ER26-3380-000 · 2026-08-21 · The Retail Energy Supply Association
Motion to Intervene and Protest of the Retail Energy Supply Association re PJM Interconnection, LLC's proposed revisions to the Open Access Transmission Tariff
PDF page 1
4900-3540-9097.1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
Docket No. ER26-3380-000
MOTION TO INTERVENE AND PROTEST OF
THE RETAIL ENERGY SUPPLY ASSOCIATION
Pursuant to Rules 211 and 214 of the Federal Energy Regulatory Commission’s
(“Commission’s”) Rules of Practice and Procedure, 18 C.F.R. §§ 385.211 and 385.214, the Retail Energy Supply Association (“RESA”)1 hereby files this Motion to Intervene and Protest in the above-referenced proceeding, in which PJM Interconnection, LLC (“PJM”) seeks to modify the Reliability Assurance Agreement (“RAA”) of its Open Access Transmission Tariff (“Tariff”) to establish a Reliability Backstop Procurement (“RBP”) process to procure new capacity to address resource adequacy issues in PJM (“RBP Proposal”).
RESA files this Protest to express the need for market certainty, stability and clarity and the importance of the granular allocation of costs using principles of cost causation. As described below, significant changes to the PJM market design can cause harm if implemented to upset settled expectations of Market Participants and if a change in market design creates rate shock. In addition, RESA opposes PJM’s default methodology that would allocate costs
1 The comments expressed in this filing represent the position of the Retail Energy Supply Association (RESA) as an organization but may not represent the views of any particular member of the Association. Founded in 1990, RESA is a broad and diverse group of more than twenty retail energy suppliers dedicated to promoting efficient, sustainable and customer-oriented competitive retail energy markets. RESA members operate throughout the United States delivering value-added electricity and natural gas service at retail to residential, commercial and industrial energy customers. More information on RESA can be found at www.resausa.org.
PDF page 2
24900-3540-9097.1
associated with the capacity procurement in accordance with RAA Schedule 8. In support of this Motion to Intervene and Protest, RESA submits as follows:
I. MOTION TO INTERVENE
A. Correspondence and Communications
Correspondence and communications regarding this matter should be addressed to the following person(s), and the same should also be designated for service on the Commission’s official list for this proceeding:
Elizabeth W. Whittle
Charles Iannello
Nixon Peabody LLP
Interstate Gas Supply, LLC
799 Ninth Street, N.W.
6100 Emerald Parkway
Suite 500
Dublin, OH 43016
Washington, DC 20001
217-899-2537
202-585-8338
charlie.iannello@igs.com
ewhittle@nixonpeabody.com
B. RESA
RESA is a non-profit trade association of independent corporations that are involved in the competitive supply of electricity and natural gas to end-use consumers. RESA and its members are actively involved in retail electricity and natural gas markets throughout the United States in states that have implemented markets that allow entities other than the incumbent electric or natural gas utility to provide commodity electric and gas service. RESA members are Load Serving Entities (“LSEs”) active in the following RTO/ISOs: PJM, ISO New England, Inc. (“ISO-NE”), Midcontinent Independent System Operator, Inc. (“MISO”), New York Independent System Operator, Inc. (“NYISO”), and California Independent System Operator, Inc. (“CAISO”). RESA members possess market-based rate authority from the Commission.
PDF page 3
34900-3540-9097.1
C. Motion to Intervene
On July 31, 2026, PJM made a filing to modify the RAA provisions of its Tariff to impose an RBP on a one-time basis to acquire additional capacity due to shortages for 2027/2028 and 2028/2029 Reliability Pricing Model Auctions. RESA, with members who are active in PJM markets, have an interest in this proceeding that cannot be represented by any other party, moves to intervene.
II. GENERAL COMMENTS
RESA asks that the Commission take note of the need for market certainty and stability and the importance of granular cost allocations consistent with cost causation principles.2 In light of today’s ever increasing capacity prices, rate shock caused by mis-allocated costs will cause significant harm to those entities who are not causing the costs to increase.
