ER26-3380-000 · 2026-08-24 · E-Cubed Policy Associates, LLC

Comment, Protest, and Motion for Leave to File One Day Out of Time of E-Cubed Policy Associates, LLC in response to PJM Interconnection, L.L.C.’s 07/31/2026…

Word notes use stable document IDs, such as [fn:8], which can differ from printed footnote numbers.

Document text

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION



PJM Interconnection L.L.C.		)		Docket No. ER26-3380-000

COMMENTS AND PROTEST OF E-CUBED POLICY ASSOCIATES, L.L.C. AND MOTION FOR LEAVE TO FILE ONE DAY OUT OF TIME

Pursuant to Rule 212[fn:1] of the Federal Energy Regulatory Commission’s (“FERC” or  “Commission”) Rules of Practice and Procedure, E-Cubed Policy Associates, L.L.C. (“E-Cubed”)[fn:2] respectfully submits these comments and protest one day out of time[fn:3] in response to PJM Interconnection, L.L.C.’s (“PJM”) filing submitted to the Commission on July 31, 2026, pursuant to Section 205 of the Federal Power Act (“FPA”),[fn:4] regarding proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to implement a Reliability Backstop Procurement (“RBP”) as a means to cure the current shortfall of 6,831.3 MW of Unforced Capacity (“UCAP”) following the 2028/2029 Base Residual Auction (“BRA”).[fn:5]  On August 14, 2026 PJM filed a supplemental Affidavit of Danielle Croop to correct errors and provide further explanation of how the RBP would operate.[fn:6]
As discussed herein, E-Cubed provides comments and protests PJM’s RBP filing on two distinct, but related dimensions. First, E-Cubed provides publicly available data and evidence that indicates the $555/MW-Day volume weighted average constraint on purchases in the RBP is not commensurate with the actual cost of bringing capacity into PJM via the RBP for any resource type. Thus, PJM will have trouble attracting capacity to offset any portion of the 6,831.3 MW UCAP shortfall that exists in the wake of the 2028/2029 BRA. From both a reliability and economic perspective such a PJM’s proposed $555/MW-day UCAP volume weighted average price constraint is not just and reasonable, is unduly discriminatory and/or preferential because the constraint is not compensatory even under PJM’s assumptions. 
Second, PJM’s proposed volume weighted average constraint is not a budget, but a de facto price cap rather than an offer cap. Instead, E-Cubed proposes a true budget concept that is a function of both the $555/MW-day price[fn:7] and the 6,831.3 MW UCAP shortfall[fn:8] that will procure capacity so long as the expenditures do not exceed the budget while allowing offers that are commensurate with the actual costs of bringing new capacity into commercial operation in PJM. The proposed budget concept will help reduce the shortfall and also provide price discovery that will inform future bilateral contracting opportunities between Large Loads and new Capacity Resources that will further aid in curing the shortfall over time.
RATIONAL OFFERS INTO THE RBP
PJM has proposed to provide long term contracts at up to a 15-year term beginning with delivery for the 2028/2029 Delivery Year (“DY”) running through the 2042/2043 DY.[fn:9] PJM also allows potential sellers to offer into the RBP with in service data up through, but no later than the start of the 2032/2033 DY implying that the shortest contract term is 11 years.[fn:10]
It should not be a surprise that when offered the opportunity for a long term contract of an 11-15 year duration, that investors would want to cover their capital recovery and desired returns over the duration of the contract, rather than taking the risk that in the out years beyond the contract term, which are highly uncertain,[fn:11] a contract framework provides some certainty, albeit incomplete, so long as the new generation resource performs as expected.[fn:12] 
Why would offers in the RBP attempt to cover all investment costs within the 11–15-year contract term as offered by the RBP? Investors in capital are looking for as much certainty as possible, though it is impossible to guarantee any kind of certainty over the life of a long-lived asset such as power generation. Uncertainty comes in the form of overall economic conditions, future net energy revenues, state and federal government policies, and changes in PJM market rules as being major areas of uncertainty.
Regarding net energy revenues, this depends on demand growth, future fuel costs, and the overall configuration of the generation fleet in PJM. Table 4 and Table 10 in Section II below show the high variability in net energy revenues over the most recent 12 years of market operation for combined cycle and simple cycle resources. 
Changes in state and federal policy have impacts. Currently the market has swung from one set of federal policies driving renewable energy development, to one that is openly discouraging renewable development.  Recently, states have become more hesitant to pursue data centers as a strategy for economic and tax base growth, and it has been the prospective data center load growth that has driven the need for RBP.[fn:13]
Overall economic conditions are showing that the capital spending on data centers is one of the biggest items driving overall GDP growth in the US.[fn:14] Yet there are concerns in the financial markets that this prospective data center buildout is a bubble that could burst and completely change the dynamic for the entire economy[fn:15] as well as the trajectory of the need for new capacity in PJM should data center build out not materialize.
Finally, changes in PJM rules and uncertainty regarding PJM’s markets are key drivers. First, PJM has not run a BRA three years forward (on time) since 2018 due to various PJM decisions, regulatory decisions, and market rule changes. Only will PJM get back on time, it seems, for the May 2027 BRA for the 2030/2031 DY…a nine-year hiatus for on time BRAs. PJM also moved to an interconnection cluster study process, ultimately a wise move, but while the backlog of projects under the old serial queue process was cleared, no new projects were allowed to enter the interconnection queue between mid-2021 and April 2026 but for PJM’s RRI mechanism.[fn:16] 
Further, PJM made an enormous change in resource accreditation by moving to ELCC for all resources starting with the 2025/2026 BRA and DY. For those investors with projects in the old serial queue process, this completely changed their economic decisions on whether to move forward. Further, with ELCC, accreditation changes year-over-year for reasons that remain unclear to investors. How are investment decisions to be made when the underlying capacity product that one can sell is highly variable and largely out of the control of the generation owner give the use of history that cannot be changed in modeling ELCC?
Incentives for the structure of offers under uncertainty

