ER26-3380-000 · 2026-08-21 · Advanced Energy United
Comments of Advanced Energy United in response to PJM Interconnection, L.L.C.’s 07/31/2026 filing
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, L.L.C
)
Docket No. ER26-3380-000
)
COMMENTS OF ADVANCED ENERGY UNITED
Pursuant to Rule 211 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedures,1 Advanced Energy United2 (“United”) submits these comments in response to PJM Interconnection, L.L.C.’s (“PJM”) revisions to the PJM Open Access Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish the Reliability Backstop Procurement (“RBP”).3 United generally supports PJM’s July 31, 2026, filing as the best available solution to address the pressing challenge of rapid load growth and slow resource entry in a manner that avoids putting even greater cost burden on existing customers not contributing to the resource adequacy shortfall. However, RBP is far from an ideal outcome, and must be implemented in a manner that avoids perverse and distortionary outcomes that could undermine the investment landscape in PJM. Advanced Energy United’s comments below point to areas that need clarification and/or commitment from PJM, both in the context of RBP itself and to improve the region’s resource adequacy outlook moving forward.
1 18 C.F.R. § 385.2112 Advanced Energy United is a national association of businesses that are making the energy we use secure, clean, and affordable. Advanced Energy United is the only industry association in the United States that represents the full range of advanced energy technologies and services, both grid-scale and distributed. Advanced energy includes energy efficiency, demand response, energy storage, wind, solar, hydro, nuclear, electric vehicles, and more.3 PJM Interconnection, L.L.C. “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” Docket No. ER26-3380-000 (filed July 31, 2026) (“Transmittal Letter”).
PDF page 2
2
I. INTRODUCTION
PJM is navigating a genuinely difficult situation, and the RBP reflects real effort to design a workable response under significant time pressure. United and its members have been active participants throughout the stakeholder process leading to this filing, and the RBP framework and related Interim Resource Adequacy Service (“IRAS”) proposal as proposed reflect meaningful refinement from the concepts PJM initially floated through the Critical Issue Fast Path processes earlier this year and in 2025. For these reasons and because of the urgency of taking action, United does not oppose the RBP mechanism PJM has proposed.
United’s support, however, is not without reservation. The comments below identify specific areas where PJM’s proposal falls short of its own stated objectives, or where PJM’s own reasoning for excluding otherwise-qualified resources does not withstand scrutiny. United urges the Commission to direct PJM to act on these issues promptly, for two related reasons. First, several of the barriers discussed below—particularly with respect to Surplus Interconnection Service and demand-side resources—unnecessarily constrain the pool of fast-to-deploy capacity available to the RBP, and addressing them would materially improve PJM’s chances of actually filling the shortfall the RBP is designed to address. Second, and more broadly, these same barriers bear directly on the success of PJM’s separate Build Your Own New Capacity (“BYONC”) initiative and on the durability of investment confidence in PJM generally; resolving them now will pay dividends well beyond this single procurement. United emphasizes that RBP was conceived, and must remain, a one-time, bounded response to the specific shortfall identified in the 2028/2029 Base Residual Auction, not a template PJM may invoke unilaterally
PDF page 3
3
each time a future auction falls short. United’s comments accordingly conclude with specific recommendations to ensure the mechanism does not outlive its stated purpose.
II. COMMENTS
A. RBP Includes Important Elements that will Contribute to its Success
PJM should be commended for several elements of the RBP design that will support full participation by qualified resources and promote fair outcomes for developers navigating the procurement’s compressed timeline.
First, United supports the shortfall-charge exception for resources unable to meet their expected commercial operation date solely due to Network Upgrades, where the resource demonstrates readiness through test energy and seeks interim deliverability.4 Network Upgrade costs and schedules represent one of the largest sources of risk facing new capacity development in PJM today. A meaningful share of the resources best positioned to participate in the RBP are currently at some stage of the interconnection process, and without this exception, those resources would bear shortfall-charge risk for delays entirely outside their control, a result that would needlessly shrink the pool of supply available to the RBP at the exact moment PJM most needs it to be as large as possible.
United cautions, however, that this exception addresses only one element of the risk that projects still in the queue face: it excuses the shortfall charge itself, but developers must still price uncertain Network Upgrade costs and schedules into their RBP bids, and continue to bear real cost and schedule risk for as long as their projects remain queued. This exception is a necessary and well-designed accommodation, but it is not a substitute for PJM continuing to prioritize a faster, more predictable interconnection process and to resolve Network Upgrade cost
4 Transmittal Letter at 60.
PDF page 4
4
and schedule uncertainty that persists even after a generator interconnection agreement is signed. Both the Commission and PJM should remain actively engaged on these challenges well beyond the scope of this proceeding.
Second, United also welcomes PJM’s decision to allow new load to use Surplus Interconnection Service (“SIS”) capacity to reduce its own RBP obligation as Qualifying RBP offset UCAP.5 Recognizing SIS-derived capacity as legitimate, usable supply for these purposes is the right outcome. United notes, however, that this recognition does not currently extend to allowing SIS-based resources to sell directly into the RBP, an asymmetry United addresses separately. Nor does it resolve barriers to full utilization of SIS to deliver new capacity to the PJM region, an issue that United urges PJM to resolve expeditiously outside of the RBP proceeding, as discussed below.
Third, United appreciates PJM’s inclusion of Demand Response and DER Aggregation Resources as eligible sources of Qualifying RBP Offset UCAP MW, including their use as a bridge for new load pending availability of generation or storage capacity not yet in service.6 United welcomes this bridge function as one use case among several, but does not read it as limiting the role Demand Response and DER Aggregation Resources can or should play; these resources provide durable capacity, energy, and congestion relief value independent of whether new generation or storage is also under development, and PJM’s Tariff should recognize that standing value rather than treating demand-side participation as merely transitional. Demand- side resources are flexible, comparatively affordable, and capable of being deployed quickly relative to new-build generation, and their inclusion here is a meaningful step, even as United
5 Id at 36.6 Id at 40.
PDF page 5
5
requests additional flexibility regarding their eligibility to participate as RBP Resources, as discussed below.