RESA members purchase services in the RTO/ISO markets such as energy, capacity and ancillary services, but they offer more than just electricity service to their customers. Competitive retail suppliers may provide retail energy to end-use customers at contracted fixed or variable prices which are tied to wholesale electricity prices. Retail suppliers may offer demand response services – assisting customers in reducing peak demand and receiving benefits for reducing consumption at peak times. Retail suppliers may offer energy efficiency services to assist customers in reducing their electricity consumption. Retail suppliers may offer electricity with a certain component of renewable energy – or all renewable energy. There is no one model –
2 Cost causation requires “all approved rates reflect to some degree the costs actually caused by the customer who must pay them.” K N Energy v FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); Midwest ISO Transmission Owners v FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004).
PDF page 4
44900-3540-9097.1
competitive wholesale markets and the introduction of retail choice in states such as Ohio, Illinois, Pennsylvania, New Jersey, Delaware and Maryland, have allowed significant innovation, which has reduced consumption of energy, lowered prices, and provided valuable services to consumers. Competitive retail suppliers operate in an environment of risk. Retail suppliers are unlike traditional utilities in several important ways. For example, retail suppliers are not cost-based regulated by state public utility commissions (although they comply with a myriad of state requirements to be authorized to provide energy-related products and services to retail customers). Retail suppliers do not have a mechanism to defer costs, like traditional utilities, and thus bear the risk of wholesale market volatility and uncertainty. Retail suppliers do not have a specified service area. They contract with customers bilaterally. Generally, these contracts are long-term – of a duration of one to five years. As a result, when a contract expires, it may or may not be renewed. Thus, a customer today may not be a customer tomorrow. As a result, charges allocated to a utility service area or load zone must be properly allocated to the appropriate retail end use customer, even if the customer has changed suppliers or returned to default service (i.e. the customer is served by different LSEs).
To offer valuable and innovative services at competitive prices, retail suppliers participating in competitive wholesale markets require market certainty, transparency and stability. Market certainty, transparency and stability allow retail suppliers to offer products and services that they know they can deliver during the term of the applicable contract. The importance of having confidence in the competitive wholesale market cannot be overstated. As with products and services offered by retail suppliers, the contracts vary by company, by service, by customer type, by term and other conditions. If competitive retail suppliers are participating in default service programs, those programs often require winning suppliers to agree to a standard form
PDF page 5
54900-3540-9097.1
contract, which may or may not address unanticipated market changes, including changes to capacity cost allocations caused by RBP.
This RBP filing, and the related Interim Resource Adequacy Service (“IRAS”), filed by PJM in Docket No. ER26-3515, may fundamentally alter the risks and credit exposure of all customers in a utility service area depending on how RBP or related costs are allocated among them. It is critical for all Market Participants to have market certainty, stability and transparency in this critical time as PJM addresses the need for additional capacity.
III. PROTEST
A. The Commission should Deny PJM’s Default Allocation Proposal and Require
PJM to Use Sub-Accounts to Allocate Costs to Large Load
RESA supports PJM's RBP Proposal to the extent that it assigns RBP costs and collateral obligations to the LSE serving the Large Load Customers that cause those costs. PJM’s proposal to facilitate the allocation of costs to cost causers, however, is undermined to the extent that PJM’s proposed default methodology applies. Under PJM’s RBP, if an Electric Distributor does not report Reliability Backstop Obligations (“RBO”) for the Large Load Customers in its zone, PJM will instead allocate RBP costs to all load in that zone based on each LSE’s existing Peak Load Contribution assignments. The result is that the cost of capacity procured specifically to serve new, not-yet-interconnected Large Load through the RBP would be borne by residential, commercial, and traditional industrial customers who did not cause those costs and who receive no corresponding benefit.
