstances.59
The NYTOs will work with the NYISO to develop a legally enforceable framework among the NYISO, NYTO, large load, and associated supplier – likely in the form of one or more pro forma agreements and/or Tariff provisions – to provide for operations requirements. In some cases, the successful installation and testing of system protection schemes will be necessary at
56 See, e.g., ISO Agreement, § 6.02; NYISO-TO Agreement § 3.01.57 See, e.g., NYISO-TO Agreement § 2.03.58 Show Cause Order at P 109.59 See id. P 113.
PDF page 28
28
energization and as a condition of continued operation. System protection and control schemes, where they can be deployed consistent with applicable reliability requirements, are tailored to the specific characteristics of the load, supply, and the bulk power system and local transmission and distribution system needs to maintain reliability in the areas of the system affected by the interconnection and service requirements. Each system protection and operations scheme will need to satisfy applicable reliability requirements as defined in the NYISO procedures.
IV. REQUEST FOR EXPEDITED COMMISSION ACTION AND SHORTENED
COMMENT PERIOD
The NYTOs respectfully request that the Commission act on this request on or before August 13, 2026, to provide the NYTOs with certainty regarding the need to file a response to the Show Cause Order and to allow the NYTOs to focus their efforts on coordinating with the NYISO and stakeholders on an FPA section 205 filing. Moreover, consistent with Rule 213(d) of the Commission’s Rules of Practice and Procedure,60 the NYTOs respectfully request that the Commission establish a 5-day comment period for any party wishing to respond to this request.
V. COMMUNICATIONS
All communications and correspondence regarding this filing should be forwarded to the following individuals, whose names should be placed on the Commission’s service list:6160 18 C.F.R. § 385.213(d)(1)(i) (“If a motion requests an extension of time or a shortened time period for action, then answers to the motion to extend or shorten the time period shall be made within 5 days after the motion is filed, unless otherwise ordered.”).61 The NYTOs respectfully request waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two individuals to be designated for service on the official service list in this proceeding.
PDF page 29
29
William R. Derasmo
C. Dixon Wallace III
Antonia M. Douglas
TROUTMAN PEPPER LOCKE LLP
401 9th Street NW, Suite 1000
Washington, DC 20004
(202) 274-2886
william.derasmo@troutman.com
dixon.wallace@troutman.com
antonia.douglas@troutman.com
Marina Chu
Regulatory Attorney – Regulatory Affairs
Central Hudson Gas & Electric Corporation
284 South Avenue
Poughkeepsie, NY 12601
mchu@cenhud.com
Phillip D. Demanchick Jr.
Senior Counsel
New York State Electric & Gas Corporation
Rochester Gas and Electric Corporation
180 South Clinton Avenue
Rochester, NY 14604
phillip.demanchick@avangrid.com
Christopher J. Novak
Senior Counsel
National Grid USA
170 Data Drive
Waltham, MA 02451
chris.novak@nationalgrid.com
Lauren A. Jones
Associate General Counsel
Joshua A. Kirstein
Senior Attorney
Consolidated Edison Co. of New York, Inc.
Orange and Rockland Utilities, Inc.
4 Irving Place
New York, NY 10003
jonesl@coned.com
kirsteinj@coned.com
VI. CONCLUSION
WHEREFORE, for the foregoing reasons, the NYTOs respectfully request that the Commission grant a full 90-day abeyance for the aspects of the Show Cause Order referenced above, including the deadline to respond to the Show Cause Order, commencing as of the deadline to respond to the Show Cause Order, to allow the NYTOs the time necessary to develop in coordination with the NYISO, NYPSC, and stakeholders, and file a comprehensive, regionally- tailored FPA section 205 filing that addresses the concerns identified in the Show Cause Order.
PDF page 30
30
Respectfully submitted,
/s/ William R. Derasmo
William R. Derasmo
C. Dixon Wallace III
Antonia M. Douglas
TROUTMAN PEPPER LOCKE LLP
Counsel to the New York Transmission Owners
/s/ Marina Chu
Marina Chu
Central Hudson Gas & Electric
Corporation
/s/ Phillip D. Demanchick Jr.
Phillip D. Demanchick Jr.
New York State Electric & Gas
Corporation
Rochester Gas and Electric Corporation
/s/ Christopher J. Novak
Christopher J. Novak
National Grid USA
/s/ Joshua A. Kirstein
Lauren A. Jones
Joshua A. Kirstein
Consolidated Edison Co. of New York, Inc. Orange and Rockland Utilities, Inc.
Dated: August 3, 2026
PDF page 31
CERTIFICATE OF SERVICE
I hereby certify that on this 3rd day of August, 2026, I have served a copy of the foregoing document on the official service list compiled by the Office of the Secretary for the captioned proceeding.
/s/ Daryl A. Bascus
Daryl A. Bascus
FERC Energy Specialist
TROUTMAN PEPPER LOCKE LLP
401 9th Street NW, Suite 1000
Washington, DC 20004
(202) 274-1949
daryl.bascus@troutman.com