Fourth, United supports the narrow opt-out PJM has proposed for Electric Distributor zones/areas with a qualifying peak-shaving adjustment.7 However, as discussed below, this provision requires clarification to ensure it functions as intended alongside PJM’s separate Interim Resource Adequacy Service (“IRAS”) filing.
PJM has made genuine progress toward a workable backstop mechanism, and it is against that backdrop that United respectfully identifies, in the comments below, the specific clarifications and commitments needed to ensure RBP achieves its intended purpose without creating new barriers to the very resources best positioned to help.
B. Some Elements of RBP Require Clarification or Further Commitment
PJM indicated that it would accept discrete revisions from the Commission “where such modification and/or severance is consistent with PJM’s overarching objectives in this filing.”8 In this context, United respectfully offers the following opportunities to enhance the RBP, provided that they can be implemented such that they do not “give[…] rise to complications” or cause delay of the RBP and/or BRA for the 2029/2030 delivery year.9 The discrete recommendations below aim to increase supply in the RBP and improve PJM’s overall resource adequacy outlook. To the extent any of these recommendations would delay implementation of RBP, United recognizes the urgency of the procurement and accepts the current design, though imperfect, as good enough. United strongly urges, however, that PJM and the Commission commit to further
7 Id at 44-45.8 Id at 3.9 Id.
PDF page 6
6
reforms across all the areas identified below to improve outcomes beyond the RBP, and to ensure that the RBP remains a one-time emergency measure.
i. Peak Shaving Adjustment Opt-Outs Should be Clarified
As noted above, United supports PJM’s proposal to allow Electric Distributor zones/areas with a qualifying peak shaving adjustment to opt out of a portion of their RBP obligation.10 This opt-out recognizes that load which has already taken concrete steps to reduce its own contribution to peak demand should not be treated the same as load that has done nothing to address the shortfall it is helping to cause, and it gives Electric Distributors a meaningful incentive to pursue peak shaving arrangements going forward.
That incentive, however, depends entirely on the opt-out actually relieving the load in question of backstop-related obligations, and PJM’s filing leaves that question unresolved. In its RBP filing, PJM states that “even if the Electric Distributor zone/area qualifies for and receives an opt-out from the RBP, the load in that zone/area may be subject to load reduction under the forthcoming proposal to implement a IRAS.”11 PJM's now-filed IRAS proposal confirms this concern rather than resolving it. Under the proposed Eligible New Large Load Amount formula, a Large Load's exposure to IRAS curtailment is reduced only by its BYONC arrangements and Allocated RBP UCAP MW; Peak Shaving Adjustment values, though separately tracked in the Large Load Registry, play no role in that calculation.12 Read in the most concerning light, this means a load that successfully qualifies for the RBP opt-out could nonetheless find itself subject to IRAS curtailment on the same basis as load that made no effort to reduce its footprint at all, a
10 Id at 44-45.11 Id, at 46.12 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, 2026); id. at 37 (Large Load Registry data field for Peak Shaving Adjustment value, tracked but not used in the eligibility calculation).
PDF page 7
7
result that would undermine the very incentive the opt-out is meant to create. Clear, unambiguous rules on this point are essential, both to actually entice Electric Distributors and large loads to pursue peak shaving adjustments in the first place, and to give those that do the confidence they will not face unexpected penalties or curtailment exposure down the line once IRAS is filed. If Electric Distributors and their large-load customers cannot be confident that a peak shaving adjustment actually reduces their exposure, whether through avoided RBP charges or reduced curtailment priority under IRAS, many will have little reason to pursue the arrangement in the first place.
United recommends that the Commission direct PJM to amend the Eligible New Large Load Amount formula in the IRAS proceeding, Docket No. ER26-3515-000, to credit Peak Shaving Adjustment values on the same basis as BYONC and Allocated RBP UCAP MW, or to explain on the record why a load managing its footprint through a state-sponsored peak shaving program should be treated identically to one that has not. Absent such a change, the RBP opt-out risks functioning as a paper protection rather than a substantive one, since PJM’s own IRAS mechanics now confirm that a load's peak shaving efforts provide no relief from curtailment exposure. While Tariff changes are not needed in the instant filing, United respectfully requests that PJM clarify that Peak Shaving Adjustment will be taken into account when calculating IRAS exposure, even if the zone/area still has some remaining curtailment risk.
C. Unpredictable ELCC Values Carry Excessive Risk for Developers
ELCC values for solar, storage, and other accredited resources are set by PJM based on system-wide fleet mix and grid conditions that no individual developer can control, predict, or hedge over a fifteen-year commitment. PJM’s proposal only partially addresses the risk this uncertainty produces in the context of the RBP. Specifically, PJM allows developers to bid into
PDF page 8
8
the RBP based on their own expectations of a resource’s future Effective Load Carrying Capability (“ELCC”), including the ability to offer above the forecasted class rating, up to a defined cap, where a developer believes its resource’s accreditation value is likely to improve over the term.13 PJM also avoids applying shortfall charges to resources whose ELCC declines below their committed RBP UCAP once they achieve commercial operation.14 This treatment is a reasonable accommodation as far as it goes, but it does not go far enough: RBP resources remain subject to unhedgeable ELCC risk in the revenue settlement for supply.
