Comments of New Jersey Board of Public Utilities in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal
Text extracted from the eLibrary original (SHA-256 a7a03785f2bf814d…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in ER26-3380
Topics in the text: Credit and exit · Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
The Board appreciates the haste with which this proposal was filed and underscores the importance of moving forward with this proposal amid significant regional resource adequacy concerns.Read this passage Filed comments: Reliability and curtailment
I. The RBP Addresses System Reliability Needs
printed heading · Topic match: Credit and exit
PJM and FERC must monitor, as much as possible, how this structure affects auction results.9 Finally, the Board has concerns about the collateral requirements for LSEs.10 The Board appreciates PJM’s efforts intended to protect consumers from the risk of stranded RBP costs.Read this passage Filed comments: Credit and exit
II. The RBP Opt-Out and Needed Clarification
printed heading
The RBP Opt-Out and Needed Clarification The Board appreciates PJM’s opt-out provisions that complement certain state laws.Read this passage
III. Conclusion
printed heading
Conclusion The Board thinks PJM’s proposal strikes a good balance between prioritizing both least- cost resources and those that can interconnect to the grid most quickly.Read this passage
CERTIFICATE OF SERVICE
printed heading
By: /s/ Steven Chaplar Steven Chaplar Deputy Attorney General New Jersey Office of the Attorney General Department of Law & Public Safety P.O.Read this passage