Positions read for this site
Each is a plain summary of one filing, checked against its pages. Where a stance is given, it is what the filing asks FERC to do with the proposal.
Office of the Ohio Consumers’ Counsel · ER26-3380-001 · 2026-10-29
On rehearing of the September order, OCC argued that households should not pay to cover a shortfall caused by data centers. It separately questioned FERC’s decision to allow sellers to receive their own bid prices.
Joint Consumer Advocates, including Delaware, D.C., Illinois, Maryland and New Jersey offices · ER26-3380-001 · 2026-10-29
The advocates estimated that buying 15 years rather than five could add $13 billion. They also warned that without a location requirement, customers could pay for capacity built far from the shortfall. These were their estimates and objections to the September order.
Public Service Commission of West Virginia · ER26-3380-000 · 2026-08-21
The West Virginia commission warned that complex rules could discourage participants from reporting qualifying capacity. That would make the final purchase larger than necessary.
American Municipal Power · ER26-3380-001 · 2026-10-13
AMP asked FERC to protect systems that did not cause the new demand. It also disputed the suggestion that the forecast table excluded projects PJM had actually counted.
Indicated PJM Transmission Owners · ER26-3380-001 · 2026-10-29
The owners argued that FERC should reject the original exit amendment on cost-causation grounds and that their agreement reserved the relevant filing right to them. Their rehearing request concerned the earlier wording.
Constellation Energy Generation · ER26-3380-001 · 2026-10-29
Constellation asked FERC to clarify that it had not assigned the departing owner’s share to suppliers by default. In its view an exiting owner, rather than captive customers, should bear exit costs it causes.
FirstEnergy Service Company · ER26-3380-001 · 2026-10-29
FirstEnergy compared supplier security of $1.5 million per MW under the earlier design with the much smaller security required of sellers. That objection predates the new $686,000 figure and serves here as a benchmark for the revised calculation.
FirstEnergy Service Company · ER26-3380-001 · 2026-10-29
FirstEnergy said the original shortfall charge stopped once a generator reached commercial operation. It questioned whether a seller then had sufficient incentive to perform throughout its 15-year term.
U.S. Department of Energy · ER26-3380-000 · 2026-10-07
DOE wanted a mandatory way to identify the large load driving additional procurement and give it a chance to build, bring or buy capacity. It questioned whether the proposed two-year lookback would capture the relevant projects.
Northern Virginia Electric Cooperative · ER26-3380-001 · 2026-10-29
NOVEC identified causes of the capacity shortage besides growth in large loads. It preferred voluntary subscription, with interruptible service for a customer that declined. NOVEC is a member-owned cooperative and does not speak for the Virginia regulator.
Public Service Commission of West Virginia · ER26-3380-000 · 2026-08-21
The West Virginia commission warned that complex rules could discourage participants from reporting qualifying capacity. That would make the final purchase larger than necessary.
Illinois Commerce Commission · ER26-3380-000 · 2026-08-19
The ICC supported a one-time supplemental purchase but wanted protection against forecast error, data for state regulators and no new obligations on states. It warned that a modest percentage error in a larger forecast could mean paying for substantial unneeded capacity.
Public Service Commission of West Virginia · ER26-3380-000 · 2026-08-21
The commission opposed the original filing in its proposed form and on its proposed timetable. It wanted PJM to learn how much demand would be covered by bilateral contracts before setting a central procurement target.
Pennsylvania Office of Consumer Advocate · ER26-3380-000 · 2026-08-21
The office argued that PJM was asking states to determine the shares suppliers would owe under a wholesale rate. It asked FERC to reject that design or explain how the new allocation would respect the line between state and federal authority.
Pennsylvania Office of Consumer Advocate · ER26-3380-000 · 2026-08-21
Pennsylvania’s consumer advocate objected to relying on states to determine wholesale obligations in the original July proposal. The distinction between a wholesale supplier’s share and retail cost recovery remained relevant when PJM refiled.
Data Center Coalition · ER26-3380-000 · 2026-08-21
The coalition supported offsetting a new load’s own capacity purchases and procurement through bilateral deals. It also wanted backstop costs charged to loads driving the need rather than customers elsewhere.
