ER26-3380-000 · 2026-08-21 · Google LLC

Comments of Google LLC re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement Proposal

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
)
)
)
Docket No. ER26-3380-000
COMMENTS OF GOOGLE LLC
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission (“Commission”),1 Google LLC (“Google”) hereby submits these
comments regarding PJM Interconnection, L.L.C.’s (“PJM”) Reliability Backstop Procurement (“RBP”) Proposal.  Google commends PJM for taking steps to ensure reliability, which must remain its first priority.  Nevertheless, while RBP may help maintain near-term resource adequacy, Google urges PJM to focus future efforts on reforms that incentivize new large loads to procure and bring their own new generation rather than relying on an interim, one-time solicitation, like RBP.  As explained below, Google believes that this bilateral contracting will do more to procure the necessary supply—after all, there is no guarantee that RBP will procure enough GW to cover the shortfall2—and do so in a way that meets future demand on a durable, forward-looking basis, rather than relying on measures that address only previously identified reliability needs.  A bilateral approach also does more to ensure the new supply meets the needs and preferences of new large load customers, unlocking the economic growth benefits that they can provide.  And it’s not just

1 18 C.F.R. § 385.211 (2026). 2 See PJM Interconnection, L.L.C., Transmittal, Docket No. ER26-3380-000, at 26 (filed Jul. 31, 2026) (“Transmittal”) (framing the RBP as a design intent rather than a guarantee); id. at 34 (recognizing that “the RBP aims to procure RBP Resources for up to a 15-year fixed term.” (emphasis added)); id. at 79 (acknowledging that the RBP may “clear short of the Final RBP Target”); id. at 125 (“resetting the [RBA] to the 2032/2033 Delivery Year recognizes that, even if the RBP successfully procures sufficient capacity to cover the shortfall, RBP Resource will need time to become operational.”).

PDF page 2

-2-
Google that sees the promise of new large loads bilaterally contracting for new generation.  During the RBP stakeholder process, in response to a Request for Information released by PJM, a “[m]ajority of parties expressed interest and preference to a bilateral contract over a central procurement.”3  Respondents to the Request for Information spanned the large load, supply, and utilities sectors.4

I. WHO WE ARE
Google’s mission is to organize the world’s information and make it universally accessible and useful.  AI is critical to that mission.  Data centers necessary to serve Google’s customers consume a large amount of electricity and require reliable electric service to operate.  As Google’s business grows, so too does its demand for reliable, affordable, and clean electricity.

II. COMMENTS
Google recognizes that the unprecedented load growth that PJM is currently experiencing is both a tremendous opportunity and a complex challenge.  The load growth reflects the dynamism of the nation’s technology sector, which can drive economic growth, create jobs, and significantly expand the tax base of the areas in which that growth occurs.  Those are real, verifiable benefits that accrue across the local, state, and national levels, and should be available to the communities that want to host the necessary digital and energy infrastructure. But those economic benefits must not come at the cost of sacrificing the reliability and affordability to which customers in those communities, and PJM more broadly, are rightly accustomed.  RBP may help protect against that result in the short term by procuring additional

3 PJM Interconnection, L.L.C., Reliability Backstop Procurement Design, at 3 (May 27, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-05---reliability- backstop-procurement-design---pjm-presentation---updated.pdf.
4 See Charles River Associates, PJM Reliability Backstop RFI Summary, at 3 (May 27, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-informational-only-- -reliability-backstop-rfi-summary---charles-river-associates.pdf.

PDF page 3

-3-
generation to ensure reliability and allocating the costs of that additional generation to the entities that caused the need for it, namely the new large loads that have not secured sufficient capacity to offset their demand.  Anything else would be unjust and unreasonable and manifestly contrary to the principles that Google has consistently supported through its Capacity Commitment Framework (“CCF”), as well as the White House’s Ratepayer Protection Pledge and the Statement of Principles from the National Energy Dominance Council and the PJM Governors.5  But the Commission alone cannot ensure that result, as PJM itself acknowledged in a letter to the region’s governors in May.  The retail level is where the rubber meets the road. Indeed, as PJM stated, “if states have not established frameworks to appropriately allocate costs to new data center loads, it is unclear to which customers those costs would be assigned,” and “it appears possible to PJM that these costs will be allocated to other consumers.”6  To date, not all PJM states have taken comprehensive steps to establish and implement these contemplated frameworks across PJM’s diverse footprint.  If RBP is accepted, the states must take up the mantle and ensure that the costs of RBP are allocated in a manner that is just and reasonable and consistent with the Ratepayer Protection Pledge.  Google stands ready to engage in that process to achieve that result.

