ER26-3380-000 · 2026-08-21 · New Jersey Board of Public Utilities
Comments of New Jersey Board of Public Utilities in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, LLC
)
)
Docket No. ER26-3380-000
COMMENTS OF THE NEW JERSEY BOARD OF PUBLIC UTILITIES
The New Jersey Board of Public Utilities (“Board”) files these comments in response to PJM Interconnection, L.L.C.’s (“PJM”) revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities to establish the Reliability Backstop Procurement (“RBP”). The Board appreciates the haste with which this proposal was filed and underscores the importance of moving forward with this proposal amid significant regional resource adequacy concerns. While there are certain elements to the RBP that the Board would have pursued differently, the Board overall supports PJM’s proposal.
I. The RBP Addresses System Reliability Needs
First, the Board supports the Tariff revisions to add the targeted one-time procurement RBP starting in 2026, rather than relying on existing Tariff language which states that the Reliability Backstop Auction (“RBA”) will be triggered only after three Base Residual Auctions (“BRA”) clear sufficiently short of capacity. The BRAs for the 2027/2028 and 2028/2029 Delivery Years (“DY”) have cleared short by 6.61 and 6.8 GW,2 respectively, and this deficit is only predicted to
1 PJM Auction Procures 134,479 MW of Generation Resources, PJM Interconnection, L.L.C., 1 (Dec. 17, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2025-releases/20251217-pjm-auction procures- 134479-mw-of-generation-resources.pdf [https://perma.cc/A89W-W99B].
2 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 3 (July 14, 2026), https://www.pjm.com/- /media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra results-report.pdf [https://perma.cc/A53K-TXXY].
PDF page 2
2
grow: PJM predicts summer peak load increases of 65.7 GW over the next 10 years and 96.7 GW over the next 20 years.3 Meanwhile, significant barriers to new supply resources remain. New supply developers face higher overall costs and market risks due to a variety of factors, including uncertainty surrounding future load forecasts and federal policy, expected capacity market reforms, existing supply chain constraints, siting and permitting challenges, and a recently backlogged interconnection queue. PJM itself has found that new ideas and reforms are needed to bring new supply to the market – the current market structures and one-year price signal no longer provide revenue streams that are sufficiently high or dependable for many new supply developers in this environment.4
The Board similarly issued a report on August 12 noting that the current capacity market could not bring new supply to the market and provide reliability at lowest cost for ratepayers.5 Among the conclusions and recommendations in the report, the Board noted that (1) data center large loads are the primary causes of the supply shortfall and should be required to pay for the new generation they require,6 and (2) long-term contracts can help provide price certainty for new investments in generation.7 Therefore, among the myriad reforms PJM is pursuing to address this supply-and-demand imbalance, the RBP addresses an important gap.
The best way to manage the needs for large loads is through bilateral contracts – that way, the large loads can work directly with developers to manage the costs and risks of building new
3 PJM Interconnection, L.L.C., 2026 Load Forecast Report Tables tbl. B1 (2026), https://www.pjm.com/- /media/DotCom/planning/res-adeq/load-forecast/2026-load-report tables.xlsx.4 See generally, PJM Interconnection, L.L.C., Powering Reliability Through Market Design (May 2026) (“PJM’s Market Report”), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506- powering-reliability-through-market-design.pdf.5 N.J. Bd. of Pub. Utils., An Investigation of PJM’s Capacity Market (Aug. 2026), https://nj.gov/bpu/pdf/reports/AN_INVESTIGATION_OF_PJMs_CAPACITY_MARKET_FINAL_8.12.26.pdf6 Id. at ii, 64.7 Id. at ii, 66.
PDF page 3
3
supply. Bilateral contracts between new large loads and new supply resources are the most effective way to protect ratepayers from costs and risks associated with load growth from data centers. Therefore, the Board appreciates how PJM’s RBP proposal encourages bilateral contracts between incoming large loads and qualifying new supply resources. This includes PJM’s retention of Charles River Associates to facilitate confidential and bilateral matchmaking, the offset of new large loads that have procured capacity from the initial RBP target, coupled with an allocation of RBP costs only to those that have not procured their own capacity, and the broader eligibility of resources that qualify for bilateral contracts compared to the RBP. The Board hopes the bilateral matchmaking process underway meaningfully reduces the procurement target and subsequent costs from the RBP, as these contracts help insulate customers from the risks and costs attributable to these new large loads.