These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.
Cost allocation
ER26-3380-001 · 2026-10-13
2 allocated to Electric Distributor zone/areas that are not experiencing load growth attributable to data centers or other large loads, as such an allocation would be inconsistent with the cost causation principle. PDF p. 2
ER26-3380-000 · 2026-08-19
The ICC recommends that the Commission require sufficient mitigation efforts to protect against cost shifts to or any negative impacts on existing ratepayers, impose no new obligations upon the states, and require PJM to provide the clarifications, transparency, and access to data as discussed herein. PDF p. 2
ER26-3380-000 · 2026-08-21
” PJM also states that “PJM is not proposing a backup methodology for how RBP Charges should be allocated to non-jurisdictional, retail customers served by each of the LSEs in any Electric Distributor’s zone/area. PDF p. 4
ER26-3380-000 · 2026-08-21
2 facilitate responsible load growth, and support the development of new generation without imposing undue costs on existing ratepayers. PDF p. 2
ER26-3380-000 · 2026-09-10
”104 To meet their capacity needs, these ratepayers may enter into bilateral arrangements, which are inherently more flexible, including with respect to the length of the term required to support Qualifying RBP Offset UCAP MW, and which can be used to decrement the procurement target of the zone/area in which that ratepayer is located. PDF p. 36
ER26-3380-000 · 2026-09-28
4 While I have concerns that the specifics of PJM’s proposals are insufficient to grant ratepayers the protections they need, broadly these core concepts are deeply necessary, and FERC should work to implement and improve them as quickly as possible. PDF p. 2
ER26-3380-000 · 2026-08-20
Movants therefore request that the Commission require PJM to specify the backup default cost allocation with particularity and to demonstrate that it is just and reasonable as applied to zones and customer classes that neither caused nor benefit from the shortfall, including in the event a RERRA does not act within the RBP timeline. PDF p. 17
ER26-3380-000 · 2026-08-21
The RFI administered by Charles River Associates identified over 100 GW of prospective supply interested in participating;18 ensuring that market rules support—rather than discourage—this participation is essential to achieving the lowest possible procurement costs for ratepayers. PDF p. 5
ER26-3380-000 · 2026-08-21
Dominion does not oppose the underlying principle of PJM’s cost allocation approach for the RBP. PDF p. 4
ER26-3380-000 · 2026-08-21
Thus, the Backstop Auction would not insulate non-large load ratepayers from the impacts of large load growth. PDF p. 13
ER26-3380-000 · 2026-08-21
Thus, the Backstop Auction would not insulate non-large load ratepayers from the impacts of large load growth. PDF p. 13
ER26-3380-000 · 2026-08-21
To be clear, because a significant portion of this load growth is due to data center demand, the Board thinks that a subscription-based or “buy-bid” central procurement amount would have been better able to protect ratepayers from costs and risks associated with load growth from data centers and their uncertain load forecasts, as the procurement amount would be directly attributable to distinct data centers. PDF p. 4
ER26-3380-000 · 2026-08-21
A Viable Long-Term Solution to PJM’s Capacity Shortfall is a Bring Your Own New Capacity Framework that Protects Existing Ratepayers from Cost Shifts and Stranded Asset Risk Google has long advocated for the principle that new large loads should pay for the costs associated with the increase in demand that they are driving and the strain that puts on existing PDF p. 4
ER26-3380-000 · 2026-08-21
AMP strongly supports PJM’s proposal in this respect, as any allocation of RBP Charges to AMP or its members would be inconsistent with cost causation principles and the Ratepayer Protection Pledge. PDF p. 2
ER26-3380-000 · 2026-08-21
Shifting that unhedgeable component to RPM, so long as an RBP resource’s underlying installed capacity remains unchanged, would allow ratepayers to bear the actual cost of ELCC variability as it occurs, rather than an inflated risk premium embedded in every RBP bid whether or not that variability ever materializes. PDF p. 9
