Motion for Abeyance and Request for Shortened Answer Period and Expedited Treatment of Silver Run Electric, LLC
Silver Run Electric, a PJM transmission owner, moves for a 90-day full abeyance of the E-7 show cause deadline to November 16, 2026, and describes the tariff revisions it expects to propose with PJM through the stakeholder process.
Asks FERC to: Hold the proceeding in abeyance for 90 days from August 17, 2026, extend Silver Run's response to November 16, 2026, shorten the answer period to five days, and rule by August 13, 2026.
Seeks to move the E-7 60-day show cause deadline to November 16, 2026, outlining study process and cost recovery revisions it expects to file; FERC granted it on August 14, 2026.
E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-7 PJM: Application / study process (P 6(a), p. 7) E-7 PJM: Cost-recovery agreement (P 77, p. 28)
Key points
- Silver Run asks for a 90-day full abeyance to coordinate with PJM and prepare a section 205 filing.
Silver Run seeks a 90-day full abeyance of the current 60-day deadline to respond to all issues raised in the Show Cause Order PDF p. 1
- It expects revisions on large load definition, readiness requirements, alternative transmission technology evaluation and a pro forma service agreement.
the definition of a large load; readiness and information requirements; the evaluation of alternative transmission technologies; a pro forma service agreement memorializing operational terms PDF p. 5
- It expects cost recovery, financial security and rate provisions to mitigate cost shifting, and a reasonable implementation period.
cost recovery, associated financial security, and rate treatment provisions intended to mitigate cost shifting among transmission customers PDF p. 5
- Silver Run says its filing depends on PJM's stakeholder process because it runs none of its own.
Silver Run does not administer a stakeholder process of its own through which the issues raised in the Show Cause Order could be resolved independently. PDF p. 7
Contents · 6 sections
Read topic-matched comments in EL26-67
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-67-000 MOTION FOR ABEYANCE AND REQUEST FOR SHORTENED ANSWER PERIOD AND EXPEDITED TREATMENT OF SILVER RUN ELECTRIC, LLCRead this passage
I. INTRODUCTION
printed heading · Topic match: Filing procedure
Silver Run believes the potential tariff changes discussed in the Show Cause Order may provide opportunities for PJM and the transmission owning members of PJM (“PJM TOs”) to integrate large loads efficiently and further protect ratepayers across the PJM region from transmission-related costs…Read this passage Filed comments: Cost allocation
II. ARGUMENT
printed heading · Topic match: Filing procedure
ARGUMENT In the Show Cause Order, the Commission states that it will consider requests for abeyances of up to 90 days, which should include both (1) a robust description of the content of a potential future filing under FPA section 205 and (2) a reasoned and specific explanation of when such a…Read this passage
A. Proposed Tariff Revisions
printed heading · Topic match: Connecting load and generation
PP 57- 65. 4 characteristics and challenges of providing transmission service to Eligible Customers on behalf of large loads, or to propose appropriate Tariff revisions.8 Second, the Commission preliminarily found that the Tariff appears to be unjust and unreasonable because it lacks adequate…Read this passage Filed comments: Connecting load and generation
B. Briefing Questions
printed heading · Topic match: Filing procedure
Briefing Questions The Commission also identifies several issues for further briefing.15 Silver Run understands that, if the Commission grants the requested full abeyance, the deadline to respond to the briefing questions will likewise be held in abeyance.16 Silver Run believes an abeyance is…Read this passage
III. REQUEST FOR SHORTENED ANSWER PERIOD AND EXPEDITED
printed heading · Topic match: Filing procedure
The Commission directed that requests for a full or partial abeyance be submitted “within 45 days of issuance of this order, to allow time for the Commission to act on the abeyance request.” Id. 45 days from June 18, 2026 was Sunday, August 2, so under Rule 2007 of the Commission’s regulations,…Read this passage
IV. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the reasons described above, Silver Run respectfully requests that the Commission (i) grant this Motion and hold this proceeding in abeyance for 90 days beginning August 17, 2026, and extend Silver Run’s deadline to respond in full to the Show Cause Order to November 16, 2026; (ii)…Read this passage
CERTIFICATE OF SERVICE
printed heading · Topic match: Filing procedure
Dated at Silver Spring, Maryland, this 3rd day of August 2026. /s/ Seth Yeazel Seth Yeazel Associate Regulatory Counsel LS Power Development, LLC 16150 Main Circle Drive, Suite 310 Chesterfield, MO 63017 Tel: (240) 904-5109 syeazel@lspower.comRead this passage