And while RBP may be a reasonable response to PJM’s current circumstances, a more permanent, long-term framework is necessary.  Constantly shifting, unpredictable regulatory constructs undermine the investor confidence necessary to support the multi-billion-dollar investments in new capacity needed to ensure reliability and affordability over the long term.

5 Google, LLC, The Capacity Commitment Framework, https://www.gstatic.com/marketing- cms/44/6b/dbb3456040b486886bb8aff87588/the-capacity-commitment-framework-ccf-jan.pdf.
6 Letter from David E. Mills, President and CEO, PJM to Governors of PJM States, PJM Interconnection, L.L.C. (May 5, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260520-pjm-board-letter-to-several-govs-re-reliability-backstop-procurement.pdf.

PDF page 4

-4-
That is particularly true for regulatory changes that call into question or cast doubt upon contracts, such as firm electric service agreements or bilateral contracts between generation and load, which were entered into in reliance on the rules in effect at the time of execution.  Rather than accepting constant change and uncertainty, the Commission, PJM, and all stakeholders should focus on developing the stable, predictable investment conditions that will facilitate the investments needed to extricate PJM from its present resource adequacy shortfall and maintain resource adequacy in the long-term.

Finally, Google also believes strongly that new capacity requires corresponding investments in the transmission infrastructure necessary to ensure that that capacity can be interconnected promptly and used to serve load reliably.  Google has been transparent with utility partners about its plans for demand growth across PJM for years, including by signing long-term contracts with utilities that provide clear growth projections and associated ramp rates. Yet the development of the energy infrastructure needed to accommodate that load growth and the corresponding new capacity needed to protect other ratepayers has lagged badly behind. While Google is prepared to bear the costs appropriately attributable to its growth, Google is not in a position to develop that transmission infrastructure unilaterally.  Accordingly, Google urges PJM not to lose sight of the need to proactively develop the transmission infrastructure that is critical to maintaining reliability and affordability.

1. A Viable Long-Term Solution to PJM’s Capacity Shortfall is a Bring Your Own New Capacity Framework that Protects Existing Ratepayers from Cost Shifts and

Stranded Asset Risk
Google has long advocated for the principle that new large loads should pay for the costs associated with the increase in demand that they are driving and the strain that puts on existing

PDF page 5

-5-
infrastructure.  The CCF that Google has advocated for at the state level7 and the “Bring Your Own New Capacity” (“BYONC”) framework that Google has advocated for at the federal level both reflect that principle.

At the federal level, Google has consistently argued that new large loads must bring their own new generation to support the demands they place on existing electrical infrastructure, where existing structures, like the Reliability Pricing Model (“RPM”), have not secured adequate new supply.8  Although not a silver bullet, requiring new large loads that interconnect to the grid to secure their own capacity is the single most important mechanism for shielding existing customers from adverse rate impacts of those new large loads.  Indeed, from the outset of PJM’s first Critical Issue Fast Path (“CIFP”) focused on large load issues, Google has supported this concept, including through a BYONC framework with an accelerated pathway for new generation and new load to interconnect to the transmission system.9

BYONC is the centerpiece of Google’s own procurement philosophy.  Google strives to serve every new MW of data center load with a new MW of capacity in the same balancing authority, ensuring that its new large loads do not draw down on the reserve margin financed by existing customers.10  This approach enables Google to choose the right size and mix of capacity assets to meet its needs, which can include demand-side resources that PJM’s existing rules do

7 See Amanda Peterson Corio, Supporting the White House Ratepayer Protection Pledge: Google's Approach for Responsible Energy Growth, Google Blog (Mar. 4, 2026), https://blog.google/innovation-and-ai/infrastructure- and-cloud/global-network/affordability-pledge-responsible-energy-growth/.
8 See Comments of Google, LLC, Docket No. RM26-4 (filed Nov. 21, 2025) (“Google ANOPR Comments”).
9 Letter of Brian George, Sr. Lead of U.S. Energy Mkts, Google, LLC (Aug. 27, 2025), at 6 (“Google CIFP Letter”).
10 Google CIFP Letter at 2 & n. 10.