Because that risk is effectively unhedgeable at the individual resource level, rational developers will either choose not to participate in RBP or price a substantial risk premium into their RBP offers to protect against it. This premium will exceed the actual expected cost of ELCC variability and raise the cost of the RBP regardless of whether the risk materializes. A better approach, consistent with proposals other stakeholders have put forward, would separate this risk into its two component parts rather than assigning both to the developer.15 The portion of ELCC decline that PJM can already forecast, based on known and projected fleet buildout, should be published as an official long-term forecast covering the full RBP term, so that developers can price that expected trajectory into their bids at face value, without needing to guess at it or pad for it. The portion that cannot be forecast, meaning the variance above or below that expected trajectory driven by factors outside any single developer’s control, should instead
13 Proposed Tariff, Attachment DD, § 18.5(e)(i) (Transmittal Letter at 55) (requiring RBP Sell Offers to state UCAP MW based on the resource’s current ELCC Class Rating or unit-specific estimate, with sellers permitted to offer up to 120% of that rating to reflect projected future improvement, at the seller’s own risk if the projection proves too optimistic).14 Transmittal Letter at 87.15 See PJM Stakeholder Proposal of REV Renewables, LS Power, Middle River Power, and Geronimo Power, PJM Reliability Backstop Procurement Design (submitted June 30, 2026) (“Proposing Companies' Alternative Proposal vs. PJM Proposal”) https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630- item-02k---rev-renewables--ls-power---mrp---geronimo---rbp---executive-summary.pdf
PDF page 9
9
be absorbed by RPM, where ELCC variability already manifests annually for every resource in the fleet as a matter of course. Shifting that unhedgeable component to RPM, so long as an RBP resource’s underlying installed capacity remains unchanged, would allow ratepayers to bear the actual cost of ELCC variability as it occurs, rather than an inflated risk premium embedded in every RBP bid whether or not that variability ever materializes. The practical result should be lower, more competitive RBP offers at equivalent or lower total cost to load. Addressing this risk is not simply a matter of fairness to developers, it bears directly on whether the RBP achieves its stated reliability purpose. An inflated risk premium does not just raise the price load pays for capacity that clears, it risks excluding resources from clearing at all. Because PJM’s proposed maximum willingness to pay is fixed as a MW-weighted average levelized cost across all selected offers, resources forced to bid in an unhedgeable ELCC risk premium are more likely to price above that cap, or above where competing offers clear, and be passed over in the selection process entirely. Every resource priced out of the RBP on that basis is capacity that does not get procured toward the Final RBP Target, increasing the chance that the target is not reached. These resources also bring reliability value beyond their raw UCAP contribution. For example, storage paired with solar helps shift midday generation into the evening hours when PJM’s system is most at risk, and a resource mix that includes solar and storage alongside gas reduces PJM’s exposure to the kind of correlated, fuel-supply-driven failures that have caused widespread forced outages among gas generation during past extreme cold weather events.16 Excluding or discouraging these resources through avoidable pricing risk
16 See “Winter Storm Elliott: Event Analysis and Recommendation Report” PJM Interconnection, L.L.C. at Page 49 (July 17,2023) (Of the total 49,959 MW forced outages 33,404 or 71% was natural gas facilities.) https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2023/20230717-winter-storm-elliott- event-analysis-and-recommendation-report.pdf.
PDF page 10
10
not only harms individual developers, it narrows the diversity and resilience of the resource mix the RBP is meant to secure.
United further notes that ELCC uncertainty is compounded for DER Aggregation Resources by factors distinct from those affecting utility-scale solar and storage. The accreditation methodology PJM applies to behind-the-meter aggregated resources depends not only on fleet-wide modeling assumptions, but also on PJM’s still-evolving rules for how distributed resources are modeled, dispatched, and measured, including ongoing changes to metering, telemetry, and baseline methodologies that can independently shift a DER aggregation’s accredited value from one delivery year to the next. Any commitment PJM makes to enhance ELCC forecasting and accreditation stability should expressly cover DER Aggregation Resources, not solely utility-scale resource classes, so that aggregators bidding into the RBP or future capacity procurements can price their offers based on a published, transparent forecast rather than guessing at both fleet-wide ELCC dynamics and PJM’s own methodological evolution simultaneously.
United requests, at a minimum, that PJM commit to enhancing its ELCC forecasting and accreditation process in the near term to promote greater stability and predictability for all capacity resources, whether bidding into RBP, the RPM, and/or pursuing other long-term commitments. Doing so would benefit not only the RBP procurement itself, but investment confidence in PJM’s capacity market more broadly, which is ultimately essential to supporting durable resource adequacy outcomes across the region. Absent such action, PJM risks
PDF page 11
11
perpetuating an uncertain investment environment that has contributed to the region’s failure to bring on new resources to address its growing reliability shortfall.
D. Exclusion of Surplus Interconnection Service from RBP is a missed opportunity
PJM recognized SIS as a tool to address “the need for more Capacity on the PJM Transmission System from resources that can be brought online quickly” when it proposed reforms to its SIS process in 2024, approved by FERC in 2025, to “encourage and facilitate the use of Surplus Interconnection Service from existing and planned generating units on PJM’s system.”17 Despite significant progress, barriers to full utilization of SIS remain, and this filing misses an opportunity to capitalize on SIS as a pathway to accelerate capacity additions. PJM’s proposal draws a sharp line between the criteria for capacity that may offset a load’s RBP obligation and the criteria for capacity eligible to be sold into the RBP as an RBP Resource, and Surplus Interconnection Service capacity falls on the favorable side of that line for one purpose and the unfavorable side for the other: new load may use SIS-derived capacity to reduce its own RBP obligation,18 but a resource relying on SIS is expressly barred from selling into the RBP as an RBP Resource.19 PJM’s stated rationale for the exclusion turns principally on the difficulty of cleanly attributing UCAP between an existing host resource and a surplus addition, which PJM states “creat[es] uncertainty and the need for sensitivities or estimates” in both the incremental capacity determination and RBP settlement.20 PJM’s reasoning treats SIS- based capacity as real and valuable enough to net against a load’s RBP obligation, yet not reliable enough to sell into the RBP, even though the underlying physical capacity is identical
17 PJM Interconnection, L.L.C. “Proposed Tariff Amendments for Surplus Interconnection Service” Docket No. ER25-778-000 (filed Dec 20, 2024), Transmittal Letter at 6.18 Transmittal Letter at 36. (Proposed Tariff, Attachment DD, § 18.2(a)(iii))19Id at 53 (“[R]esources relying on Surplus Interconnection Service to bring new UCAP MW on the PJM system do not qualify as RBP Resources, because these resources do not have any independent rights to the PJM system.”).20 Croop Affidavit at P 20 (Transmittal Letter at 53-54).
