Comments of Advanced Energy United in response to PJM Interconnection, L.L.C.’s 07/31/2026 filing
Text extracted from the eLibrary original (SHA-256 49711740e92162c6…). Download the original from the official source.
Contents · 12 sections
- I. INTRODUCTION
- II. COMMENTS
- A. RBP Includes Important Elements that will Contribute to its Success
- B. Some Elements of RBP Require Clarification or Further Commitment
- C. Unpredictable ELCC Values Carry Excessive Risk for Developers
- D. Exclusion of Surplus Interconnection Service from RBP is a missed opportunity
- E. Restrictions to DR/DER Participation will Limit RBP Participation of
- III. PJM MUST BE HELD ACCOUNTABLE FOR ENSURING THAT RBP
- A. RBP is Specifically Designed as a One-Time Mechanism
- B. RBP Must be Followed by a Commitment to Durable Reforms
- IV. RETAIL COST ALLOCATION - SUPPORTING STATE/LARGE LOAD
- V. CONCLUSION
Read topic-matched comments in ER26-3380
Topics in the text: Reliability and curtailment · Connecting load and generation · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
However, RBP is far from an ideal outcome, and must be implemented in a manner that avoids perverse and distortionary outcomes that could undermine the investment landscape in PJM.Read this passage Filed comments: Reliability and curtailment
I. INTRODUCTION
printed heading · Topic match: Reliability and curtailment
United emphasizes that RBP was conceived, and must remain, a one-time, bounded response to the specific shortfall identified in the 2028/2029 Base Residual Auction, not a template PJM may invoke unilaterally 3 each time a future auction falls short.Read this passage Filed comments: Reliability and curtailment
II. COMMENTS
printed heading
II.Read this passage
A. RBP Includes Important Elements that will Contribute to its Success
printed heading · Topic match: Cost allocation
United cautions, however, that this exception addresses only one element of the risk that projects still in the queue face: it excuses the shortfall charge itself, but developers must still price uncertain Network Upgrade costs and schedules into their RBP bids, and continue to bear real cost and…Read this passage Filed comments: Cost allocation
B. Some Elements of RBP Require Clarification or Further Commitment
printed heading · Topic match: Reliability and curtailment
While Tariff changes are not needed in the instant filing, United respectfully requests that PJM clarify that Peak Shaving Adjustment will be taken into account when calculating IRAS exposure, even if the zone/area still has some remaining curtailment risk.Read this passage Filed comments: Reliability and curtailment
C. Unpredictable ELCC Values Carry Excessive Risk for Developers
printed heading · Topic match: Cost allocation
United requests, at a minimum, that PJM commit to enhancing its ELCC forecasting and accreditation process in the near term to promote greater stability and predictability for all capacity resources, whether bidding into RBP, the RPM, and/or pursuing other long-term commitments.Read this passage Filed comments: Cost allocation
D. Exclusion of Surplus Interconnection Service from RBP is a missed opportunity
printed heading · Topic match: Connecting load and generation
If storage instead interconnects independently as a co-located resource, it must participate in PJM markets as energy-only—forfeiting all capacity accreditation and preventing SIS from serving as a tool to expedite accredited capacity entry in PJM.Read this passage Filed comments: Connecting load and generation
E. Restrictions to DR/DER Participation will Limit RBP Participation of
printed heading · Topic match: Reliability and curtailment
United requests that PJM clarify that behind-the-meter generation and storage backing a demand response arrangement is not categorically confined to the more restrictive pathway in § 18.2(c)(iii) solely because of its behind-the-meter configuration, consistent with PJM's function as a…Read this passage Filed comments: Reliability and curtailment
III. PJM MUST BE HELD ACCOUNTABLE FOR ENSURING THAT RBP
printed heading
PJM MUST BE HELD ACCOUNTABLE FOR ENSURING THAT RBP REMAINS A ONE-TIME MECHANISMRead this passage
A. RBP is Specifically Designed as a One-Time Mechanism
printed heading
United nonetheless requests assurance that steps will be taken to ensure this characterization holds in practice, so that RBP does not become a recurring tool PJM invokes each time a future auction reveals a shortfall.Read this passage
B. RBP Must be Followed by a Commitment to Durable Reforms
printed heading · Topic match: Connecting load and generation
RBP Must be Followed by a Commitment to Durable Reforms RBP treats the symptom of PJM’s current resource adequacy gap rather than its cause.Read this passage Filed comments: Connecting load and generation
IV. RETAIL COST ALLOCATION - SUPPORTING STATE/LARGE LOAD
printed heading · Topic match: Cost allocation
As discussed above, PJM’s now-filed Interim Resource Adequacy Service proposal confirms that a Large Load’s Peak Shaving Adjustment, one of the concrete steps a load can take to manage its footprint and reduce its cost exposure, plays no role in reducing that load’s exposure to IRAS curtailment.57…Read this passage Filed comments: Cost allocation
V. CONCLUSION
printed heading · Topic match: Reliability and curtailment
United respectfully requests that the Commission direct PJM to address these issues on the timeline necessary to preserve the September 29, 2026, effective date PJM has requested, consistent with PJM’s own invitation for the Commission to modify or clarify specific provisions of its proposal.Read this passage Filed comments: Reliability and curtailment
CERTIFICATE OF SERVICE
printed heading
Dated this 21st day of August 2026. /s/ Mike HaughRead this passage