The RBP’s centralized procurement terms, which provide a price commitment of up to 15 years for qualified new supply resources, will also help attract new supply resources. The Board supports PJM’s proposed Tariff revisions to conduct this backstop before waiting for an additional BRA to clear short. The Board also supports assigning the costs of this procurement to zones in proportion to their expected large load additions. This is necessary to ensure large loads can be made responsible for the costs, while recognizing that states have ultimate authority over retail cost allocations. This RBP effort is a step in the right direction today – but, in the long term, PJM must continue to coordinate with stakeholders to develop robust reforms in its Powering Reliability Through Market Design workstream.
The above support does not come without some concerns worth noting, however. The Board understands PJM’s reasoning for basing the central procurement target amount on the 2028/2029 BRA shortfall of 6.8 GW, despite the Joint Electric Distribution Companies and Data
PDF page 4
4
Center Coalition proposal—the only proposal to receive more than two-thirds sector-weighted member support—recommending a subscription-based procurement target. To be clear, because a significant portion of this load growth is due to data center demand, the Board thinks that a subscription-based or “buy-bid” central procurement amount would have been better able to protect ratepayers from costs and risks associated with load growth from data centers and their uncertain load forecasts, as the procurement amount would be directly attributable to distinct data centers. Therefore, the procurement target could be directly aligned to interested large loads, and costs would be allocated with more accuracy to these incoming large loads. However, the Board realizes that this would require additional time before the backstop could be initiated and understands the importance of running this backstop procurement promptly. The Board will work closely with other state entities and utilities to ensure that these costs are properly allocated to incoming data centers.
Furthermore, while the Board appreciates many of the requirements and the standardization of eligible supply resources for the RBP, the Board would have liked to see more flexibility for the participation of demand response (“DR”) and distributed energy resources (“DER”). DR and DER resources are intrinsically very different from generating resources, and requiring these resources to provide “customer agreements or binding commitments with identified locations and customer names” that can serve the MW for 15 years is very onerous.8 DR and DER resources build their business models expecting customer turnover; it is not reasonable to expect these resources to pre- specify customers for the RBP contract period. The Board thinks PJM should have pursued more flexible options for these resources – allowing these resources, for instance, to replace contracted customers to satisfy the RBP obligation. The Board recommends more flexibility for DR and DER
8 PJM Interconnection, L.L.C., Initiating Filing at 74, Docket No. ER26-3380 (July 31, 2026).
PDF page 5
5
resources to encourage greater participation and unlock demand-side tools for the region in an environment where they are sorely needed.
The Board also has concerns about the opportunity for market power to arise in PJM’s
selection process. Specifically, projects with an earlier Delivery Year may be overly favored over cost concerns. In PJM’s centralized procurement, resources with earlier Delivery Years are chosen first, up to the maximum willingness-to-pay cap of $555/MW-day UCAP; however, if these
resources lead to a higher average price in early DYs and don’t initially clear, they can clear later in the process if lower-cost resources selected in later DYs create “room in the budget” to select these higher-cost, earlier-DY offers. PJM, stakeholders, and the Federal Energy Regulatory Commission (“FERC”) should monitor the results of the RBP to ensure it produces an efficient outcome with just and reasonable results. Similarly, the Board has concerns that the pay-as-bid market structure, compared to PJM’s uniform clearing price in the capacity market, would create inefficient market outcomes or allow for market manipulation. PJM and FERC must monitor, as much as possible, how this structure affects auction results.9
Finally, the Board has concerns about the collateral requirements for LSEs.10 The Board
appreciates PJM’s efforts intended to protect consumers from the risk of stranded RBP costs. However, the Board is concerned that the size of the collateral requirements may make it difficult for LSEs to secure the required collateral. In theory, an LSE would pass on the collateral costs to
9 PJM lists the benefits of a pay-as-bid model in its filing to support its proposed auction structure. However, this market design does not inherently provide lower costs to customers, as the PJM filing suggests. In a pay-as-bid market structure, developers are unlikely to bid at their marginal cost, for they would not make a profit. Instead, developers are expected to bid strategically by submitting offers near an estimated market-clearing price, with larger market participants often having more resources to forecast the clearing price and bid at or near those forecasts. Ultimately, however, it will be difficult to assess the competitiveness and efficiency of this RBP under the pay-as-bid structure because stakeholders will not have access to the data and models developers used to set their final bid price. 10 PJM Interconnection, L.L.C., Initiating Filing at 114, ER26-2563 (July 31, 2026).