ER26-3380-000 · 2026-08-21
The proposed language would effectively treat capacity procured through previously executed bilateral contracts with existing generation resources the same as Qualifying RBP Offset UCAP MW for purposes of reducing an Electric Distributor zone/area’s allocation of the Initial RBP Target and, as a result, allocation of RBP Charges. PDF p. 6
ER26-3380-000 · 2026-08-21
RBP Cost Allocation Should Align with Load Procurement of its Own New Capacity. PDF p. 8
ER26-3380-000 · 2026-08-21
Specifically, the Commission should: (1) either reject PJM’s proposed Transmission Owner4 exit provisions or direct PJM to modify them to limit any continuing RBP financial obligation of a departing Transmission Owner to the RBP Charges already allocated to that Transmission Owner’s zone under the Commission- accepted RBP Charge cost allocation methodology, and confirm that any new provisions do not disturb the Commission’s established precedent governing Regional Transmission Operator 3 See RBP Proposal at 3. PDF p. 2
ER26-3380-000 · 2026-08-21
In other words, the most consequential cost allocation outcome in this proceeding would be determined not by a reasoned Commission judgment about cost causation, but by the pace of administrative implementation in individual states, RERRAs and Electric Distributor service territories. PDF p. 6
ER26-3380-000 · 2026-08-21
A capacity-cost allocation that fails to distinguish new, unusually large, data-center-driven load from the established industrial base would have immediate practical consequences. PDF p. 3
ER26-3380-000 · 2026-08-21
EKPC explains the uncertain cost allocation that LSEs face: Most concerning, PJM’s proposal for a default allocation methodology, should the Electric Distributor not report an RBO [“RBP Obligation”], is that all LSEs in the zone/area will be held accountable to pay the costs PJM assigns to the zone/area, regardless of whether they serve any large load or contributed to the need for backstop procurement. PDF p. 3
ER26-3380-000 · 2026-08-21
LIMITED PROTEST Notwithstanding Vistra’s general support of the proposal, Vistra submits this limited protest to address certain discrete issues and ensure that the RBP proposal is consistent with cost causation principles and is not unduly discriminatory. PDF p. 2
ER26-3380-000 · 2026-08-21
2 As set forth below, Blue Ridge is concerned that the lack of specificity in the RBP Proposal as to cost allocation to load-serving entities may result in unjust and unreasonable rates to Blue Ridge’s members. PDF p. 1
ER26-3380-000 · 2026-08-21
”39 If NOVEC (or others) cannot assign these costs directly to large loads, then the results should be viewed through the lens of whether the actual cost allocation is just and reasonable, and not whether a hypothetical allocation occurred. PDF p. 14
ER26-3380-000 · 2026-08-21
12 Specifically, the Commission should direct PJM to submit a compliance filing to revise the RBP Opt-Out, as follows: (d) Opt-Out When calculating the Final RBP Target, the Initial RBP Target shall also be decremented where the Electric Distributor’s zone/area has rates that are not regulated by the states and is unable to address cost allocation associated with capacity procured in the backstop includes load that is 12 PJM Transmittal Letter at 3. PDF p. 8
ER26-3380-000 · 2026-08-21
12 mechanism fails because a “generalized showing of regional reliability need” is insufficient to support the “particular RBP rate design” under FPA section 205,49 and the zonal or Electric Distributor cost allocation process does not ensure the assignment of RBP obligations to the specific LSE responsible for supplying the large load. PDF p. 12
ER26-3380-000 · 2026-09-02
6 The Attorney General is equally concerned that steps should be taken to ensure that ratepayers are protected from the potential unjust and unreasonable cost allocation that could occur under the proposal. PDF p. 2
ER26-3380-000 · 2026-09-02
These supplemental comments address one narrower issue that has been sharpened by subsequent filings: whether the original determination of cost causation should remain fixed over a long-duration RBP obligation when the underlying facts materially change. PDF p. 1
ER26-3380-000 · 2026-09-04