PDF page 12
12
either way.21 United is concerned by PJM’s decision to leave valuable SIS capacity on the sidelines, and urges the Commission and PJM to act quickly to increase SIS opportunities, for two reasons.
First, SIS is a uniquely fast-to-deploy resource, and allowing SIS-based capacity to contribute to addressing PJM’s resource adequacy challenges should be a priority independent of the RBP. SIS was designed specifically to bring new capacity online faster than a full interconnection study process would otherwise allow, by making use of interconnection rights an existing resource is not fully utilizing.22 At a moment when PJM has determined that a 6,831.3 MW UCAP shortfall requires an unprecedented 15-year backstop procurement mechanism,23 PJM should simultaneously be doing everything it can to ensure that one of the fastest-to-market sources of new capacity is actually facilitating new capacity additions in practice. Second, and relatedly, this is not the only barrier limiting the full use of SIS to deliver new capacity to PJM. Current market participation rules do not provide a meaningful pathway in practice for SIS based resources to bring new capacity onto the system. A surplus resource that wishes to participate in PJM’s markets must either hybridize with the original interconnection customer, which generally requires unwinding existing commercial obligations; or abandon its SIS-based interconnection status and instead pursue a full interconnection study to obtain its own incremental Capacity Interconnection Rights and Maximum Facility Output, co-located with the existing host resource.24 PJM's own affidavit confirms that this is true for the RBP specifically as
21 Compare Proposed Tariff, Attachment DD, § 18.2(a)(iii) (Transmittal Letter at 36), with Croop Aff. ¶ 20 (Transmittal Letter at 53–54).22 Croop Affidavit at P 17.23 Id at P 4.24 Id at P18 (“[T]hese sited projects would still have an opportunity to offer into the RBP and co-locate with the existing resource and be studied by PJM for increased CIRs and MFO at the facility through the interconnection process.”).
PDF page 13
13
well: a surplus resource's only path to participate in the RBP is this same full interconnection process, not its existing SIS arrangement.25 In other words, current market participation rules effectively restrict meaningful capacity participation, in the RBP or otherwise, by SIS resources, undermining the speed-to-market advantage that makes these resources valuable in the first place. To take the common example of storage added to an existing solar site, SIS only grants capacity interconnection rights (“CIRs”) if the storage merges into the solar plant as a single hybrid resource. However, this pathway typically requires unwinding existing PPA, tax equity, and lender agreements, which is rarely feasible on an operating asset. If storage instead interconnects independently as a co-located resource, it must participate in PJM markets as energy-only—forfeiting all capacity accreditation and preventing SIS from serving as a tool to expedite accredited capacity entry in PJM. United recommends that PJM address this barrier both within the RBP and more broadly across its capacity market participation rules. Within the RBP, United recommends that the Commission direct PJM to allow the incremental UCAP created by an SIS-based addition, meaning the difference between the resulting hybrid resource's UCAP and what the host resource's UCAP would have been on a standalone basis, to qualify for the RBP. This approach directly resolves PJM’s stated concern regarding unclear UCAP attribution between the existing resource and the surplus addition,26 because it does not require PJM to determine how much of the hybrid resource’s total UCAP belongs to which component. It instead isolates and credits only the new value created by the surplus addition, a discrete and calculable quantity, while leaving the host resource’s pre-
25 Id.26 Id at P 20.
PDF page 14
14
existing UCAP contribution untouched and outside the RBP altogether. This should be a discrete and surgical adjustment to RBP eligibility.
Separate and apart from RBP, United requests that PJM commit to expand opportunities for SIS-based resources in PJM's capacity market, so that this same fast-to-deploy source of capacity is not permanently forced to choose between hybridization or a full interconnection study as its only options to deliver new capacity to PJM. Specifically, United requests that PJM commit to a broader stakeholder review that would consider the following solutions:
• Settle UCAP into two accounts. Keep CIRs pooled under a single GIA—no allocation or division required—but settle the resulting UCAP between two capacity market participant accounts, one for solar and one for the battery. Because a hybrid resource behind one set of CIRs generates more combined UCAP than the same two assets would under any divided-CIR approach, this option preserves the most total UCAP while still giving each owner an independently recognized, bankable capacity position. One reasonable way to handle UCAP allocations would be to allocate the existing resource whatever it would have gotten without the hybrid addition and then to allocate the remaining UCAP to the addition. Capacity market revenues, PAI obligations, and PAI liability would flow to each account according to this split.
• Independent E&AS participation. Allow the component parts of a hybrid resource to participate independently in Energy & Ancillary Services markets. PJM has already indicated interest in exploring this pathway in its “Hybrid Resources Market Model Selection” Problem Statement / Issue Charge.27 Capacity market revenue still has to be
27 PJM, Issue Charge: Hybrid Resources Market Model Selection (Aug. 2026), available at https://www.pjm.com/- /media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-2---hybrid-resources- market-model-selection---issue-charge.pdf.
PDF page 15
15
disaggregated ex post between the two owners in many cases, but this model has attracted significant developer interest.
• CIR transfer between components. Enable CIR transfers between the components of a co-located resource, so each party can hold, finance, and transfer its own share. Suppliers—not a fixed ELCC proportional formula—should determine how CIRs are allocated between them. This would resemble the CIR transfer process that is available to deactivating generators, i.e., this would enable CIR transfers for resources that are partially giving up capacity resource status. It would be appropriate to require that any transfer only be allowed if it resulted in a net increase in system UCAP.
