EL26-70-000 · 2026-08-07 · American Municipal Power, Inc.

Answer of American Municipal Power, Inc. in Response to the Motion to Hold Abeyance filed by Midcontinent Independent System Operator, Inc. et al

American Municipal Power answers the MISO abeyance motion, saying it falls short of the Show Cause Order's standards, and asks FERC to condition any abeyance on a cost-transparency and cost-shifting proposal within 20 days and a compliance filing by November 16.

Asks FERC to: Direct MISO to present a cost-transparency and cost-shifting proposal within 20 days, vet it with states and customers, and file compliant Tariff revisions by November 16, 2026.

Opposes abeyance of the E-8 deadline unless MISO advances the order's cost-recovery agreement, financial security and cost-transparency directives; FERC granted abeyance but cited AMP's objection.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Minimum cost recovery / security (P 119, p. 74)

Key points

  1. AMP says the motion fails the Show Cause Order's abeyance standards, so FERC has grounds to deny it.
    The Motion fails to provide the information required by the Commission’s June 18 Show Cause Order in the event abeyance is sought PDF p. 1
  2. AMP names the missing protections: disclosure of upgrades and costs, cost recovery agreements, financial security and stranded-cost protection.
    public disclosure of large-load-driven network upgrades and their costs, cost recovery agreements, financial security requirements, and protection of existing transmission customers from stranded costs PDF p. 2
  3. AMP calls MISO's roadmap a few lines with a vague November filing.
    This falls well short of the detailed roadmap to compliance that the Commission required to justify abeyance. PDF p. 3
  4. AMP says upgrade costs are likely in the billions and MISO has presented no cost proposals in the stakeholder process.
    Costs associated with transmission upgrades to serve large loads are likely to be in the billions of dollars. PDF p. 4
  5. AMP says municipal and cooperative transmission-dependent utilities are not protected by state commissions because zonal cost allocation is wholesale.
    Transmission dependent utilities such as municipalities and cooperatives are not protected by state utility commissions and retail tariffs PDF p. 5
  6. AMP proposes three directives to MISO.
    bring forward a specific proposal to meet its obligations under the Show Cause Order to address cost transparency and cost shifting within the next twenty days PDF p. 5
Contents · 6 sections
  1. I. ANSWER p. 2
  2. A. The Show Cause Order identified critical issues for MISO to address p. 2
  3. B. The Show Cause Order adopted reasonable standards for evaluating p. 2
  4. C. MISO’s Motion fails to meet the standards for abeyance established in p. 3
  5. D. To expedite resolution of this matter, the Commission should p. 5
  6. II. CONCLUSION p. 6

Read topic-matched comments in EL26-70

Topics in the text: Filing procedure · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”)1 and the Commission’s notice,2 American Municipal Power, Inc. (“AMP”) respectfully submits this Answer in response to the abeyance motion filed by Midcontinent…
Read this passage

I. ANSWER

printed heading

I.
Read this passage

A. The Show Cause Order identified critical issues for MISO to address

printed heading

The Show Cause Order identified critical issues for MISO to address in Tariff revisions to be proposed through a compliance filing that remains due on August 17, 2026.
Read this passage

B. The Show Cause Order adopted reasonable standards for evaluating

printed heading · Topic match: Filing procedure

The Commission anticipated that MISO and the MISO Transmission Owners may need additional “time while they work through the stakeholder processes to develop FPA section 205 filings to revise the Tariff to address the issues raised in [the Show Cause Order].”5 The Show Cause Order indicated “that…
Read this passage

C. MISO’s Motion fails to meet the standards for abeyance established in

printed heading · Topic match: Cost allocation

P 37. 7 Id. 8 See id. 9 16 U.S.C. § 824d. 4 feedback requests as they are developed in anticipation of a November FPA section 205 filing to address any Commission directives not addressed in a prior FPA section 205 filing.10 Whereas the Commission has thoughtfully outlined its expectations in terms…
Read this passage Filed comments: Cost allocation

D. To expedite resolution of this matter, the Commission should

printed heading · Topic match: Cost allocation

There is a clear gap between the existing broad cost allocation methodologies applied to transmission projects in MISO generally, and a targeted allocation that is necessary to protect against cost shifting due to the addition of large loads.
Read this passage Filed comments: Cost allocation

II. CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully requests that the Commission issue an order containing the three directives described herein, and that the Commission grant such further relief as the Commission may deem appropriate.
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Hull Deputy General Counsel for Regulatory Affairs American Municipal Power, Inc. 1111 Schrock Road, Suite 100 Columbus, OH 43229 (614) 540-1111 Dated at Columbus, Ohio, this 7th day of August, 2026.
Read this passage