PJM has proposed a “pay-as-bid” framework for the RBP. Leaving aside the known incentive problems with pay-as-bid auctions as well as inefficiencies that PJM itself has recognized,[fn:17] Investors will want to include a monetary value for uncertainty into their offers.
The tables below showing that even if there is “certainty” on investment costs and EAS for Net CONE, any prospective offers will likely be higher to account for uncertainty and risk. PJM has stated clearly that those who offer into RBP face the risk of interconnection costs[fn:18] and ELCC variation.[fn:19] For most potential offers, interconnection costs are not yet well known. Transition Cycle 2 (“TC2”) is not yet complete,[fn:20] and Cycle 1 has only started so there is no clear line of sight on ultimate interconnection costs for many projects that could offer into the RBP.
Furthermore, ELCC values have varied significantly for many resource types, especially for gas resources that are likely to be the highest ELCC value resources that could reach commercial operation and offer into the RBP.[fn:21] Given the analysis in Section III below, it is not feasible for any resource type available to meet the $555/MW-day UCAP volume weighted average price cap as an offer price for any of the contract duration terms on offer in the RBP. This becomes even more untenable with ELCC risk and variance.
Accounting for updated installed costs and uncertainty, the only reasonable conclusion to draw from PJM’s proposed RBP is that it will fail to attract the capacity it seeks under its $555/MW-day UCAP cap. But there is a possible way forward that will help provide some price discovery and will admit offers and commit resources with offers well in excess of $555/MW-day and still meet the intent and spirit of the willingness to pay as discussed in Section III.


ESTIMATING THE GROSS AND NET COSTS OF NEW ENTRY AT CURRENT MARKET PRICES AND EXPECTATIONS OF NET ENERGY REVENUES
We start from the basics of the Capital Recovery Factor (CRF)[fn:22] which indicates how much cashflow must be returned each year for an investment to return capital plus returns on investment over the term. We use PJM’s choice of 9.5% WACC, which goes into the CONE calculations for the Reliability Pricing Model (RPM), and as PJM has proposed for is discount rate in the RBP formulation the target return. Table 1 below shows the CRF for terms of 20, 15, 14, 13, 12, and 11 years. These terms correspond to the asset life assumption from RPM, and the potential terms of the contracts that could be procured under the RBP.
Table 1: Capital Recovery Factor for Different Terms at 9.5% WACC
Contract Years
20
15
14
13
12
11
In service Delivery Year
RPM CONE Calculation
2028/2029
2029/2030
2030/2031
2031/2032
20232/2033
CRF @ 9.5%
0.113476695
0.1277437
0.13206809
0.13715206
0.14318771
0.15043693

Combined Cycle Net CONE UCAP Cost Estimates Show it is Not Financially Feasible to Offer at or Below $555/MW-day

What we know from recent announcements, estimates, and analysis is that the cost of building both combined cycle gas and simple cycle gas facilities has increased precipitously. Table 2 below provides a range of combined cycle cost estimates including the Brattle CONE Study.[fn:23]


Table 2: Recent Installed Cost Estimates of Combined Cycle Gas Facilities
Source or Project Name
Installed Cost $/kW
Date of Report
JP Morgan[fn:24]
$2200-$2800
March 2026
Grid Lab[fn:25]
$2125-$2255
September 2025
Oglethorpe Power[fn:26]
$2315
May 2026
JEA (FL)[fn:27]
$2370
September 2025
Entergy (Jefferson)[fn:28]
$2122
November 2025
Brattle CONE Study[fn:29]
$1795-$1929
April 2025

The above estimates in Table 2 are for projects estimated to enter service in 2028 or later. These estimates stand in contrast to the Brattle/Sargent Lundy 2025 estimates of new combined cycle installed costs with an in-service date to start with the 2028/2029 DY of with installed cost differences ranging from just over $300/kW to more than $500/kW.[fn:30]  Given the public announcements, the Brattle figures reported in Table 2 seem to be substantially underestimated and are not addressed in the subsequent analysis.
There is one other announcement that has been excluded from Table 2, the 9.2 GW SoftBank announced facility in southern Ohio, whose public costs estimates imply an installed cost of $3600/kW.[fn:31] Applying the estimates in Table 2 to the CRF in Table shows the estimated Gross Cone in $/MW-day ICAP.
Table 3: Estimated Combined Cycle Gross CONE Based on CRF, Term, and Installed Cost Estimates