PDF page 6

-6-
not accommodate.11  Google’s agreements with Voltus to unlock up to 100 MW of capacity from distributed energy resources in PJM12 and with Indiana Michigan Power (I&M) to leverage demand response to reduce I&M’s peak load13 are examples of the type of innovative solutions to the capacity shortfall that BYONC enables. In addition, as a customer-driven approach, BYONC allows Google and other data center developers to invest in capacity solutions that can scale to meet projected growth, which provides a forward-looking and more durable means to protect customers from the demand-driven effects of new large loads than backward-looking measures like RBP.  In short, a BYONC framework can unlock more capacity and do so in advance of the identified reliability needs—a result that is better for all PJM customers. The BYONC framework is also consistent with the White House’s Ratepayer Protection Pledge, under which companies including Google have committed to build, bring, or buy the new generation and electricity needed to meet their new demand and to pay for it whether or not they ultimately use it, and the Statement of Principles from the National Energy Dominance Council and the PJM Governors.14

On the state level, Google’s CCF is built on five key pillars that complement a BYONC approach:

11 PJM’s existing demand response rules require unlimited availability, needlessly prohibiting demand response capacity from participating in the market. Given the shortfall PJM faces, it should accommodate any and all MWs that a capacity resource or market participant can physically supply. 12 See Michael Terrell, We’ve signed a first-of-its-kind agreement with Voltus to create a smart capacity solution for the grid, Google Blog (Jun. 2, 2026), https://blog.google/company-news/outreach-and- initiatives/sustainability/voltus-agreement/.
13 See Michael Terrell, How we’re making data centers more flexible to benefit power grids, Google Blog (Aug. 4, 2025), https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/how-were-making-data- centers-more-flexible-to-benefit-power-grids/.
14Ratepayer
Protection
Pledge,
The
White
House
(Mar.
4,
2026),
https://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/
(“Ratepayer
Protection
Pledge”);
Statement
of
Principles
Regarding
PJM,
National
Energy
Dominance
Council
(Jan.
15,
2026),
https://www.energy.gov/documents/statement-principles-regarding-pjm (“NEDC/PJM Governors’ Principles”).

PDF page 7

-7-
1. Non-Discriminatory Applicability: Terms should apply to all new large loads with an expected peak demand above a certain threshold.  Regulators should avoid adoption of mandatory terms for specific end uses of

electricity.
2. Long-Term Commitment: New large loads should be required to sign a
long-term contract that ensures that the customer commits to providing
sufficient revenue to cover the investments made on their behalf.
Regulators should consider flexibility for customers to ramp into their load over time.

3. Significant Minimum Charges:  New large loads should be required to pay costs of power capacity (e.g., approximated via demand charges) at a

sufficient minimum to guard against potential cost shifting in the event that metered customer demand is significantly lower than planned for.

4. Upfront Collateral:  To ensure financial stability of the requesting customer, regulators should consider the appropriate role for upfront collateral to provide financial assurance to the utility that the long-term contract

minimums can be met.
5. Flexible and Transparent Fees for Modifications: To protect other
ratepayers, while also maintaining reasonable flexibility for new large
loads, regulators should consider appropriate notice periods and fees for contract cancellation or capacity reduction.

