ER26-3380-000 · 2026-08-21 · North Carolina Electric Membership Corporation
Comments of North Carolina Electric Membership Corporation re PJM Interconnection, L.L.C.'s 07/31/2026 filing
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3380-000
COMMENTS OF NORTH CAROLINA ELECTRIC MEMBERSHIP
CORPORATION
Pursuant to Rules 211 and 212 of the Commission’s Rules of Practice and Procedure1 and the Commission’s Combined Notice of Filings #1 of August 3, 2026, North Carolina Electric Membership Corporation (“NCEMC”)2 submits the following comments on the filing by PJM Interconnection, L.L.C. (“PJM”) proposing revisions to its Open Access Transmission Tariff (“Tariff”) and Reliability Assurance Agreement Among Load Serving Entities (“RAA”) to establish a Reliability Backstop Procurement (“RBP Proposal”).3
PJM states that the RBP Proposal will be a one-time procurement of new capacity resources intended to address previously identified resource adequacy challenges that have arisen as a result of insufficient capacity commitments in the 2027/2028 and 2028/2029 Reliability Pricing Model (“RPM”) Capacity Market Auctions. NCEMC shares the reliability concern that PJM is attempting to address; however, PJM’s proposed fix gives rise to a key cost-allocation concern
1 18 C.F.R. § 385.211 & .212 (2025).2 NCEMC filed a (doc-less) motion to intervene in this proceeding on August 12, 2026.3 PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026).
PDF page 2
2
articulated in the Protest of East Kentucky Power Cooperative, Inc. (“EKPC”) being filed in this proceeding today (“EKPC Protest”).
I. NCEMC
NCEMC is a generation and transmission cooperative responsible for the full or partial power supply requirements of its 25 members throughout the state of North Carolina. Those 25 distribution cooperatives, in turn, supply electricity to approximately one million homes, farms, and businesses in which more than 2.5 million North Carolinians live and work. NCEMC distribution cooperative loads are located throughout the service areas of three investor-owned public utilities: Duke Energy Carolinas, LLC, and Duke Energy Progress, LLC, both subsidiaries of Duke Energy Corporation, and Virginia Electric and Power Company, doing business as Dominion Energy Virginia in Virginia and as Dominion Energy North Carolina in North Carolina (hereinafter, Dominion).
NCEMC is a member of PJM, which operates transmission facilities owned by Dominion and other electric utilities. NCEMC purchases transmission services from PJM over Dominion’s transmission facilities to serve the loads of its six member cooperatives that distribute power at retail in the Dominion transmission zone of the PJM region. NCEMC is a member of PJM’s Electric Distributor sector, a load-serving entity, and a participant in PJM’s energy, ancillary services, capacity, and financial transmission rights markets.
PDF page 3
3
II. The RBP Proposal Allocates Costs to Non-Cost-Causers, including NCEMC and its Member Cooperatives.
NCEMC shares EKPC’s concern that “[t]he PJM RBP Proposal does not adequately define who is responsible for the charges (which affects how much of the zone/area assigned costs any individual LSE [Load-Serving Entity] may receive) or how the charges are tied to incremental cost causation.” EKPC Protest at 19. EKPC points out that “PJM has failed to provide ‘clear and transparent procedures’ to allow an LSE to determine the amount of costs it may be allocated under the PJM RBP Proposal.” Id. at 17 (citation omitted). EKPC explains the uncertain cost allocation that LSEs face:
Most concerning, PJM’s proposal for a default
allocation methodology, should the Electric Distributor
not report an RBO [“RBP Obligation”], is that all
LSEs in the zone/area will be held accountable to pay
the costs PJM assigns to the zone/area, regardless of
whether they serve any large load or contributed to the
need for backstop procurement. The uncertainty of
being assigned costs, as well as the magnitude of the
costs that may be assigned, should the large loads not
materialize in each zone/area as PJM anticipated in
establishing the procurement target, will itself impact
whether large loads materialize as forecasted. It is
nearly impossible for an LSE, based on the
information available to it in PJM’s RBP Proposal, to
determine the amount of costs it may be allocated.
Id. at 17–18 (citation omitted).
PDF page 4
4
PJM could and should clearly identify entities which will not bear costs under the RBP Proposal.4 With regard to NCEMC, PJM has not done so. EKPC provided the following helpful example:
It is also unclear whether PJM is properly using the
information from Table B9b from the 2026 PJM Load
Forecast to ensure Electric Distributor zone/areas
receive correct allocations from PJM. For example,
[NCEMC] is located in the Dominion Energy zone.
But, the NCEMC area is not currently reflected as “0”
in PJM’s Initial Allocation to Electric Distributor
zone/area table. Therefore, as initially presented by
PJM, NCEMC could be subject to some kind of cost
allocation if the cross-state cost allocation is not
appropriately determined.
Id. at 20 (citation omitted).
PJM should be required to clearly identify entities which will not bear costs under the RBP Proposal’s primary cost-allocation methodology as well as under its alternative “default methodology.” EKPC’s Protest explains the deficiency of PJM’s proposed default methodology:
PJM’s proposal to use a default allocation based on
Daily Unforced Capacity Obligation if the more
targeted allocation process does not produce an LSE-
specific result is also unjust and unreasonable. When a
state or RERRA [Relevant Electric Retail Regulatory
Authority] has not determined an RBO for LSEs
within a zone/area, PJM defaults to allocating costs
based on each LSE’s Daily Unforced Capacity
Obligation ratio share. This backup methodology
socializes RBP costs across all load within the zone—
4 Indeed, as EKPC points out, if PJM had designed its proposal to align with the only stakeholder proposal to receive the required two-thirds sector-weighted member support, PJM would not have proposed “a mandatory procurement, especially one that did not identify or track with specificity who would bear the costs of, or who receives the RBP MW credit resulting from, the procurement.” EKPC Protest at 9.
PDF page 5
5
including LSEs serving customer bases that
contributed nothing to the capacity shortfall.
Id.
III. Conclusion
PJM’s proposal does not adequately address the cost-allocation concerns set forth above and is not just and reasonable. Based on this particular ratepayer- protection issue, NCEMC supports the relief requested in the EKPC Protest. August 21, 2026
Respectfully submitted,
/s/ Michael D. Youth
Charles Bayless
Senior Vice President and General
Counsel
Michael D. Youth
Vice President and Deputy General
Counsel
North Carolina Electric Membership
Corporation
3400 Sumner Blvd.
Raleigh, NC 27616
Charlie.Bayless@ncemcs.com
Michael.Youth@ncemcs.com
Sean T. Beeny
F. Alvin Taylor
Randolph L. Elliott
McCarter & English, LLP
1301 K Street NW, Suite 1000 West
Washington, D.C. 20005
(202) 753-3400
sbeeny@mccarter.com
ataylor@mccarter.com
relliott@mccarter.com
Attorneys for North Carolina Electric
Membership Corporation
PDF page 6
6
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. this 21st day of August, 2026.
/s/ Randolph Elliott
Randolph L. Elliott
McCarter & English, LLP
1301 K Street NW, Suite 1000 West
Washington, D.C. 20005
(202) 753-3428