Contract Years
20
15
14
13
12
11
Installed Cost







$2,122 

$659.72 
$742.66 
$767.80 
$797.36 
$832.45 
$874.59 
$2,255 

$701.07 
$789.21 
$815.93 
$847.34 
$884.63 
$929.41 
$2,315 

$719.72 
$810.21 
$837.64 
$869.88 
$908.16 
$954.14 
$2,370 

$736.82 
$829.46 
$857.54 
$890.55 
$929.74 
$976.81 
$2,800 

$870.51 
$979.95 
$1,013.13 
$1,052.13 
$1,098.43 
$1,154.04 

The IMM has provided in its 2025 State of the Market Report (“SoM”)[fn:32] new entrant combined cycle net energy and ancillary service revenues by zone from 2014 through 2025. Table 4 below summarizes the average over those 12 years to show the variation in net energy revenues that a new entrant combined cycle resource might expect over time per unit of ICAP in $/MW-year and $/MW-day. This table shows that revenues are highly variable over time as can be seen by the standard deviations shown in Table 4.


Table 4: Average and Standard Deviation of New Entrant Combined Cycle Net Energy Revenues 2014-2025 Derived from IMM 2025 State of the Market Report Table 7-10[fn:33]
Zone
Avg 2014-2025
$/MW-day Avg
Std Dev 2014-2025
Std Dev $/MW-day
ACEC
$60,282
$165
$23,963
$66
AEP
$103,370
$283
$38,982
$107
APS
$114,911
$315
$37,622
$103
ATSI
$101,808
$279
$38,914
$107
BGE
$121,709
$333
$37,120
$102
COMED
$64,195
$176
$27,643
$76
DAY
$107,301
$294
$44,008
$121
DOM
$113,300
$310
$54,596
$150
DPL
$58,252
$160
$29,533
$81
DUKE
$101,752
$279
$42,673
$117
DUQ
$98,181
$269
$37,618
$103
EKPC
$91,451
$251
$35,372
$97
JCPLC
$60,760
$166
$24,229
$66
MEC
$97,336
$267
$35,199
$96
PE
$127,644
$350
$46,195
$127
PECO
$79,864
$219
$25,123
$69
PEPCO
$89,926
$246
$30,604
$84
PPL
$114,342
$313
$55,824
$153
PSEG
$72,620
$199
$33,881
$93
REC
$69,513
$190
$24,432
$67
PJM
$90,731
$249
$29,554
$81


Location matters regarding the net energy revenues that have been and will be available going forward. Using the most attractive location from a net revenue perspective (PE zone with an average of $350/MW-day) the Net CONE ICAP in expectation is shown below. The purpose of using the most generous and attractive value in Table 5 is to show that even under the most optimistic of locations and circumstances, it is not financially feasible for a new entry combined cycle facility to offer in at or below the $555/MW-day UCAP de facto price cap.
Table 5: Net CONE ICAP Estimate from Installed Costs Alone for Combined Cycle based on Zonal Maximum of 2014-2025 Net Energy Revenues by Installed Cost Estimate

Contract Years
20
15
14
13
12
11
Installed Cost







$2,122 

$309.72 
$392.66 
$417.80 
$447.36 
$482.45 
$524.59 
$2,255 

$351.07 
$439.21 
$465.93 
$497.34 
$534.63 
$579.41 
$2,315 

$369.72 
$460.21 
$487.64 
$519.88 
$558.16 
$604.14 
$2,370 

$386.82 
$479.46 
$507.54 
$540.55 
$579.74 
$626.81 
$2,800 

$520.51 
$629.95 
$663.13 
$702.13 
$748.43 
$804.04 

But this is the Net CONE in ICAP terms. The ELCC value for combined cycle for the 2029/2030 BRA is 75%.[fn:34] Table 6 shows the Net CONE in UCAP terms. And since PJM buys UCAP, not ICAP, this is the relevant Net CONE value for thinking about offers into the RBP.
Table 6: Net CONE UCAP Estimate from Installed Costs Alone for Combined Cycles based on 75% ELCC Value and Zonal Maximum Average Net Energy Revenue