Pursuing these reforms to SIS will not deliver more capacity through the RBP, but it will make additional capacity available in upcoming BRAs and via bring your own new capacity arrangements, and thus help to resolve tight resource adequacy conditions that are expected to persist beyond the RBP. The Commission can encourage progress from PJM to fully realize its goal to “encourage and facilitate the use of Surplus Interconnection Service” as a tool to bring more capacity onto its system quickly28; and, if progress is not made, take further action to ensure a fully functional SIS process in PJM.
E. Restrictions to DR/DER Participation will Limit RBP Participation of
Affordable, Fast-to-Deploy Resources
Demand-side resources and demand response are among the most affordable and flexible solutions to address PJM’s resource adequacy shortfall, capable of being deployed on timescales of three to twenty-four months, alongside generation resources that may target later commercial
28 “Proposed Tariff Amendments for Surplus Interconnection Service” Docket No. ER25-778-000 Transmittal Letter at 6. (December 20, 2024)
PDF page 16
16
operation dates.29 PJM has offered some promising opportunities to deploy more of these resources in the instant filing, but has simultaneously erected unnecessary barriers. As with Surplus Interconnection Service, PJM applies materially different eligibility standards to Demand Response and DER Aggregation Resources depending on whether they are offsetting a load’s own RBP obligation or competing to sell into the RBP as RBP Resources. While both pathways suffer deficiencies, they can be remedied through surgical changes that will expand DR and DER availability and help to close PJM’s resource adequacy gap.
a. Qualifying RBP Offset MW Rules for DR and DERs
Should be Clarified
To offset an RBP obligation, DR/DER can provide Qualifying RBP Offset MW either as a new supply resource or through direct enrollment of a new load as an Annual Demand Response or DER Capacity Aggregation Resource. United supports these pathways. However, the latter is described as a bridge mechanism pending the availability of generation or storage capacity not yet in service.30 United does not oppose the option for DR/DER to serve as a bridge mechanism, but also urges against artificially constraining Demand Response and DER Aggregation Resources to serve as temporary solutions. Demand-side resources and demand response deliver standing capacity, energy, and transmission congestion relief benefits that persist independent of whether new generation or storage capacity comes online; they are not merely a placeholder for supply that has not yet materialized. PJM’s Tariff and this proceeding should recognize Demand Response and DER Aggregation Resources as a durable, permanent
29 Voltus, Inc., Submission to the PJM Board, Critical Issue Fast Path Stage 4, Reliability Backstop Procurement / Connect & Manage, at 1 (June 2026). https://www.pjm.com/-/media/DotCom/committees-groups/cifp- rbp/2026/20260630/20260630-item-02l---voltus---cm-and-rbp---executive-summary.pdf30 Transmittal Letter at 40.
PDF page 17
17
component of the resource mix addressing PJM’s shortfall, not solely as an interim measure to be phased out or superseded once other capacity arrives.
A related ambiguity in the offset pathway itself warrants clarification. Proposed Tariff, Attachment DD, § 18.2(c) offers Qualifying RBP Offset UCAP MW status through three evidentiary pathways, but it is unclear whether behind-the-meter generation or storage backing a demand response arrangement may rely on the signed bilateral contract pathway in § 18.2(c)(i), available on equal terms to front-of-the-meter resources, or whether it is instead confined to the demand response pathway in § 18.2(c)(iii), which imposes two requirements not applicable under (c)(i): that the resource offset the new load's full MW quantity rather than a partial share, and that it be in place by the 2028/2029 Delivery Year Second Incremental Auction or the load purchase replacement offset capacity. United requests that PJM clarify that behind-the-meter generation and storage backing a demand response arrangement is not categorically confined to the more restrictive pathway in § 18.2(c)(iii) solely because of its behind-the-meter configuration, consistent with PJM's function as a technology-neutral procurement mechanism.31 The offset provision also raises a threshold eligibility question distinct from the evidentiary ambiguity above. Proposed Tariff, Attachment DD, § 18.2(a) appears to limit Qualifying RBP Offset UCAP MW eligibility for demand-side resources to Planned Demand Response or Planned DER Capacity Aggregation Resource as described in RAA Schedule 6 and Schedule 6.2, potentially excluding reactivations of previously active sites and new capacity at existing sites, categories that generation and storage resources are expressly permitted to rely on under § 18.2(b), and that were included as offset-eligible for demand-side resources in every version of PJM's proposal discussed during the stakeholder process. United requests that PJM
31 Proposed Tariff, Attachment DD, § 18.2(c)(i), (iii).
PDF page 18
18
amend § 18.2(a) to align demand-side offset eligibility with the treatment already afforded to generation and storage under § 18.2(b), consistent with the stakeholder consensus reached on this issue.32
b. DR and DER Participating as RBP Supply face
Unnecessary Barriers to Entry
To participate in RBP, DR and DER must meet eligibility requirements that will render most, if not all, such resources unable to participate in practice. To qualify as an RBP Resource, a Demand Response or DER Aggregation Resource must have executed participation contracts covering the full fifteen year term, with every location identified, in place at the time of the RBP Sell Offer itself.33 PJM states this heightened requirement is necessary “to provide assurance that the supply will be available for the 15-year term,” in contrast to Qualifying RBP Offset UCAP MW, where commitment terms are simply “managed by the commercial contract between the buyer and seller.”34 PJM’s own reasoning treats demand-side resources as flexible and reliable enough to satisfy a load’s offset obligation on privately negotiated terms, yet not reliable enough to sell into the RBP without locking in a full fifteen year, fully site-identified commitment before ever submitting an offer.35 United does not oppose heightened requirements under the RBP, nor do we seek preferential treatment for DR/DER assets relative to other RPB resources. However, PJM’s proposal introduces three avoidable barriers to full participation by DR and DERs in the RBP itself that can be easily remedied to unlock additional supply through RBP. First, the proposed Tariff requires that every site in that portfolio must be identified and under contract for the full term at the time of the offer.36 For generation and storage resources, by
32 Proposed Tariff, Attachment DD, § 18.2(a), (b).33 Transmittal Letter at 54.34 Id at 55.35 Id at 40.36 Proposed Tariff, Attachment DD, §§ 18.5(c)(ii), 18.5(d)(i).
