Comments of Google LLC re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement Proposal
Text extracted from the eLibrary original (SHA-256 c7048f2a68af2b12…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in ER26-3380
Topics in the text: Cost allocation · Reliability and curtailment · Credit and exit
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
Google commends PJM for taking steps to ensure reliability, which must remain its first priority.Read this passage Filed comments: Reliability and curtailment
I. WHO WE ARE
printed heading
WHO WE ARE Google’s mission is to organize the world’s information and make it universally accessible and useful.Read this passage
II. COMMENTS
printed heading · Topic match: Cost allocation
The Costs of the RBP Must Be Allocated in a Manner that Complies with Cost Causation, the CCF, the Ratepayer Protection Pledge, and the Statement of Principles from the NEDC and the PJM Governors As noted above, Google recognizes that RBP may be a reasonable response to the current resource…Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading
CONCLUSION PJM is right to focus on ensuring reliability and affordability.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated: August 21, 2026 San Francisco, CA /s/ Jenae Sharp Jenae Sharp Wilson Sonsini Goodrich & Rosati One Market Plaza, Spear Tower #3300 San Francisco, CA 94105Read this passage