Google has worked with industry stakeholders to refine retail tariffs so that they incorporate and/or reflect the protections and principles of the CCF.  For example, Google collaborated with stakeholders representing diverse interests, including I&M, the Indiana Office of Utility Consumer Counselor, the Citizens Action Coalition, the Data Center Coalition, and other large load customers to reform I&M’s Industrial Power Tariff to protect existing retail customers from stranded asset risks.  The resulting tariff, which applies to 70-MW large loads at a single site, includes a 12-year minimum contract term, an 80 percent minimum monthly billing demand tied to the customer’s contract capacity, and exit fees.15  Google helped secure a

15 See Order of the Commission, Cause No. 46097, Ind. Util. Reg. Comm’n (issued Feb. 19, 2025).

PDF page 8

-8-
unanimous settlement,16 which illustrates that consumer protection and energy infrastructure development need not be at odds.  As of July 2026, the CCF has been adopted by 12 utilities in 11 states.

2. The Costs of the RBP Must Be Allocated in a Manner that Complies with Cost
Causation, the CCF, the Ratepayer Protection Pledge, and the Statement of
Principles from the NEDC and the PJM Governors
As noted above, Google recognizes that RBP may be a reasonable response to the current resource adequacy shortfall, but it should not become a permanent substitute for market-driven, long-term mechanisms that deliver resource adequacy at just and reasonable rates.  Indeed, Google is concerned that, as things stand, RBP could lead to the sort of cost shifting that Google has long advocated against and that would be inconsistent with both the Ratepayer Protection Pledge and the National Energy Dominance Council and PJM Governors’ Statement of Principles.17  Because not all states in PJM have separate mechanisms for allocating costs directly to large loads, there is no way to ensure that the costs of RBP can be allocated exclusively to those that have not already covered their load.  It should be incumbent on PJM to proactively coordinate with states to ensure that they have the retail mechanisms in place to properly allocate to new large loads the costs that RBP would impose.

To that end, Google applauds and supports the collaborative effort announced by the Virginia State Corporation Commission (“VA SCC”) and the Data Center Coalition (“DCC”) to develop model state tariff provisions addressing the retail allocation of RBP costs, among other necessary criteria (e.g., geographic matching of load and supply).  Such provisions are designed to assign RBP costs to the large load customers whose demand causes the need for those

16 See Ind. Mich. Power Co., Cause No. 46097, Settlement Testimony of Justin B. Farr, at 2-5 (filed December 4, 2024) (“Farr Settlement Testimony”).
17 Ratepayer Protection Pledge; NEDC/PJM Governors’ Principles at 1.

PDF page 9

-9-
procurements.  That is a necessary step to protect residential and existing commercial and industrial customers from cost shifts.18  Google is committed to participating in that effort and doing everything it reasonably can to help ensure adequate protections are in place, building on our proven track record of advancing responsible grid solutions.  In addition, given the importance of those efforts and the States’ exclusive authority over the retail cost allocation mechanisms, Google urges PJM to be prepared to accommodate the needs of the States, ensuring that they have the information that they need and the costs are allocated on timelines that consider and reflect state retail ratemaking processes.

3. PJM Must Make Progress to Address the Additional Factors Contributing to the Current Resource Adequacy Shortfall

Reforms that require new large loads to secure their own new capacity are a critical element of ensuring reliability and affordability.  Yet they are only part of the answer.  As Google has consistently maintained, one of the chief barriers to the integration of new large loads in a manner that does not undermine affordability and reliability are long interconnection timelines and the “[t]erawatts of new generation capacity [that] are stuck in interconnection queues because inadequate transmission infrastructure” renders interconnection too slow, too expensive, or both.19 New large loads cannot bring forth new capacity resources if those resources’ interconnection to the transmission system is stymied or delayed due to unpredictable—and often high—network upgrade costs or delays in identifying or developing that infrastructure.

18 Letter of Kelsey Bagot, Chair of Va. State Co. Comm’n and Josh Levi, President & Chief Exec. Off. of Data Ctr. Coal. (Jun. 30, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public- disclosures/2026/20260630-va-scc-and-data-center-coalition-letter-re-cifp-connect-manage-reliability-backstop- procurement.pdf (“VA SCC and DCC Letter”).
19 Google ANOPR Comments at 3.