Contract Years
20
15
14
13
12
11
Installed Cost







$2,122 

$412.96 
$523.55 
$557.07 
$596.48 
$643.27 
$699.46 
$2,255 

$468.09 
$585.61 
$621.24 
$663.12 
$712.83 
$772.55 
$2,315 

$492.96 
$613.61 
$650.18 
$693.18 
$744.22 
$805.52 
$2,370 

$515.76 
$639.28 
$676.72 
$720.73 
$772.99 
$835.75 
$2,800 

$694.01 
$839.94 
$884.17 
$936.17 
$997.90 
$1,072.05 

Given what is shown in Table 6, the only way a combined cycle plant could make the $555/MW-day is if it came into service for 2028/2029 and was located in the most advantageous zone in PJM, PE (Penelec), and had the lowest of the current cost estimates for a combined cycle facility.
The cost estimates presented in Table 6 above are installed costs and do include items such as Fixed O&M and ongoing pipeline transportation costs. We know that ongoing Fixed O&M costs, which include pipeline transportation as estimated by Brattle for combined cycles range from $109-$164/MW-day ICAP ($146-$219/MW-day UCAP).[fn:35] If one adds the Fixed O&M value into results in Table 6 there is no possible way for a new combined cycle to meet the $555/MW-day cap to enter through the RBP as shown in Table 7. 
Table 7:Net CONE UCAP Estimate from Installed Costs Alone for Combined Cycles based on 75% ELCC Value and Zonal Maximum Average Net Energy Revenue and Lowest Fixed O&M Estimate from Brattle

Contract Years
20
15
14
13
12
11
Installed Cost







$2,122 

$558.96 
$669.55 
$703.07 
$742.48 
$789.27 
$845.46 
$2,255 

$614.09 
$731.61 
$767.24 
$809.12 
$858.83 
$918.55 
$2,315 

$638.96 
$759.61 
$796.18 
$839.18 
$890.22 
$951.52 
$2,370 

$661.76 
$785.28 
$822.72 
$866.73 
$918.99 
$981.75 
$2,800 

$840.01 
$985.94 
$1,030.17 
$1,082.17 
$1,143.90 
$1,218.05 

Further, we do not know if the quoted public installed costs include pipeline interconnection and electric interconnection, estimates of which are included in the Brattle 2025 CONE Study[fn:36] and if they do not the costs of entry are even higher yet.
Simple Cycle Net CONE UCAP Cost Estimates Show it is Not Financially Feasible to Offer at or Below $555/MW-day

This section walks through the same logic as we did for the combined cycle cost estimates. Data on CT installed costs are not as readily available as for combined cycle costs. Table 8 below presents the Brattle estimates and GridLab range of its survey of simple cycle gas CT’s going into service in or after 2028. 

Table 8: Recent Installed Cost Estimates of Simple Cycle Gas CT Facilities
Source or Project Name
Installed Cost $/kW
Date of Report
Brattle CONE Study[fn:37]
$1647-$1715
April 2025
Grid Lab[fn:38]
$1557-$1995
September 2025

Unlike the estimates for combined cycles, the GridLab survey and Brattle numbers are in greater alignment. Table 9 presents the estimated simple cycle Gross CONE estimates based on the CRF in Table 1 and the information in Table 8.

Table 9: Estimated Gross CONE ICAP of Simple Cycle CT Based on CRF, Term, and Installed Cost Estimates

Contract Years
20
15
14
13
12
11
Installed Cost







$1,557 

$484.06 
$544.92 
$563.37 
$585.06 
$610.80 
$641.73 
$1,647 

$512.04 
$576.42 
$595.93 
$618.88 
$646.11 
$678.82 
$1,715 

$533.19 
$600.22 
$620.54 
$644.43 
$672.79 
$706.85 
$1,995 

$620.24 
$698.22 
$721.85 
$749.64 
$782.63 
$822.25 
   
To obtain the Net CONE ICAP estimates we took average new entrant CT net EAS revenues from the IMM 2025 SoM that covers the 12 years from 2014 through 2025. The net EAS revenues are generally not as high as for combined cycles, but like those revenues there is variability year-over-year.  

Table 10: Average and Standard Deviation of New Entrant Simple Cycle CT Net Energy Revenues 2014-2025 Derived from IMM 2025 State of the Market Report Table 7-8[fn:39]
Zone
Avg 2014-2025
$/MW-day Avg
Std Dev 2014-2025
Std Dev $/MW-day
ACEC
$37,303
$102.20
$21,117
$57.86
AEP
$68,188
$186.82
$24,790
$67.92
APS
$73,150
$200.41
$35,860
$98.25
ATSI
$67,588
$185.17
$26,147
$71.63
BGE
$80,357
$220.16
$36,162
$99.07
COMED
$39,601
$108.50
$17,309
$47.42
DAY
$72,026
$197.33
$29,509
$80.85
DOM
$78,092
$213.95
$45,132
$123.65
DPL
$41,972
$114.99
$23,897
$65.47
DUKE
$67,865
$185.93
$27,915
$76.48
DUQ
$68,038
$186.40
$26,760
$73.31
EKPC
$56,828
$155.69
$20,622
$56.50
JCPLC
$36,614
$100.31
$20,917
$57.31
MEC
$69,545
$190.53
$29,748
$81.50
PE
$97,672
$267.59
$38,184
$104.61
PECO
$53,813
$147.43
$23,622
$64.72
PEPCO
$51,141
$140.11
$24,362
$66.75
PPL
$87,802
$240.55
$51,439
$140.93
PSEG
$48,483
$132.83
$30,963
$84.83
REC
$41,619
$114.02
$18,659
$51.12
PJM
$59,791
$163.81
$22,522
$61.70

Taking the most attractive (generous) of the net EAS revenues to paint the best-case scenario as we did for combined cycle resources which happen to be from the PE zone (Penelec), we derive the Net CONE ICAP for a simple cycle CT.