PDF page 19
19
contrast, PJM requires a critical path construction schedule, evidence of site control, financing and permitting plans, and, critically, “[s]igned memoranda or other documentary evidence that the developer has or will procure the major equipment necessary,” not a completed, executed equipment purchase contract.37 This reflects PJM's own recognition that final investment commitments are prudently made only once a revenue stream, meaning a successful auction result, is in place. PJM's own affidavit confirms that Demand Response and DER Aggregation Resources face no such accommodation, explaining that they “need to have contracts for the RBP term (i.e., up to 15 years) with the identified sites that are offering as RBP Resources.”38 The barrier PJM has constructed is a timing and term-length one: every site that will ever back the commitment must be locked in before the resource can even bid, for a term length that few demand-side commercial agreements are structured to support. PJM’s failure to explore alternative approaches to satisfying its stated deliverability-certainty objective, including a defined enrollment ramp-up plan supported by a credible compliance mechanism, rather than requiring a fully built and contracted portfolio as a precondition to bidding at all, is a missed opportunity of the RBP.
Second and more consequential, PJM’s proposal lacks any mechanism allowing a Demand Response or DER Aggregation Resource to substitute a departing site or customer for a new one over the course of a fifteen-year commitment. Section 18.6 of the proposed Tariff, which governs RBP Resource obligations over the life of a commitment, addresses numerous changes or challenges that could impact generation and storage resources, including shortfall
37 Proposed Tariff, Attachment DD, § 18.5(f)(i) (generation and storage evidentiary requirements) (emphasis added).38 Proposed Tariff, Attachment DD, § 18.5(f)(i) (Demand Response and DER Aggregation Resource evidentiary requirements) (emphasis added).
PDF page 20
20
charges,39 rescission for prolonged non-performance,40 and the treatment of a commitment upon change of ownership of the underlying resource.41 However, it contains no analogous provision permitting a DER Aggregator or Curtailment Service Provider to replace an individual site whose participation ends, whether because a customer relocates, closes, or simply does not renew, with a new, equivalent site. Where an ownership change in a generation or storage asset is expressly accommodated because the physical resource persists, a demand-side portfolio has no equivalent accommodation despite facing a materially higher likelihood, over a fifteen-year term, that at least some constituent sites will turn over. Allowing this flexibility would not relieve DER Aggregators or Curtailment Service Providers of any delivery or performance obligations under RBP, but would meaningfully expand willingness and ability of such resources to participate in RBP in the first place. Existing RPM deficiency charges already discipline an aggregator against over-committing volume it cannot deliver, since any underdelivery exposes the aggregator to those penalties independent of RBP; a substitution mechanism would not weaken that existing discipline, only allow a portfolio to remain whole as individual sites turn over. Absent a substitution mechanism, an RBP Resource in this position has no cure path other than exposure to daily shortfall charges under Section 18.6(d) for a portion of its portfolio it no longer controls.
These barriers fall with particular force on residential DER aggregators, whose portfolios consist of hundreds or thousands of individually enrolled households rather than a handful of commercial or industrial facilities. For a residential virtual power plant operator, requiring every participating site to be identified and under contract for a full fifteen-year term at the time of the
39 Proposed Tariff, Attachment DD, § 18.6(d).40 Proposed Tariff, Attachment DD, § 18.6(e).41 Proposed Tariff, Attachment DD, § 18.6(f).
PDF page 21
21
RBP Sell Offer is not merely burdensome; it is operationally incompatible with the way these resources are built and maintained. Residential DER portfolios experience predictable, ongoing customer turnover as homeowners relocate, sell their homes, or choose not to renew participation agreements, at rates that are well understood and manageable at the portfolio level but that guarantee individual site changes over any multi-year horizon. A residential aggregator with a diversified portfolio of several thousand homes can deliver highly reliable aggregate capacity even as individual customers cycle in and out, precisely because the portfolio’s statistical depth makes its aggregate performance far less sensitive to any single customer’s status than a commitment backed by one or two large facilities. PJM’s proposed eligibility criteria do not account for this distinction, and by treating a portfolio of thousands of residential sites identically to a single generation facility, PJM has effectively foreclosed participation by one of the fastest- growing and most scalable sources of dispatchable capacity available to address the shortfall. Third, the gating criteria applicable to Demand Response and DER Aggregation
Resource sell offers require, prior to selection, executed customer agreements identifying specific locations, customer names, and per-site curtailment or injection capability,42 together with either a procurement plan for, or evidence of already deployed, metering, telemetry, load control, and related equipment.43 United does not object to requiring a credible plan for this infrastructure as a condition of eligibility, but requests that PJM confirm on the record that a procurement plan, rather than infrastructure already installed and operational at the time of the offer, is sufficient to satisfy this requirement, consistent with the plain language of the proposed
42 Transmittal Letter at 74-75.43 Id at 75.
PDF page 22
22
Tariff provision itself.44 Absent that confirmation, developers may face pressure to build out costly infrastructure at their own risk, despite having no assurance their offer will be selected. United recommends that the Commission direct PJM to: (i) explore shorter or laddered commitment terms for Demand Response and DER Aggregation Resource sellers, consistent with the lighter-touch, procurement-plan-based approach already applied to generation and storage at the same stage of development, in lieu of a uniform fifteen year requirement; (ii) adopt a site substitution mechanism allowing an RBP Resource to replace a departing site with a new, equivalent capacity site without triggering shortfall charges under Section 18.6(d), consistent with the accommodation already made for generation and storage ownership changes under Section 18.6(f); and (iii) confirm that the equipment and metering requirements in Section 18.5(f)(i) may be satisfied by a credible deployment plan rather than requiring infrastructure to be fully installed prior to bid submission: (iv) confirm that behind-the-meter generation and storage backing a demand response arrangement may rely on the bilateral contract pathway in Section 18.2(c)(i) on the same terms as front-of-the-meter resources; and (v) amend Section 18.2(a) to align demand-side offset eligibility with the treatment already afforded to generation and storage under Section 18.2(b), consistent with the stakeholder consensus reached on this issue.