PDF page 10

-10-
Further, PJM’s existing rules also unnecessarily limit the ability of new storage resources to use Surplus Interconnection Service (“SIS”) to provide additional capacity, even where Capacity Interconnection Rights (“CIRs”) at the same point of interconnection are underutilized.  Where storage is added to an existing inverter-based resource, PJM requires the resources to operate as a single hybrid resource for the storage to access those CIRs, which can significantly limit the commercial viability of the arrangement.20  And where storage is added to a non-inverter-based resource, such as a gas generator, PJM’s mixed-technology facility rules do not permit the storage resource to use those CIRs to increase the facility’s unforced capacity (“UCAP”) contribution at all.

These barriers could be addressed through a relatively straightforward rule change allowing an existing resource with underutilized CIRs to allocate a portion of those rights to a new resource interconnecting through SIS.  Because the surplus resource must be studied before receiving SIS, PJM can identify and impose any necessary restrictions through that process to address reliability, operational, or market-power concerns.  Such a reform could unlock significant amounts of additional capacity from storage using existing interconnection capability and allow that capacity to come online more quickly.

Google intends to work with PJM and its stakeholders to address these barriers promptly. Google is not asking the Commission to resolve these issues in this proceeding but respectfully requests that the Commission encourage PJM to pursue reforms that make more efficient use of existing interconnection capability as part of its ongoing efforts to address the region’s resource

20 See PJM Interconnection, L.L.C., Problem/Opportunity Statement: Hybrid Resources Market Model Selection (Aug. 5, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/committees/mic/2026/20260805/20260805-item-04-1---hybrid-resources-market-model-selection---problem- statement.pdf (storage resources cannot obtain capacity resource status through the surplus interconnection process unless it becomes a hybrid resource, which presents “potentially insurmountable challenge[s] . . . and limit[s] SIS as a pathway for PJM to obtain much-needed capacity that can come online more rapidly.”).

PDF page 11

-11-
adequacy challenges.  If these barriers cannot be addressed expeditiously through the stakeholder process, further Commission attention may be warranted.

Although Google recognizes the significant progress that PJM has made and continues to pursue on interconnection reform, these issues remain a major reason why, at the moment, supply is not keeping up with demand.  Resolving that imbalance also requires coordinated, holistic transmission planning processes that reflect the growing demands placed on the grid by both new demand and new supply.  Given the scale, pace, and volume of large load interconnection requests as well as the corresponding scale, pace, and volume of new generator interconnection requests— both of which contribute significantly to the need for new transmission infrastructure— transmission planners must have a realistic picture of the generators and large loads planning to interconnect to the transmission grid so that they can develop the transmission system that accommodates both sides of the supply and demand equation.  Only then will PJM have the infrastructure foundation needed to maintain resource adequacy at just and reasonable rates and capitalize on the economic opportunity that load growth presents without succumbing to its challenges.

III. CONCLUSION
PJM is right to focus on ensuring reliability and affordability.  However, a more enduring structural approach is preferable to perpetual reliance on RBP or similar stopgap mechanisms. BYONC frameworks can unlock more capacity, do so in advance of the relevant reliability needs, and automatically ensure that the costs of new demand are borne by the entities that cause those costs.  That is a much better result for PJM and all its stakeholders.  Accordingly, BYONC should form the foundation for future PJM and Commission efforts to address the demand-driven effects of new large loads.

PDF page 12

-12-
Respectfully submitted,
/s/ Brian George
Brian George
Sr. Lead, US Energy Markets
Elizabeth Savage
Strategic Negotiator
Google LLC
655 New York Ave., NW
Washington, DC 20001
(202) 999-0990
briangeorge@google.com
eomsavage@google.com
 /s/ Matthew Christiansen
Matthew Christiansen
Bryan Shpall
Rachel Neuburger
Jenae Sharp
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
mchristiansen@wsgr.com
bshpall@wsgr.com
rneuburger@wsgr.com
jmsharp@wsgr.com
Counsel for Google LLC
Dated:  August 21, 2026

PDF page 13

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.

Dated:  August 21, 2026
San Francisco, CA
/s/ Jenae Sharp
Jenae Sharp
Wilson Sonsini Goodrich & Rosati
One Market Plaza,
Spear Tower #3300
San Francisco, CA 94105