As a result, potentially allocating to EKPC any costs related to RBP selected resources should, at some point over the next 15 years, EKPC contemplate exit from PJM is completely divorced from cost causation and not just and reasonable. PDF p. 3
ER26-3380-000 · 2026-09-08
Second, it uses fifteen years of gross contract value rather than the net RBP Charges that LSEs actually will be billed, should RBP Resources not be segregated from the market. PDF p. 6
ER26-3380-000 · 2026-09-29
ENABLING THE SAME RESOURCES TO SUPPORT BOTH QRBPO AND BYONC ALIGNS INCENTIVES AND SUPPORTS THE OVERALL DESIGN OF PJM’S LARGE LOAD RESOURCE ADEQUACY SOLUTIONS Without this or similar adjustment in the final tariff filing, BYONC arrangements incorporating reactivated locations will not function to reduce the volume of RBP central procurement, resulting in duplicative matching of new capacity volumes to DY27/28 and DY28/29 load additions, along with the unnecessary imposition of socialized risk across all ratepayers in the PJM footprint. PDF p. 4
ER26-3380-001 · 2026-10-29
62 The assertion that RPM-cleared resources support the pooled regional requirement or that additional capacity may confer regional reliability benefits does not explain why PJM recognizes an LSE’s contribution when reducing the regional target yet disregards that contribution when determining the LSE’s own RBP Charges and collateral obligation. PDF p. 14
ER26-3380-001 · 2026-10-29
In addition, the paper hearing should distinguish ordinary RBP Charges attributable to load that departs PJM from incremental costs created by the Transmission Owner’s withdrawal, including pseudo-tie, accelerated-payment, contract-preservation, and stranded-obligation costs. PDF p. 18
ER26-3380-001 · 2026-10-29
To do otherwise would be to impose manifestly unjust and unreasonable costs on ratepayers. PDF p. 12
ER26-3380-001 · 2026-10-29
The amount of RBP charges for PJM’s proposed procurement total of 6,831 MWs at a rate of $555/MW-day x 365 days x 15 years would be $20,756,847,375. PDF p. 24
ER26-3380-001 · 2026-10-29
Should the Commission’s clarification restrict the scope of the paper hearing, then NOVEC seeks rehearing of any limitations imposed on the scope of the paper hearing insofar as cost allocation associated with RBP is concerned. PDF p. 1
ER26-3380-001 · 2026-10-29
The combination of a more stringent shortage penalty with a structure that allocated such costs either to the developers or the load causing the costs to be incurred would be fair, follow cost causation principles and protect all other consumers in Ohio and elsewhere in PJM. PDF p. 21
ER26-3380-000 · 2026-10-07
4 PJM should implement the cost allocation and other reforms identified by the Commission to ensure that the costs of serving new data centers or other large electric energy loads are not unfairly shifted to PJM’s existing ratepayers. PDF p. 2
Credit and exit
ER26-3380-000 · 2026-09-10
This would allow LSEs to make long-term plans for such RBP Charges, including arrangements to post collateral, and avoid scenarios where new load bilaterally contracts for new capacity but subsequently gets allocated RBP Charges. PDF p. 61
ER26-3380-000 · 2026-08-21
Additionally, PPL Electric requests clarification on a specific credit collateral contingency, as discussed below in Section III. PDF p. 2
ER26-3380-000 · 2026-08-21
Data centers would likely be more realistic about their capacity needs if they have to put down collateral. PDF p. 24
ER26-3380-000 · 2026-08-21
Data centers would likely be more realistic about their capacity needs if they have to put down collateral. PDF p. 24
ER26-3380-000 · 2026-08-21
However, the Board is concerned that the size of the collateral requirements may make it difficult for LSEs to secure the required collateral. PDF p. 5
ER26-3380-000 · 2026-08-21
Upfront Collateral: To ensure financial stability of the requesting customer, regulators should consider the appropriate role for upfront collateral to provide financial assurance to the utility that the long-term contract minimums can be met. PDF p. 7
ER26-3380-000 · 2026-08-21
Modify the proposed RBP Collateral provisions so that the RBP Credit Rate is calibrated to reasonably foreseeable forward exposure and the forms of credit support accepted under Tariff, Attachment Q are available. PDF p. 6
