Comments of PJM Industrial Customer Coalition on PJM Interconnection, L.L.C.’s Reliability Backstop Procurement Proposal
The PJM Industrial Customer Coalition comments on PJM's July 31 Reliability Backstop Procurement proposal. It identifies three gaps in how wholesale backstop costs reach state retail rates: cost allocation alignment, regulatory accountability and information sharing.
Asks FERC to: Consider the Coalition's comments, and require that retail allocation methodologies be on file and that PJM tag backstop costs by load for states.
Comments in PJM's separate backstop procurement docket ER26-3380. Its call to trace backstop costs to individual large loads parallels the E-7 cost transparency directive and the E-7 adequacy report on generation for new load.
E-7 PJM: Cost transparency (P 71, p. 51) E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- The Coalition says PJM's backstop filing lacks tools to align wholesale charges with state retail cost allocation.
PJM’s filing lacks the tools needed to ensure that retail costs are, and will be, allocated in a just and reasonable manner at the state level. PDF p. 3
- Gap 1: wholesale costs must be designed with retail allocation in mind, tied to cost causation.
Wholesale costs must be designed with retail allocation in mind; otherwise, simply claiming that states can allocate costs to retail customers may prove inadequate. PDF p. 4
- Gap 2: utilities' retail allocation methodologies should be on file with FERC or a state commission.
While not mandating retail pricing, the FERC should require that methodologies be on file with the FERC or a relevant state commission. PDF p. 7
- Gap 3: PJM should add a separate billing line item for backstop costs, broken out by the load growth that caused them.
PJM should create a new billing line item (similar to how PJM separately reports Transmission Enhancement, Generation Deactivation, or other itemized costs) tagged specifically as “Reliability Backstop Procurement” costs PDF p. 8
- PJM should add subaccounts identifying each large load by interconnection point and issue billing guidance.
Under each billing line item related to RBP, PJM should add subaccounts identifying each individual large load customer by interconnection point. PDF p. 8
Contents · 9 sections
- I. INTRODUCTION
- II. BACKGROUND
- III. PJMICC COMMENTS
- A. The RBP, as proposed, is incomplete because it lacks key protections and components to enable alignment of wholesale and retail cost allocation.
- B. Gap #1: Cost Allocation Alignment: Effective cooperative federalism must position states and retail customers for success by providing appropriate alignment between wholesale and retail costs.
- C. Gap #2: Regulatory Accountability: Assignment of costs to retail customers by utilities must be on file before a state commission or FERC.
- Attachment M-2s stand at the border between state and federal regulatory responsibility.
- D. Gap #3: Information-Sharing: Clear tagging of RBP participation and relevant carveouts.
- IV. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
ER26-3380-000 : COMMENTS ON PJM’S RELIABILITY BACKSTOP PROCUREMENT PROPOSAL ON BEHALF OF PJM INDUSTRIAL CUSTOMER COALITION Pursuant to the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) August 3, 2026, Combined Notice of Filings #1, the PJM Industrial Customer Coalition (“PJMICC”…Read this passage
I. INTRODUCTION
printed heading · Topic match: Reliability and curtailment
INTRODUCTION As described by PJM, the Reliability Backstop Procurement (“RBP”) is a “one-time procurement of new capacity to address resource adequacy challenges in the PJM Region arising from insufficient commitments of capacity in the 2027/2028 and 2028/2029 Reliability Pricing Model (‘RPM’)…Read this passage Filed comments: Reliability and curtailment
II. BACKGROUND
printed heading · Topic match: Cost allocation
See also id. at 29 (“the proposed RBP is intended to occur concurrently, on a parallel path, with an ongoing bilateral matching process that credits new capacity being brought by new large loads and therefore guards against double procurement in the RBP”). 3 ultimate retail cost allocation…Read this passage Filed comments: Cost allocation
III. PJMICC COMMENTS
printed heading
III.Read this passage
A. The RBP, as proposed, is incomplete because it lacks key protections and components to enable alignment of wholesale and retail cost allocation.
PDF bookmark · Topic match: Cost allocation
The RBP, as proposed, is incomplete because it lacks key protections and components to enable alignment of wholesale and retail cost allocation.Read this passage Filed comments: Cost allocation
B. Gap #1: Cost Allocation Alignment: Effective cooperative federalism must position states and retail customers for success by providing appropriate alignment between wholesale and retail costs.
PDF bookmark · Topic match: Cost allocation
Gap #1: Cost Allocation Alignment: Effective cooperative federalism must position states and retail customers for success by providing appropriate alignment between wholesale and retail costs.Read this passage Filed comments: Cost allocation
C. Gap #2: Regulatory Accountability: Assignment of costs to retail customers by utilities must be on file before a state commission or FERC.
PDF bookmark · Topic match: Cost allocation
Gap #2: Regulatory Accountability: Assignment of costs to retail customers by utilities must be on file before a state commission or FERC.Read this passage Filed comments: Cost allocation
Attachment M-2s stand at the border between state and federal regulatory responsibility.
printed heading · Topic match: Cost allocation
While the FERC may not direct retail cost allocation, it has jurisdiction over rules and regulations “affecting or pertaining to [jurisdictional] rates and charges”10 Utilities must be required to set 9 PJM keeps an inventory of methodologies on its website.Read this passage Filed comments: Cost allocation
D. Gap #3: Information-Sharing: Clear tagging of RBP participation and relevant carveouts.
PDF bookmark · Topic match: Cost allocation
Additionally, states must know well in advance what information they will have access to as they design cost allocation at the retail level.Read this passage Filed comments: Cost allocation
IV. CONCLUSION
printed heading
CONCLUSION WHEREFORE, the PJM Industrial Customer Coalition respectfully requests the Commission to consider these Comments when evaluating PJM’s Reliability Backstop Procurement proposal.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 21st day of August, 2026. /s/ Matthew L.Read this passage