Table 11: Net CONE ICAP for Simple Cycle CT based on Zonal Maximum of 2014-2025 Net Energy Revenues by Installed Cost Estimate

Contract Years
20
15
14
13
12
11
Installed Cost







$1,557 

$217.06 
$277.92 
$296.37 
$318.06 
$343.80 
$374.73 
$1,647 

$245.04 
$309.42 
$328.93 
$351.88 
$379.11 
$411.82 
$1,715 

$266.19 
$333.22 
$353.54 
$377.43 
$405.79 
$439.85 
$1,995 

$353.24 
$431.22 
$454.85 
$482.64 
$515.63 
$555.25 

For the 2029/2030 DY, CTs have an ELCC value of 59%.[fn:40] So adjusting the Net CONE Values in Table 11 for the ELCC value provides the Net CONE UCAP for simple cycle CTs in Table 12. 
Table 12: Net CONE UCAP for Simple Cycle CT based on Zonal Maximum of 2014-2025 Net Energy Revenues by Installed Cost Estimate

Contract Years
20
15
14
13
12
11
Installed Cost







$1,557 

$367.90 
$471.06 
$502.32 
$539.08 
$582.72 
$635.13 
$1,647 

$415.33 
$524.44 
$557.52 
$596.40 
$642.56 
$698.00 
$1,715 

$451.16 
$564.78 
$599.22 
$639.71 
$687.77 
$745.50 
$1,995 

$598.70 
$730.87 
$770.93 
$818.03 
$873.95 
$941.10 

Table 12 seems to show, before considering Fixed O&M costs, that CTs at the lower end of the cost range and if those units enter in 2028/2029 or 2029/2030. However, the Fixed O&M for CTs from Brattle range from $57/MW-day ICAP to $90/MW-day ICAP.[fn:41] However, adjusting for the ELCC value these fixed O&M values are $97/MW-day to $153/MW-day UCAP. Adding the Fixed O&M to the values to Table 12 shows that even CTs cannot feasibly make a compensatory offer into the RBP as the lowest cost estimate exceeds $555/MW-day as shown in Table 13.


Table 13: Net CONE UCAP Estimate from Installed Costs Alone for Simple Cycle CT based on 59% ELCC Value and Zonal Maximum Average Net Energy Revenue and Lowest Fixed O&M Estimate from Brattle

Contract Years
20
15
14
13
12
11
Installed Cost







$1,557 

$464.90 
$568.06 
$599.32 
$636.08 
$679.72 
$732.13 
$1,647 

$512.33 
$621.44 
$654.52 
$693.40 
$739.56 
$795.00 
$1,715 

$548.16 
$661.78 
$696.22 
$736.71 
$784.77 
$842.50 
$1,995 

$695.70 
$827.87 
$867.93 
$915.03 
$970.95 
$1,038.10 

Other Technology Net CONE UCAP Cost Estimates Show it is Not Financially Feasible to Offer at or Below $555/MW-day

Battery Energy Storage Systems (“BESS”)
The case for batteries being unable to enter at under $555/MW-day is shown in the Brattle CONE study in the last periodic review. Even including ITC, the Gross CONE ranges between $650-$726/MW-day over a 20-year horizon,[fn:42] so the Gross CONE costs for contract terms of 11-15 years would be even higher on an ICAP basis.
The IMM has not provided any new entrant battery net revenues in the SoM thus the best estimate available is Brattle Net CONE ICAP value of $409/MW-day.[fn:43] But when applying the 2029/2030 ELCC value to 4-hour BESS of 57%,[fn:44] this comes to $717/MW-day UCAP over 20 years. There is simply no room for BESS to enter via the RBP as the costs will be even higher under terms of 15 years or less.
Solar
In the most recent PJM update for MOPR tracking solar has a Gross CONE ICAP of $659/MW-day for 2030 delivery.[fn:45] The maximum average EAS is $250/MW-day ICAP for new entry solar over the 2014-2025 period.[fn:46] This implies an estimated $409/MW-day ICAP Net CONE (absent any REC credits). The ELCC value of solar is only 7%[fn:47] so resulting in a $5824/MW-day UCAP for solar absent REC credits.
If we take REC credits into account as estimated by the IMM,[fn:48] only solar in New Jersey would be able to enter the RBP. But even so, the UCAP contribution is minimal at 7%. The current Cycle 1 queue only shows 4 MW of solar based on maximum facility output (“MFO”) in NJ[fn:49] while the transition queues show on 253 MW of energy in other locations. 7% of that value is de minimis and solar elsewhere in PJM is simply not able to make the $555/MW-day.
Onshore Wind
In the most recent PJM update for MOPR Onshore wind $786/MW-day ICAP for 2030 delivery.[fn:50] The maximum average EAS is $235/MW-day ICAP for new entry onshore wind over the 2014-2025 period.[fn:51] This implies an estimated $551/MW-day ICAP Net CONE (absent any REC credits). The ELCC value of solar is only 37%[fn:52] so resulting in a $1,489/MW-day UCAP for onshore wind absent REC credits.
If we take REC credits into account as estimated by the IMM,[fn:53] the maximum average is $122/MW-day ICAP. This would reduce the Net CONE ICAP to $429/MW-day but with the ELCC value of 37%, this still comes to $1159/MW-day UCAP over 20 years making new onshore wind more expensive than the $555/MW-day UCAP de facto price cap.