Beyond RBP, PJM should commit to reforms that optimize DR and DER participation in its markets, including but not limited to addressing metering and data access barriers, introducing additional DR and DER products with different durations and commitments, and improving communication during emergencies to enable optimal performance. As fast-to-deploy resources,
44 Proposed Tariff, Attachment DD, § 18.5(f)(i)(11) (requiring “[a]n equipment procurement plan or evidence of deployed” infrastructure) (emphasis added).
PDF page 23
23
DR and DERs offer promising tools to address PJM’s current capacity shortfall and deliver benefits to all customers, but market rules and participation barriers must be addressed to allow full participation and ensure optimal performance.
III. PJM MUST BE HELD ACCOUNTABLE FOR ENSURING THAT RBP
REMAINS A ONE-TIME MECHANISM
A. RBP is Specifically Designed as a One-Time Mechanism
PJM’s own filing provides the clearest evidence that RBP is meant to be a bounded, non- recurring response to the shortfall identified in the 2028/2029 Base Residual Auction, and PJM should be held to that characterization going forward. United understands that PJM has represented RBP as a one-time mechanism and takes PJM at its word on that point. United nonetheless requests assurance that steps will be taken to ensure this characterization holds in practice, so that RBP does not become a recurring tool PJM invokes each time a future auction reveals a shortfall.
Most notably, PJM defends its choice of a pay-as-bid clearing structure, rather than the uniform clearing price design PJM otherwise favors across its markets,45 specifically on the ground that the RBP “is not designed to be a durable or repeatable procurement,” such that “its pricing outcomes are less likely to serve as incentive market signals.”46 PJM further explains that because RBP resources will differ in contract duration, commercial operation date, and ELCC accreditation over the term, they do not constitute a single homogeneous product suited to uniform pricing, a rationale that only holds together if RBP is understood as a one-time, purpose-
45 Croop Affidavit at P 21 (“PJM generally supports a single-clearing-price market design and continues to view uniform clearing prices as the most efficient market outcome.”).46 Id at P 23.
PDF page 24
24
built mechanism rather than an ongoing feature of PJM’s capacity procurement architecture.47 Having justified a significant departure from its preferred market design specifically because RBP is one-time and non-repeatable, PJM should not be permitted to invoke RBP, or a substantially similar mechanism, as a recurring tool each time a future Base Residual Auction reveals a shortfall.
United recommends that the Commission condition its approval of this filing on an explicit acknowledgment that RBP is a one-time mechanism addressed specifically to resolve the shortfall identified in the 2028/2029 Base Residual Auction, and not a template PJM may invoke unilaterally in response to future shortfalls without a fresh stakeholder process and a new Section 205 filing subject to the Commission’s full review. Such a condition would simply hold PJM to the premise on which it has already built its own pay-as-bid justification, and would ensure that any future backstop procurement, should one prove necessary, is developed with the benefit of a new stakeholder process reflecting conditions and lessons learned at that time, rather than treated as a foregone conclusion based on this proceeding.
B. RBP Must be Followed by a Commitment to Durable Reforms
RBP treats the symptom of PJM’s current resource adequacy gap rather than its cause. The 6,831.3 MW shortfall identified in the 2028/2029 Base Residual Auction is itself the product of deeper structural issues. PJM itself has acknowledged that its capacity market is no longer fit for purpose, and requires holistic reform.48 New entry has been further hampered by persistent interconnection queue delays, evolving supply chain constraints, and permitting timelines, barriers documented in United’s own analysis, which found that PJM had the largest
47 Id at P 25.48 PJM, Powering Reliability Through Market Design (May 6, 2026), available at https://www.pjm.com/- /media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market- design.pdf.
PDF page 25
25
interconnection backlog of any U.S. grid operator at the end of 2023, that gas turbine wait times of five to seven years are now delaying new capacity into 2030–2032, and that 46 GW of PJM- approved projects remain unbuilt due to supply chain, siting, and permitting constraints.49 While PJM’s interconnection queue has begun processing new requests, the timeline for those projects to reach commercial operation is still many years out. Other factors have further stymied development in the region, including highly variable and uncertain ELCC values and lack of participation options available to the growing range of DR and DER technologies and solutions available today. RBP, as a one-time backstop, addresses the immediate shortfall these dynamics have produced, but does nothing to correct the underlying market structure and infrastructure challenges that produced it in the first place.
United commends PJM’s engagement, through the Critical Issue Fast Path process and otherwise, with the broader question of how to improve long term investment signals in PJM’s capacity market.50 United is encouraged by PJM’s commitment to holistic market reforms as part of its “Powering Reliability Through Market Design” effort.51 Absent such reform, PJM risks finding itself in the same position again: a future Base Residual Auction resulting in a shortfall that RPM’s existing structure was not designed to prevent, with RBP, or a mechanism like it, offered again as the only available remedy.
