Conditional Motion for Abeyance on Behalf of the Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California,
The Six Cities conditionally ask FERC to hold the 60-day show cause response deadline in abeyance for 90 days. The request becomes moot if FERC grants their pending motion to rescind the order.
Asks FERC to: Hold the 60-day deadline to respond to the show cause order in abeyance for 90 days, if the Six Cities' motion to rescind is not granted.
Invokes the E-10 CAISO show cause order's up-to-90-day abeyance option. FERC granted the Six Cities' rescission motion on August 14, 2026, which leaves this conditional request moot.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- The motion is conditional on the pending rescission request and is moot if that request is granted.
if that Motion to Rescind is granted, the Cities’ abeyance request will be moot. PDF p. 2
- The Six Cities rely on the show cause order's offer of an abeyance of up to 90 days.
to hold, for up to 90 days, all or certain aspects of this FPA section 206 proceeding in abeyance, including the deadline to respond to this order. PDF p. 3
- The cities need time to coordinate with CAISO's stakeholder proceeding and with co-owners and contract counterparties.
the Six Cities will need an additional 90 days to prepare responses to the Show Cause Order, develop potential revisions to each of their TO Tariffs PDF p. 4
- Any tariff revisions may need approval from a Public Utility Board or City Council.
each City will need to evaluate whether proposed revisions to their TO Tariffs to address the Show Cause Order require review and approval by the City’s Public Utility Board or the City Council PDF p. 4
Contents · 2 sections
Topics in the text: Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-71-000 CONDITIONAL MOTION FOR ABEYANCE ON BEHALF OF THE CITIES OF ANAHEIM, AZUSA, BANNING, COLTON, PASADENA, AND RIVERSIDE, CALIFORNIA Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure,1 the Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California…Read this passage
I. MOTION FOR ABEYANCE
printed heading · Topic match: Filing procedure
In the Show Cause Order, the Commission explained that it would consider requests “to hold, for up to 90 days, all or certain aspects of this FPA section 206 proceeding in abeyance, including the deadline to respond to this order.”8 The purpose of the abeyance, according to the Commission, is to…Read this passage
II. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION WHEREFORE, for the foregoing reasons, the Six Cities respectfully request that the Commission grant the Six Cities’ request to hold the 60-day deadline to respond to the Show Cause Order in abeyance for an additional 90 days.Read this passage
CERTIFICATE OF SERVICE
printed heading
McNaul Attorney for the Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California Law Offices of: Thompson Coburn LLP 1909 K Street, N.W., Suite 600 Washington, D.C. 20006-1167 202.585.6900 202.585.6969 (facsimile)Read this passage