PDF page 6
6
the large load, but there may need to be additional forcing mechanisms in restructured states where retail choice and default service has been the assumed retail system. This type of collateral requirement will put pressure on the retail-jurisdictional authorities to ensure the collateral obligation does not fall upon ratepayers. While the Board does not provide a solution at this time, the Board and stakeholders could have used additional time to build a more thoughtful collateral system.
The Board hopes that the RBP will succeed and attract new resources to the PJM system to address large load growth. The Board also hopes that PJM, FERC, and all stakeholders will take the lessons learned from this process and the results to inform future market reform efforts.
II. The RBP Opt-Out and Needed Clarification
The Board appreciates PJM’s opt-out provisions that complement certain state laws. New Jersey recently passed the Data Center Fair Share Act (“Act”) to help protect customers from the load impacts of new data centers in the state.11 The Act aims to provide data centers the opportunity to offset their load contributions through voluntary load reduction agreements with third parties. Under one such available program specifically mentioned in the Act, the peak shaving adjustment (“PSA”), as detailed in PJM’s tariff under Attachment DD-2, a zone’s load can be offset by committed load reduction programs. The Act notes that data center participation in such programs should relieve the data center from RBP costs and other related obligations.
PJM’s RBP proposal provides an opt-out that allows electric distribution companies (“EDC”) to decrement their associated MW quantity of load that participates in PSA programs. This opt-out appears aimed at complementing and working with the Act, and the Board appreciates PJM’s consideration. However, the Board thinks clarifications are needed to ensure the option is
11 P.L. 2026, c.32.
PDF page 7
7
workable within the RBP timeline. Namely, it is currently unclear whether the RBP opt-out submission requires full compliance with Attachment DD-2 in time for the centralized procurement or whether program details under Attachment DD-2 can be accomplished later. PJM should clarify that planned PSAs can qualify for the opt-out – MW for MW – if they are being pursued under requirements codified in state law even if program details are not yet finalized. The EDC, New Jersey, and related stakeholders would then have time to fully develop their PSA programs in advance of the 2028/2029 Delivery Year and would submit such final details when needed under Attachment DD-2, which would be September 2027. New Jersey looks forward to participating in this effort and hopes that participation will be workable within the RBP deadlines. These types of efforts can help unlock efficient ways to incorporate large loads into the grid, and the Board truly appreciates PJM’s efforts to accommodate these state efforts.
III. Conclusion
The Board thinks PJM’s proposal strikes a good balance between prioritizing both least- cost resources and those that can interconnect to the grid most quickly. Granted, if the Board had designed the RBP to its own specifications, it may have made some reasonable changes. Nonetheless, the Board ultimately supports PJM’s RBP proposal and the Board recommends approving it so PJM can run the central procurement in 2026.
PDF page 8
8
MICHAEL ZUCKERMAN
ACTING ATTORNEY GENERAL
OF NEW JERSEY
By: /s/ Steven Chaplar
Deputy Attorney General
Department of Law and Public Safety
Division of Law
P.O. Box 112
Trenton, NJ 08625
Steven.chaplar@law.njoag.gov
Attorneys for the New Jersey Board of
Public Utilities
Dated: August 21, 2026
Trenton, New Jersey
Respectfully,
PDF page 9
9
CERTIFICATE OF SERVICE
I hereby certify that, on this 21st day of August, 2026, I have caused the foregoing document to be served upon each party designated on the official service list compiled by the Secretary in this proceeding, by email.
By: /s/ Steven Chaplar
Steven Chaplar
Deputy Attorney General
New Jersey Office of the Attorney General
Department of Law & Public Safety
P.O. Box 112
Trenton, New Jersey 08625
Steven.chaplar@law.njoag.gov