ER26-3380-000 · 2026-08-21
3 MW × $1,500,000/MW = $10,246,950,000) would need to be posted by LSEs as collateral no later than 45 days ahead of the start of the 2028/2029 Delivery Year. PDF p. 7
ER26-3380-000 · 2026-08-21
LIMITED PROTEST OF CERTAIN CREDIT AND COLLATERAL PROVISIONS The Commission should exercise its authority to modify the proposed Tariff language to clarify two aspects of the credit and collateral provisions in the proposed Tariff. PDF p. 16
ER26-3380-000 · 2026-08-21
FERC should direct PJM to strengthen supplier performance and credit requirements; and 9. PDF p. 2
ER26-3380-000 · 2026-08-21
PJM Must Clarify That RBP Collateral Obligations Apply to Load Serving Entities, Not Electric Distributors, Because Credit Responsibility Should Follow the Entity Responsible for RBP Charges PJM proposes to require that those LSEs allocated responsibility for RBP Charges for a given Delivery Year must post credit associated with that obligation. PDF p. 32
ER26-3380-000 · 2026-08-21
The Commission should Deny PJM’s Default Allocation Proposal and Require PJM to Use Sub-Accounts to Allocate Costs to Large Load RESA supports PJM's RBP Proposal to the extent that it assigns RBP costs and collateral obligations to the LSE serving the Large Load Customers that cause those costs. PDF p. 5
ER26-3380-000 · 2026-08-21
EKPC explains the uncertain cost allocation that LSEs face: Most concerning, PJM’s proposal for a default allocation methodology, should the Electric Distributor not report an RBO [“RBP Obligation”], is that all LSEs in the zone/area will be held accountable to pay the costs PJM assigns to the zone/area, regardless of whether they serve any large load or contributed to the need for backstop procurement. PDF p. 3
ER26-3380-000 · 2026-08-21
If the Commission does not reject the RBP, it should require revisions on compliance to eliminate or substantially reduce the nearly $2 billion collateral requirement that the RBP Proposal would impose on NOVEC, and to eliminate the resulting subsidization of the PJM capacity market by NOVEC and a relatively small number of the other Load Serving Entities (“LSEs”) that would be primarily responsible for providing financial security for the contracts that PJM would enter into with RBP Resources. PDF p. 1
ER26-3380-000 · 2026-08-21
PJM should confirm that the Tariff is what it intends for RBP Default Allocation. PDF p. 2
ER26-3380-000 · 2026-08-21
At the start of each Delivery Year, the registry would capture Large Load meter-level information to facilitate billing and collateral tracking, accommodate LSE switching in retail choice states, and address corporate ownership changes. PDF p. 10
ER26-3380-000 · 2026-09-08
PJM does not explain why the exposure arising before collateral can be drawn and any residual default reallocated should be measured by one-half of a fifteen-year gross payment stream. PDF p. 6
ER26-3380-001 · 2026-10-29
The RBP assigns long-term costs and collateral obligations through a framework that lacks the specificity necessary to be just and reasonable because the RBP does not sufficiently identify the LSE responsible for causing the capacity shortage, does not ensure that any offsets or opt-outs follow the entity that secured them, and does not protect LSEs whose existing resource portfolios already support their expected load obligations from incurring 28 Coscia Protest Affidavit at PP 159-61. PDF p. 6
ER26-3380-001 · 2026-10-29
10 In an abundance of caution, Constellation also requests clarification that the paper-hearing procedures leave fully open the collateral, Transmission Owner exit-charge, and cost-allocation issues identified below. PDF p. 3
Reliability and curtailment
ER26-3380-001 · 2026-10-13
Clarification is also appropriate to resolve the incongruity between, on the one hand, the Commission’s aim of ensuring that RBP costs are allocated to zone/areas with large load growth driving resource adequacy deficiencies, and, on the other hand, the likelihood that its proposed cost allocation method would allocate RBP costs to zone/areas without new large loads. PDF p. 7
ER26-3380-000 · 2026-08-19