A TRUE BUDGET WOULD ALLOW SOME RESOURCE TO BE COMMITTEED IN RBP TO ALLEVIATE THE SHORTFALL
PJM’s filing states that their so-called “budget” is a MW-weighted average of $555/MW-day in net present value terms which would allow for some offers below $555/MW-day to offset some offers that would come in above $555/MW-day.[fn:54] Notwithstanding the source of the choice of $555/MW-day, it is clear from the discussion above that it is unlikely that many offers, if any, could possibly come in below $555/MW-day, and thus, it is unlikely that any capacity will be committed via RBP to offset the 6,831.3 MW UCAP shortfall being targeted. PJM itself admits this is a de facto price cap.[fn:55]
The so-called flexibility PJM avers assumes, and as shown in Section II above incorrectly so, that some offers will come in below the $555/MW-day UCAP value while others will come in above that providing offer flexibility. While it may be theoretically possible this may occur, the likelihood of that happening is slim given the implied offers required under the most optimistic of circumstances as discussed above.
This result alone makes PJM’s proposal unjust, unreasonable and unduly discriminatory and preferential in that not only in the proposed de facto price cap not reflective of actual costs, but it is also not solving the capacity shortfall in any meaningful way. 
However, if one takes the idea of a budget seriously, a budget is simply an amount of money that can be spent, as opposed to a target weighted average price as PJM has proposed. With that in mind it is possible to construct a budget from the willingness to pay at $555/MW-day and the target quantity procured of 6,831.3 MW UCAP.  A simple way to do this would be to multiply the $555/MW-day by 6831.3 MW by 15 years by 365 days per year which would indicate a budget of $20.75 billion to procure capacity.[fn:56] 
But this would violate the spirit and intent of what PJM has proposed regarding the levelized costs discounted at 9.5% WACC. In the alternative, a net present value budget can be determined easily by assuming the purchase of the 6,831.3 MW UCAP shortfall at $555/MW-day for each of the 15 years of the maximum contract term available in RBP. This results in a net present value budget of $11.86 billion.[fn:57] This is simply another way of expressing willingness to pay, but in the form of how much money can be spent on capacity.
This proposed “true” budget approach caps the amount that can be spent on capacity purchased through the RBP, while allowing for the purchase of some capacity to reduce the shortfall and allowing offers above the $555/MW-day threshold to be committed, and a levelized weighted average price above $555/MW-day UCAP so long as the total expenditures are at or under the budget amount.
The point of a true budget-based approach as proposed here is to allow offers to reflect the true cost of bringing new capacity into service while accounting for uncertainties and still honoring the spirit of the willingness to pay, albeit in the form of total expenditures rather than as a price per unit as PJM is doing. It also provides a means to reduce the MW UCAP shortfall, albeit not likely all the way. 
For example, using the simple levelized cost approach PJM has proposed, if the weighted average offers were $1000/MW-day UCAP, PJM would be able to procure 3,780 MW UCAP under the proposed budget approach, rather than procuring nothing as PJM’s current proposal would do. If the weighted average offers came in at $850/MW-day UCAP, PJM would be able to procure up to 4,450 MW UCAP. While both figures do not fully cure the 6,831.3 MW shortfall, reliability would be enhanced compared to procuring nothing in the RBP.
Such an approach would provide a truer sense of price discovery as a known budget and known awards will allow market participants to back out the implied weighted average cost without being privy to the actual offers, and this would inform future bilateral contracting discussions. as market participants can estimate the weighted average offer from the outcome of the RBP.  In contrast the $555 de facto price cap keeps the true nature of the costs opaque to bring capacity into operation and thus hindering future bilateral contracting.
CONCLUSION
E-Cubed requests that the Commission accept these comments and protest filed one day out of time for the reasons cited above. Further, E-Cubed asks the Commission to reject PJM’s RBP proposal for the reasons cited herein and implement the proposed budget approach to improve resource adequacy in PJM even incrementally.  



Respectfully submitted,

 
/s/ Paul M. Sotkiewicz, Ph.D.
______________________
President, E-Cubed Policy Associates, LLC
5502 NW 81st Avenue
Gainesville, FL 32653
352-234-9500 (office) (note the new office number)
610-955-2411 (mobile)
paul.sotkiewicz@e-cubedpolicy.com
drpaulg8r@gmail.com


Dated: August 22, 2026 




CERTIFICATE OF SERVICE 

I hereby certify that I have this day served the foregoing document on each person designated on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding.  
 