This is not a remote contingency. As PJM acknowledges, neither the Commission nor PJM can dictate how RBP costs are allocated among the customers and LSEs behind each Electric Distributor. Ensuring allocation of RBP costs to cost causers will require each Relevant Electric
PDF page 6
64900-3540-9097.1
Retail Regulatory Authority (“RERRA”) and each Electric Distributor across the PJM footprint to implement regulations, tariff provisions, registry processes, and data exchanges necessary to identify Large Load Customers and assign RBO to their LSEs. Changes necessary to implement RBO may even require a change in state law or be dependent on PJM implementing the necessary changes to implement RBO. While the commitments made today will not be paid until the 2028/2029 Delivery Year, this is a significantly compressed schedule for the States and RERRAs to execute the necessary changes to implement RBO. If the necessary changes are not implemented in time, the default allocation attaches automatically, and capacity costs associated with Large Load Customers are spread across non-cost causing residential, commercial and traditional industrial customers. In other words, the most consequential cost allocation outcome in this proceeding would be determined not by a reasoned Commission judgment about cost causation, but by the pace of administrative implementation in individual states, RERRAs and Electric Distributor service territories.
PJM touts its cost allocation proposal as supporting the Statement of Principles Regarding PJM issued on January 16, 2026, by the National Energy Dominance Council and the 13 governors of the PJM states (“NEDC/PJM Governors’ Principles”)3
Thus, a cost allocation methodology that provides PJM states and/or RERRAs with the ability to determine the specific RBOs that should be assigned to LSEs, as well as to cost allocate to end-use customers in their respective states in accordance with their laws and policies, supports the NEDC/PJM Governors’ Principles, which include the principle that the cost of new capacity should be allocated to data centers who have caused the need for additional capacity in the PJM Region.43 Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm4 PJM RBP Proposal Filing Letter at 106-107.
PDF page 7
74900-3540-9097.1
However, if for any reason, the states, RERRAs, and Electric Distributors are unable to timely implement the necessary changes to implement RBO, the NEDC/PJM Governor’ Principles would be gravely violated by the socialization of RBP costs against all captive customers. There is a mechanism to prevent any unjustified cost allocations to LSEs – PJM should establish as a default methodology the obligation to create a sub-account to the LSE serving the Large Load where those costs can be appropriately assigned. For these reasons, RESA respectfully requests the Commission reject PJM’s default zonal cost allocation proposal and require PJM to establish an LSE sub-account associated with the Large Load in the PJM system where the costs can be directly assigned.
B. If the Commission Accepts PJM’s Default Allocation Proposal, PJM Should be Ordered to Take Additional Steps to Protect Residential, Commercial and
Traditional Industrial Customers from Cost Shifts
If the Commission accepts PJM’s Tariff proposal to, as a default, allocate RBP costs to LSEs based on the sum of their customers’ Peak Load Contributions, states, RERRAs and Electric Distributors will be under significant pressure to timely implement RBO. Accordingly, RESA respectfully requests that the Commission facilitate discussions among and between the states, RERRAs, Electric Distributors and interested Market Participants to assist in implementing the RBP Proposal and RBO.
RESA hereby emphasizes the urgency of state action and collaboration between the states and PJM in implementing RBO. If the RBP Proposal is accepted substantially as filed, every PJM state — and particularly those open to retail competition — will need to move immediately to identify Large Load Customers and to assign RBP costs and collateral obligations to those customers and their LSEs. RESA intends to participate in those proceedings, and the Commission should recognize in any order approving the RBP that the reasonableness of the cost allocation
PDF page 8
84900-3540-9097.1
outcome depends entirely on the implementation of the necessary changes by states, RERRAs and Electric Distributors to complete implementation of RBO before obligations attach to all LSEs serving load in a zone.
