ER26-3380-000 · 2026-08-24 · E-Cubed Policy Associates, LLC

Comment, Protest, and Motion for Leave to File One Day Out of Time of E-Cubed Policy Associates, LLC in response to PJM Interconnection, L.L.C.’s 07/31/2026…

Text extracted from the eLibrary original (SHA-256 7e0d74ef60e3b4bf…). Download the original from the official source.

Read topic-matched comments in ER26-3380

Topics in the text: Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Instead, E-Cubed proposes a true budget concept that is a function of both the $555/MW-day price[fn:7] and the 6,831.3 MW UCAP shortfall[fn:8] that will procure capacity so long as the expenditures do not exceed the budget while allowing offers that are commensurate with the actual costs of…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Reliability and curtailment

Further, E-Cubed asks the Commission to reject PJM’s RBP proposal for the reasons cited herein and implement the proposed budget approach to improve resource adequacy in PJM even incrementally.
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated at Gainesville, FL this 22nd day of August, 2026. /s/ Paul M.
Read this passage

Footnotes

Word notes · Topic match: Reliability and curtailment

E-Cubed represents multiple parties in the PJM stakeholder process and assists them in economic and regulatory matters in the power industry in PJM and other RTO markets. [fn:3] Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.212 (2025), E-Cubed…
Read this passage Filed comments: Reliability and curtailment