Dated at Gainesville, FL this 22nd day of August, 2026.
 
 
  /s/ Paul M. Sotkiewicz, Ph.D.
___________________________ 
 					








Footnotes
[fn:1] 18 C.F.R. §385.212 (2025).
[fn:2] E-Cubed is a consulting firm founded and led by Paul M. Sotkiewicz, Ph.D. E-Cubed represents multiple parties in the PJM stakeholder process and assists them in economic and regulatory matters in the power industry in PJM and other RTO markets.
[fn:3] Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.212 (2025), E-Cubed respectfully requests that the Commission accept these comments and protest, which are being filed one day out of time.  E-Cubed Policy timely moved to intervene in this proceeding, but due to an administrative oversight, E-Cubed Policy was not able to submit these comments and protest by the deadline established by the Commission.  These comments and protest are being filed only one day late, and acceptance of these comments and protest will therefore not cause any prejudice to or any additional burden upon other parties.  See, e.g., Southwest Power Pool, Inc., 193 FERC ¶ 61,244 at P 68 (2025) (accepting out-of-time comments); PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at P 13 (2025) (accepting out-of-time comments and out-of-time protest); PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 at P 83 (2024) (accepting out-of-time comments).
[fn:4] 16 U.S.C. § 824d (2000).
[fn:5] PJM Interconnection, L.L.C., Reliability Backstop Procurement To Address Resource Adequacy Concerns Stemming from Large Loads, FERC Docket No. ER26-3380-000, July 31, 2026. (“Filing”)
[fn:6] Supplemental Filing in PJM Interconnection, L.L.C., Docket No. ER26-3380-000, August 14, 2026, Attachment A, Supplemental Affidavit of Danielle Croop. (“Croop Supplemental Affidavit”)
[fn:7] Filing Transmittal Letter at 61-62. See also Filing Proposed Tariff, Attachment DD, section 18.5(f)(ii).
[fn:8] Id. at 68.
[fn:9] Id. at 8, 48.
[fn:10] Id. at 8, 48, 125.
[fn:11] There is no known crystal ball for anybody to foretell the future, but the current way in which PJM constructs the Gross CONE and Net CONE values seems to imply perfect foresight, especially with regard to future net energy and ancillary service (“EAS”) revenues.
[fn:12] Of course, investors are taking risks that the generation asset perform as is expected.
[fn:13] See Paul Cobler, “Data center approvals in Texas halted until audits completed, Gov. Greg Abbott says”, Texas Tribune, August 3, 2026. https://www.texastribune.org/2026/08/03/texas-data-center-project-audit-greg-abbott/.
[fn:14] See Nick Lichtenberg, “Without data centers, GDP growth was 0.1% in the first half of 2025, Harvard economist says,” October 7, 2025. https://fortune.com/2025/10/07/data-centers-gdp-growth-zero-first-half-2025-jason-furman-harvard-economist/.
[fn:15] See Michelle Cheng, “Nvidia Calms Credit Markets With AI Capital Consortium,” August 12, 2026. https://www.bloomberg.com/news/newsletters/2026-08-12/nvidia-calms-credit-markets-with-ai-capital-consortium.
[fn:16] See Ethan Howland, “PJM fast-tracks 11.8 GW, mainly gas, to bolster power supplies” May 5, 2025. https://www.utilitydive.com/news/pjm-resource-reliability-rri-gas-interconnection/747090/.
[fn:17] Croop Affidavit P 21.
[fn:18] Filing Transmittal Letter at 56, Filing Proposed Tariff Attachment DD, Section 18.5(e).
[fn:19] Filing Transmittal Letter at 54-55, Filing Proposed Tariff Attachment DD, Section 18.5(e).
[fn:20] See “Cycle Schedule Update,” Colleen Lauver, Interconnection Analysis Interconnection Process Subcommittee July 27, 2026. https://www.pjm.com//media/DotCom/committeesgroups/subcommittees/ips/2026/20260727/20260727-item-03---cycle-schedule-update.pdf. Phase III of TC 2 has just started as of July 8, 2026 for review. Cycle 1 is still in the application review process to start Phase I.
[fn:21] See also Installed Reserve Margin (IRM), Forecast Pool Requirement (FPR), and Effective Load Carrying Capability (ELCC) for 2029/2030 BRA, Patricio Rocha-Garrido Resource Adequacy Planning Markets and Reliability Committee August 19th, 2026 (“IRM Presentation”) that shows the variation from one year to the next in ELCC accreditation value. https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260819/20260819-item-01a---1-periodic-review-of-default-cone-and-acr-values---presentation.pdf.
[fn:22] Table 1 uses a simple CRF formula of
[fn:23] The Brattle Group: Samuel A. Newell, Andrew W. Thompson, Bin Zhou, Nathan Felmus, Harsha Haribhaskar