The ICC generally supports PJM’s proposal to implement a one-time, supplemental procurement of new capacity to address the identified resource adequacy shortfall that aligns with the National Energy Dominance Council/PJM Governors’ Principles and the Commission’s recognition of the need for action. PDF p. 1
ER26-3380-000 · 2026-08-21
5 OPSI hopes that this targeted intervention will bolster regional resource adequacy by addressing the present-day capacity shortfall, which would not have occurred but for large loads, while complementing the ongoing bilateral matching process. PDF p. 2
ER26-3380-000 · 2026-08-21
Given the urgency of PJM’s resource adequacy challenge, DCC supports moving forward with the RBP as a limited, one-time backstop. PDF p. 2
ER26-3380-000 · 2026-09-10
18 Dominion Partial Protest and Comments at 3 (“Dominion generally supports the RBP as a one-time procurement to bring the PJM region to a more stable state of resource adequacy and pave the way for holistic market design reforms that will support the infrastructure needed to reliably serve load growth in the region. PDF p. 5
ER26-3380-000 · 2026-09-28
I support one key idea across both PJM’s Reliability Backstop Procurement (RBP) and Interim Resource Adequacy Service (IRAS) – ensuring that data centers are responsible for bringing new generation capacity to the grid. PDF p. 2
ER26-3380-000 · 2026-08-21
INTRODUCTION SEIA does not oppose PJM’s RBP Proposal as a necessary and timely response to the resource adequacy challenges facing the PJM Region. PDF p. 2
ER26-3380-000 · 2026-08-21
3 As explained below, Dominion generally supports the RBP as a one-time procurement to bring the PJM region to a more stable state of resource adequacy and pave the way for holistic market design reforms that will support the infrastructure needed to reliably serve load growth in the region. PDF p. 3
ER26-3380-000 · 2026-08-21
FERC should reject the tariff revisions because PJM can address its resource adequacy mechanisms through other means at lower cost and with less risk of cost-shifting. PDF p. 14
ER26-3380-000 · 2026-08-21
FERC should reject the tariff revisions because PJM can address its resource adequacy mechanisms through other means at lower cost and with less risk of cost-shifting. PDF p. 14
ER26-3380-000 · 2026-08-21
Rather than accepting constant change and uncertainty, the Commission, PJM, and all stakeholders should focus on developing the stable, predictable investment conditions that will facilitate the investments needed to extricate PJM from its present resource adequacy shortfall and maintain resource adequacy in the long-term. PDF p. 4
ER26-3380-000 · 2026-08-21
SUMMARY CPV supports the RBP Proposal and believes it is a critical step toward restoring resource adequacy in the PJM region. PDF p. 1
ER26-3380-000 · 2026-08-21
3 United generally supports PJM’s July 31, 2026, filing as the best available solution to address the pressing challenge of rapid load growth and slow resource entry in a manner that avoids putting even greater cost burden on existing customers not contributing to the resource adequacy shortfall. PDF p. 1
ER26-3380-000 · 2026-08-21
INTRODUCTION Equinix supports PJM’s RBP approach as a one-time response to a severe resource adequacy shortfall posing a near-term threat to reliability. PDF p. 4
ER26-3380-000 · 2026-08-21
7 This modest adjustment to PJM’s proposal will allow the RBP to procure the megawatts needed to address PJM’s immediate resource adequacy shortfall, while preserving RPM’s effectiveness for price formation in support of long-term resource adequacy. PDF p. 2
ER26-3380-000 · 2026-08-21
Although PJM cites the 2028/2029 Delivery Year resource adequacy shortfall as the basis for the proposal, PJM has not shown that delaying commencement of the procurement for a reasonable period would undermine the stated objectives of the RBP. PDF p. 18
ER26-3380-000 · 2026-08-21
AEP has urged PJM to aggressively address both the current resource adequacy crisis and the existing structures that gave rise to the shortfall, and supports measures to address the PJM region’s capacity shortfall. PDF p. 2
ER26-3380-000 · 2026-08-21
SUMMARY AND REQUESTED COMMISSION ACTION OELC supports the objective of maintaining resource adequacy and recognizes the need for timely, durable action where new load growth is genuinely causing incremental capacity needs. PDF p. 1