If PJM’s default allocation proposal is accepted as filed, and the Commission declines to implement RESA’s suggestion to create an LSE sub-account for Large Load as noted in Section IV.A above, then the Commission should require PJM to take additional steps to protect customers and LSEs before the default RPB cost allocation is triggered. First, PJM should be required to publish, well in advance of each cost allocation determination, which zones lack a qualifying framework for identifying Large Load Customers and assigning Reliability Backstop Obligations. States, RERRAs, LSEs, and customers need notice of that exposure before the RBP costs are allocated, not after. Second, if the Commission nonetheless permits a default allocation, the Tariff should make clear that it is a last resort of strictly limited duration and that it establishes no precedent for allocating costs caused by Large Load to customers other than Large Load.
C. The Commission Should Require Certain Commitments and Advance
Disclosure from PJM to Reduce Risk and Provide Greater Certainty to
LSEs.
PJM’s RBP injects significant uncertainty to competitive wholesale markets to the detriment of wholesale and retail customers. In the short amount of time to analyze this filing, RESA has identified a number of concerns that are identified below.
First, PJM should publish RBO determinations and resulting cost allocations expeditiously. Retail suppliers such as RESA members are currently submitting bids into default service supply solicitations to provide service to retail customers for long-term obligations of between one and five years. Price certainty and the RBO is critical information in responding to these procurements
PDF page 9
94900-3540-9097.1
for future Delivery Years. The central RBP auction is proposed to run from September 30 through October 21, 2026, while the facilitated bilateral matchmaking process is expected to continue for another six to nine months. Thus, RESA asks that the Commission require PJM to publish Reliability Backstop Obligation determinations and cost allocations sufficiently in advance of those solicitations for suppliers to reflect them in their offers.
Second, PJM offers no guarantee regarding timing of resettlement of RBP charges. RESA asks the Commission to confirm that RBP charges will not be subject to retroactive resettlement outside PJM's standard resettlement window. Retail suppliers cannot recover charges retroactively imposed after a contract has been priced and served, and the magnitude of the obligations at issue here makes that exposure materially different from ordinary settlement variance. Third, RESA further notes that excluding Large Load growth from future Reliability Pricing Model auction demand until that load is covered by new supply is directionally consistent with cost causation and may reduce capacity costs for all LSEs and the customers they serve. To realize that benefit, however, RESA asks that PJM be directed to re-release the 2029/2030 Base Residual Auction planning parameters promptly upon any change to the load forecast so suppliers can reflect a demand adjustment of this significance in their estimate of future capacity costs procured through the RPM.
Fourth, PJM’s proposal appears to lack specificity around how RBP costs will be assigned to LSE’s serving Large Load Customers as those customers switch from one LSE to another throughout the period the RBP will be in effect. For example, each state that permits retail access has rules and guidelines governing switching LSEs. Under the RBP, how will PJM be notified of the transfer of the Large Load and how will appropriate collateral be collected from the transferee LSE and returned to the transfer LSE? Will PJM deadlines interfere with the switch and leave the
PDF page 10
104900-3540-9097.1
transfer LSE with the Large Load? These issues must be addressed in the PJM Tariff. Finally, while PJM’s proposal provides detailed steps to address LSE default on RBP obligations, the proposal lacks details related to Large Load Customer load not materializing or decommissioning. RESA supports the portion of the proposal intended to protect traditional customers if a Large Load Customer ceases operations after its load clears the RBP and requests that the Commission require PJM to address that scenario more completely. For example, PJM’s proposal does not resolve whether the remaining fifteen-year cost obligation would be socialized to other customers in the zone, satisfied by drawing on an LSE's collateral, or reallocated. That ambiguity exposes non-cost causing customers and their LSEs to an open-ended liability and, as a practical matter, is itself an impediment to the Large Load interconnection the RBP is intended to facilitate.
WHEREFORE, RESA respectfully requests that RESA’s Motion to Intervene is granted and its Protest considered by the Commission in this proceeding.
Respectfully submitted,
Elizabeth W. Whittle
Elizabeth W. Whittle
Counsel for
The Retail Energy Supply Association
Of Counsel:
Nixon Peabody, LLP
799 9th Street, N.W.
Suite 500
Washington, DC 20001
202-585-8338
ewhittle@nixonpeabody.com
Dated: August 21, 2026