Sargent and Lundy: Sang H. Gang, Joshua C. Junge, Hyojin Lee, Liam Tawelian, “Brattle 2025 CONE Report for PJM: Informing Parameters for PJM’s RPM Auctions for Delivery Year 2028/29 through 2031/32”, April 9, 2025. https://www.brattle.com/wp-content/uploads/2025/04/Brattle-2025-CONE-Report-for-PJM.pdf. (Brattle CONE Report”)
[fn:24] Michael Cembalest, JP Morgan, “EYE ON THE MARKET 16TH ANNUAL ENERGY PAPER |
MARCH 2026: Fighting Words at 14. (JP Morgan Report”) https://cdn.jpmorganfunds.com/content/dam/jpm-am-aem/global/en/insights/eye-on-the-market/fighting-words-amv.pdf
[fn:25] GridLab, Energy Futures Group, Halcyon, “THE NEW REALITY OF POWER GENERATION An Analysis of Increasing Gas Turbine Costs in the U.S. September 2025 (“GridLab Report”), Appendix, Table 2. https://gridlab.org/portfolio-item/gas-tubine-cost-report/.
[fn:26] Margaret Walker, “Oglethorpe Power breaks ground on $3.3B Monroe natural gas plant to meet rising demand” Macon Telegraph, May 18, 202.6 https://www.macon.com/news/environment/article315684127.html. The $/kW was taken as $3.3 billion divided by the 1,425 MW capacity.
[fn:27] Robert Walton, “JEA plans $1.6B, 675-MW gas plant”, September 2, 2025. https://www.utilitydive.com/news/jea-jacksonville-plans-675-mw-gas-plant/758981/. The $/kW was taken from $1.6 billion divided by the 675 MW announced capacity.
[fn:28] Talk Business & Politics staff, “Entergy Arkansas estimates Jefferson Power Station to cost $1.6 billion”, Talk Business and Politics, November 6, 2025. https://talkbusiness.net/2025/11/entergy-arkansas-estimates-jefferson-power-station-to-cost-1-6-billion/. The $/kW was taken from $1.6 billion divided by the 754 MW announced capacity.
[fn:29] Brattle CONE Report, Table 17.
[fn:30] The $2800/kW JP Morgan figure has not been considered as there have been no public announcements to verify this.
[fn:31] See By Liam Denning, Bloomberg, “SoftBank’s Ohio power plant delivers an AI sticker shock” The Japan Times, March 3, 2026. https://www.japantimes.co.jp/commentary/2026/03/03/japan/softbanks-ohio-power-plant-ai-sticker-shock/
[fn:32] Monitoring Analytics, Independent Market Monitor for PJM, “2025 State of the Market Report for PJM Volume 2: Detailed Analysis,” March https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025-som-pjm-vol2.pdf. (“2025 SoM Report”)
[fn:33] Id. Table 7-10.
[fn:34] IRM Presentation at 5.
[fn:35] Brattle 2025 CONE Study Table 17 at 58.
[fn:36] Id. at Table 15 at 52.
[fn:37] Brattle 2025 Cone Study,
[fn:38] GridLab Report, Appendix Table 1. There is one outlier at $1130/kW that seems to be a special case and has been omitted from the range. It seems the turbines were announced in 2023 and likely purchased at a much lower cost at the time.
[fn:39] 2025 SoM Report Table 7-8.
[fn:40] IRM Presentation at 5.
[fn:41] Brattle CONE Study, Table 13 at 49
[fn:42] Brattle CONE Study, Table 21 at 69.
[fn:43] Id. at Table 22 at 76.
[fn:44] IRM Presentation.
[fn:45] “Periodic Review of Default Gross CONE and Gross ACR Values,” Pete Langbein, Markets & Reliability Committee August 19, 2026, at 5. https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260819/20260819-item-01a---1-periodic-review-of-default-cone-and-acr-values---presentation.pdf.  (“MOPR Update Presentation”).
[fn:46] 2025 SoM Table 7-28 taking the highest zonal; average over the 2014-2025 period. The IMM only provides net revenue for zones in New Jersey plus Dominion and DPL.
[fn:47] IRM Presentation at 5.
[fn:48] 2025 SoM at Table 7-29 taking the highest zonal; average over the 2014-2025 period.
[fn:49] See https://www.pjm.com/planning/m/cycle-service-request-status.
[fn:50] MOPR Update Presentation at 5.
[fn:51] 2025 SoM. Table 7-18 taking the highest zonal average over the 2014-2025 period. The IMM only provides net revenues for AEP, ComEd, APS, and PE.
[fn:52] IRM presentation at 5.
[fn:53] 2025 SoM Table 7-19 taking the highest zonal; average over the 2014-2025 period.
[fn:54] Filing Transmittal Letter at 61-64. Croop Affidavit PP 26-29
[fn:55] Id. at 64. PJM states, “In the case of the RBP, the proposed maximum
willingness to pay is based on the Commission-approved price cap set administratively through PJM’s periodic review, equal to Point 1 on the Commission-approved VRR curve, representing the high end of the range of uncollared clearing prices.”
[fn:56] $555/MW-day UCAP x 365 days per year x 15 years.
[fn:57] Levelized value of 6,831.3 MW UCAP each year at $555/MW-day.

footer1 (Word template)
Page | 2