ER26-3380-000 · 2026-08-21
Vistra generally supports the proposal to use a backstop mechanism to address near-term the resource adequacy needs in the PJM system, even as Vistra believes it is critically important to ensure that the “ordinary” tools for ensuring resource adequacy, including the Reliability Pricing Model (“RPM”), remain the principal mechanisms by which PJM meets that critically important goal. PDF p. 1
ER26-3380-000 · 2026-08-21
2 (c)(iii) appears to apply to the commercial relationship between curtailment service providers and flexible loads that may not be supported by physical assets, and incorporates additional limitations that would not appropriately apply to Qualifying RBP Offset UCAP MW provided by behind-the-meter generation projects. PDF p. 3
ER26-3380-000 · 2026-08-21
FERC should order PJM to revise its RBP auction structure to be subscription-based with the load growth that is not subscribed being subject to curtailment by default, as contemplated by the stakeholder proposal. PDF p. 26
ER26-3380-000 · 2026-08-21
”45 EKPC shares PJM’s concern about resource adequacy and the reliability challenges facing the PJM region, and EKPC supports measures that maintain resource adequacy 42 PJM RBP Filing at 22 (“[T]he PJM Board adopted various concepts from the Coalition RBP Proposal that received a sector-weighted majority of stakeholder support. PDF p. 10
ER26-3380-000 · 2026-08-24
Further, E-Cubed asks the Commission to reject PJM’s RBP proposal for the reasons cited herein and implement the proposed budget approach to improve resource adequacy in PJM even incrementally. Source text
ER26-3380-000 · 2026-09-02
7 In general, the Kentucky Attorney General is concerned with the potential for others to free ride on the prudent resource adequacy decisions made by Load Serving Entities in Kentucky. PDF p. 2
ER26-3380-000 · 2026-09-02
material changes in large-load status, timing, commitment, responsible entity, default condition, or resource adequacy contribution trigger appropriate revalidation; residual or default-related costs are not automatically reassigned to prudent Load Serving Entities without a fresh evidentiary determination supporting continued causation; and long-duration cost obligations remain tied to evidence that continues to support the underlying causation conclusion. PDF p. 5
ER26-3380-000 · 2026-09-29
ENABLING THE SAME RESOURCES TO SUPPORT BOTH QRBPO AND BYONC ALIGNS INCENTIVES AND SUPPORTS THE OVERALL DESIGN OF PJM’S LARGE LOAD RESOURCE ADEQUACY SOLUTIONS Without this or similar adjustment in the final tariff filing, BYONC arrangements incorporating reactivated locations will not function to reduce the volume of RBP central procurement, resulting in duplicative matching of new capacity volumes to DY27/28 and DY28/29 load additions, along with the unnecessary imposition of socialized risk across all ratepayers in the PJM footprint. PDF p. 4
ER26-3380-001 · 2026-10-29
The RBP assigns long-term costs and collateral obligations through a framework that lacks the specificity necessary to be just and reasonable because the RBP does not sufficiently identify the LSE responsible for causing the capacity shortage, does not ensure that any offsets or opt-outs follow the entity that secured them, and does not protect LSEs whose existing resource portfolios already support their expected load obligations from incurring 28 Coscia Protest Affidavit at PP 159-61. PDF p. 6
ER26-3380-001 · 2026-10-29
Those distinctions concern the very factors the Commission has considered when balancing the reliability rationale for out-of-market support against its effect on market price formation and the potential impacts on resource adequacy in the long-term: purpose, magnitude, duration, and certainty of need. PDF p. 12
ER26-3380-001 · 2026-10-29
39 Nor does the September 29 Order explain how ELCC accreditation—a measure of a resource's contribution to resource adequacy— accounts for the inertia, dynamic reactive support, frequency response, and voltage control that NERC identified as needed for reliability. PDF p. 11
ER26-3380-001 · 2026-10-29
Allowing capacity and load to be added without accounting for locational resource adequacy would also result in higher energy market prices and increased transmission costs. PDF p. 30