PJM should also prioritize the more immediate, lower-lift improvements identified elsewhere in these comments, including the ELCC risk allocation, Surplus Interconnection
49 “The Next Decade in PJM: A Path to Reliability and Affordability,” Synapse Energy Economics, Inc., prepared for Advanced Energy United, at 2–3 (Feb. 2026).50 Croop Affidavit at P 5 (describing RBP as designed to work “in part with ... a return to market fundamentals to support the expected load growth over the next decade”). 51”Powering Reliability Through Market Design : Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability” Walter Graf, PJM Interconnection L.L.C. (May 20, 2026) found at: https://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2026/20260520/20260520- powering-reliability-through-market-design
PDF page 26
26
Service reforms, network upgrade cost and schedule uncertainty, and Demand Response and DER Aggregation Resource participation barriers. These changes do not require a fundamental RPM redesign, but they would expand the capacity pool available in the interim, reducing the risk that PJM may resort to a second one-time backstop before durable reform is complete. The Commission should make clear that it expects PJM to make progress across these issues in the near term; at minimum, the Commission should explicitly state that it will categorically reject any future iteration of RBP if PJM cannot demonstrate that it has taken meaningful steps to avoid the need for a future RBP.
IV. RETAIL COST ALLOCATION - SUPPORTING STATE/LARGE LOAD
COORDINATION
The fairness premise underlying PJM’s proposed cost allocation framework, that large loads should bear the cost of the capacity procured on their account, depends on state and Relevant Electric Retail Regulatory Authority (“RERRA”) action that PJM’s proposal cannot itself guarantee.52 PJM’s allocation stops at the LSE level, using a state or RERRA-determined RBP Obligation where one is reported, or a default Peak Load Contribution ratio share where it is not.53 Whether the cost that lands on an LSE is then actually passed through to the large load causing it, or spread across an LSE’s broader retail base, is a retail ratemaking question entirely outside PJM’s proposal and, as PJM itself acknowledges, outside the Commission’s jurisdiction.54
United accordingly welcomes the June 30, 2026 letter from the Virginia State Corporation Commission and the Data Center Coalition, in which the parties committed to jointly develop model state retail tariff provisions addressing RBP retail cost allocation by
52 Transmittal Letter at 96-99.53 Id.54 Id at 96.
PDF page 27
27
January 1, 2028, and model retail emergency load reduction and interruptible service tariffs by February 1, 2027.55 This kind of state-level collaborative process is precisely the vehicle needed to close the gap between PJM’s wholesale allocation and actual cost recovery from the large loads driving the shortfall, since PJM’s wholesale-to-LSE allocation does not by itself guarantee that the customers causing the cost are the ones who ultimately pay it.
United supports a state level collaborative approach both because it appropriately respects the jurisdictional line between wholesale market design and retail ratemaking, and because it offers the most realistic path to fulfilling the commitment that all governors across the PJM states made in the January 16, 2026 Statement of Principles to use their authorities to allocate RBP costs to data centers and protect residential customers.56 United therefore does not ask the Commission to mandate a particular retail rate design in this proceeding, nor to compel state action beyond the Commission’s jurisdiction. That does not mean that there is no role for PJM or the Commission in ensuring fair outcomes at the state level. Specifically, PJM could commit to monitoring and supporting the development of state-level rate design mechanisms of this kind across its footprint, and report progress to the Commission and stakeholders on the extent to which RERRAs in each state have adopted RBP-reporting or comparable retail-level cost allocation mechanisms as RBP implementation proceeds. Such monitoring would preserve the cooperative-federalism structure PJM’s proposal is built on, while ensuring that the absence of state action in any given jurisdiction does not go unnoticed until costs have already been
55 Letter from Chair Kelsey Bagot, Virginia State Corporation Commission, and Josh Levi, Data Center Coalition, to Paula Conboy and David Mills, PJM Interconnection, L.L.C. (June 30, 2026) (Transmittal Letter at 11–12, nn. 27– 34).
56 Statement of Principles Regarding PJM, National Energy Dominance Council, at 2 (Jan. 16, 2026), https://www.energy.gov/documents/statement-principles-regarding-pjm.
PDF page 28
28
diffused across residential and small-commercial ratepayers who were not responsible for causing the shortfall in the first place.
The gap between this proceeding's cost-allocation premise and its actual retail-level effect is not merely theoretical. As discussed above, PJM’s now-filed Interim Resource Adequacy Service proposal confirms that a Large Load’s Peak Shaving Adjustment, one of the concrete steps a load can take to manage its footprint and reduce its cost exposure, plays no role in reducing that load’s exposure to IRAS curtailment.57 That outcome is a direct illustration of the risk that a mechanism intended to reward large loads that take affirmative steps to reduce their impact on the system can fail to deliver that benefit in practice, absent careful coordination across PJM’s parallel proceedings. United’s request that PJM commit to monitoring and reporting on state-level implementation applies with equal force to ensuring consistency between RBP’s cost-allocation and opt-out provisions and IRAS’s curtailment mechanics.
V. CONCLUSION
United accepts PJM’s proposed Reliability Backstop Procurement as a necessary tool to address the extraordinary challenges facing the region, and offers the clarifications and commitments identified in these comments as opportunities to improve the ability of the RBP to close PJM’s identified resource adequacy shortfall. United respectfully requests that the Commission direct PJM to address these issues on the timeline necessary to preserve the September 29, 2026, effective date PJM has requested, consistent with PJM’s own invitation for the Commission to modify or clarify specific provisions of its proposal. United appreciates the
57 Proposed RAA, Attachment DD-4, § V(b) (PJM Interconnection, L.L.C., Docket No. ER26-3515-000, Aug. 13, 2026).
PDF page 29
29
Commission’s consideration of these comments and looks forward to continuing to work with PJM and other stakeholders as this proceeding moves forward.
Respectfully submitted,
/s/ Mike Haugh
Caitlin Marquis, Managing Director
Mike Haugh, Director
Jon Gordon, Senior Director
Kelsey Koenig, Associate
Advanced Energy United
1801 Pennsylvania Ave. N.W., Suite 410
Washington, D.C. 20006
cmarquis@advancedenergyunited.org
mhaugh@advancedenergyunited.org
jgordon@advancedenergyunited.org
kkoenig@advancedenergyunited.org
PDF page 30
30
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated this 21st day of August 2026.
/s/ Mike Haugh