Comments of North Carolina Electric Membership Corporation re PJM Interconnection, L.L.C.'s 07/31/2026 filing
Text extracted from the eLibrary original (SHA-256 760a118a2d290fd4…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment · Credit and exit
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
ER26-3380-000, “Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads” (filed July 31, 2026). 2 articulated in the Protest of East Kentucky Power Cooperative, Inc. (“EKPC”) being filed in this proceeding today (“EKPC Protest”).Read this passage Filed comments: Reliability and curtailment
I. NCEMC
printed heading
NCEMC NCEMC is a generation and transmission cooperative responsible for the full or partial power supply requirements of its 25 members throughout the state of North Carolina.Read this passage
II. The RBP Proposal Allocates Costs to Non-Cost-Causers, including
printed heading · Topic match: Cost allocation
Therefore, as initially presented by PJM, NCEMC could be subject to some kind of cost allocation if the cross-state cost allocation is not appropriately determined.Read this passage Filed comments: Cost allocation
III. Conclusion
printed heading · Topic match: Cost allocation
Based on this particular ratepayer- protection issue, NCEMC supports the relief requested in the EKPC Protest.Read this passage Filed comments: Cost allocation
F. Alvin Taylor
printed heading
Elliott McCarter & English, LLP 1301 K Street NW, Suite 1000 West Washington, D.C. 20005 (202) 753-3400 sbeeny@mccarter.com ataylor@mccarter.com relliott@mccarter.com Attorneys for North Carolina Electric Membership Corporation 6Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 21st day of August, 2026. /s/ Randolph Elliott Randolph L.Read this passage