Partial Protest and Comments of Dominion Energy Services, Inc. re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal
Text extracted from the eLibrary original (SHA-256 4d2e1cc7ed2f4151…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. ) ) ) ER26-3380-000 PARTIAL PROTEST AND COMMENTS OF DOMINION ENERGY SERVICES, INC.Read this passage Filed comments: Reliability and curtailment
I. Introduction
printed heading · Topic match: Reliability and curtailment
Dominion Energy respectfully requests the Commission approve the PJM Filing subject to PJM submitting a compliance filing to adjust the allocation methodology.Read this passage Filed comments: Reliability and curtailment
II. Comments
printed heading · Topic match: Reliability and curtailment
The PJM region must address near-term deficiencies to begin focusing on the long-term solution, which is why Dominion Energy supports the RBP.Read this passage Filed comments: Reliability and curtailment
III. Partial Protest
printed heading
III.Read this passage
A. PJM’s proposed methodology for allocating the Final RBP Target to individual
printed heading · Topic match: Cost allocation
Recognizing that much of the shortfall experienced in the last two capacity auctions is attributable to Large Load adjustments added to the load forecasts, PJM proposes pro-rata allocation to ED zone/areas based on their share of forecasted load growth between the 2026/2027 and 2028/2029 Delivery…Read this passage Filed comments: Cost allocation
B. Subtracting Qualifying RBP Offset UCAP MW from Initial RBP Target
printed heading · Topic match: Cost allocation
Dominion Energy provides the following edits to PJM’s tariff amendments in sections 18.2 and 18.3 to effectuate the necessary change: 18.2 Qualifying RBP Offset UCAP MW (e) The total quantity of Qualifying RBP Offset UCAP MW verified by the Office of the Interconnection and used to decrement the…Read this passage Filed comments: Cost allocation
C. The Commission has the authority to direct modification of the Final RPB
printed heading · Topic match: Cost allocation
PJM has consented to modification of its proposal where such modification is consistent with PJM’s overarching objectives.14 This change will not affect those objectives and will in fact better align with cost allocation principles and the design of the RBP.Read this passage Filed comments: Cost allocation
IV. CONCLUSION
printed heading
CONCLUSION Dominion Energy respectively requests that the Commission grant PJM’s proposed Tariff revisions subject to PJM submitting a compliance filing for the reasons discussed above.Read this passage
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that in accordance with Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026), I have served a copy of the foregoing to all parties on the official service list in these proceedings. /s/ Wesley Walker Wesley Walker August…Read this passage