ER26-3380-000 · 2026-08-20 · Individual No Affiliation

Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers re PJM Interconnection, L.L.C.’s 07/31/2026…

Text extracted from the eLibrary original (SHA-256 371dad7c1b1c4fd2…). Download the original from the official source.

Contents · 15 sections
  1. I. PRELIMINARY STATEMENT p. 1
  2. II. MOTION TO INTERVENE p. 3
  3. A. Identity of Movants p. 3
  4. B. Movants' Interest p. 4
  5. III. BACKGROUND p. 6
  6. A. The RBP Filing p. 6
  7. B. PJM's independent evaluation of that model p. 7
  8. C. PJM's own sensitivity analyses p. 9
  9. D. What the RBP Filing says about any of this p. 10
  10. IV. THE COMMISSION SHOULD NOT FIND THE PROCUREMENT p. 11
  11. V. PJM SIMULTANEOUSLY PROPOSES TO DEFER THE TARIFF'S OWN p. 13
  12. VII. COST ALLOCATION: THE PROPOSAL RESTS ON STATE ACTION p. 16
  13. VIII. REQUESTED RELIEF p. 17
  14. IX. COMMUNICATIONS p. 19
  15. X. CONCLUSION p. 19

Read topic-matched comments in ER26-3380

Topics in the text: Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

ER26-3380-000 MOTION TO INTERVENE AND PROTEST OF NICHOLAS MAX NEAL AND DAVID NEAL, DELAWARE STANDARD OFFER SERVICE RATEPAYERS Pursuant to Rules 211 and 214 of the Commission's Rules of Practice and Procedure, 18 C.F.R. §§ 385.211, 385.214, and the Commission's notice of August 6, 2026, Nicholas Max…
Read this passage Filed comments: Cost allocation

I. PRELIMINARY STATEMENT

printed heading · Topic match: Reliability and curtailment

PJM asks the Commission to authorize a novel, one-time procurement of capacity commitments of up to fifteen years, extending through the 2042/2043 Delivery Year, in a quantity defined by the output of PJM's ELCC/Reserve Requirement Study model.
Read this passage Filed comments: Reliability and curtailment

II. MOTION TO INTERVENE

printed heading

II.
Read this passage

A. Identity of Movants

printed heading

The Customer is a retail electric customer of Delmarva Power & Light Company ("DPL"), taking service in the State of Delaware within the DPL transmission zone of the PJM Region under DPL Service Classification MGS-S (Medium General Service — Secondary).
Read this passage

B. Movants' Interest

printed heading · Topic match: Cost allocation

Movants do not assert that they will be directly assessed RBP Charges.
Read this passage Filed comments: Cost allocation

III. BACKGROUND

printed heading

III.
Read this passage

A. The RBP Filing

printed heading · Topic match: Reliability and curtailment

PJM proposes a one-time procurement of new capacity, with commitments "for a fixed term of up to 15 years, starting with the 2028/2029 Delivery Year and ending with the 2042/2043 Delivery Year." 19.
Read this passage Filed comments: Reliability and curtailment

B. PJM's independent evaluation of that model

printed heading

Movants disclose, as they must, E3's overall qualification: "E3 does not view implementation of any of these considerations as strictly necessary for the continued use of the current model in the administration of the capacity market.
Read this passage

C. PJM's own sensitivity analyses

printed heading

Movants bring them to the Commission's attention because, taken together, they demonstrate that the Reliability Requirement — and therefore the RBP Target — is materially sensitive to modeling choices that PJM's own consultant has identified as unresolved, in amounts of the same order of magnitude…
Read this passage

D. What the RBP Filing says about any of this

printed heading

Movants have searched the complete filing, including its attachments and testimony.
Read this passage

IV. THE COMMISSION SHOULD NOT FIND THE PROCUREMENT

printed heading · Topic match: Cost allocation

If the Initial RBP Target is materially overstated because of a modeling question that PJM's consultant identified in December 2025 and PJM resolves in 2027 or 2028, customers in the zones allocated RBP Charges will nonetheless pay for the resulting commitments for as long as fifteen years — and…
Read this passage Filed comments: Cost allocation

V. PJM SIMULTANEOUSLY PROPOSES TO DEFER THE TARIFF'S OWN

printed heading · Topic match: Reliability and curtailment

PJM SIMULTANEOUSLY PROPOSES TO DEFER THE TARIFF'S OWN MANDATED INVESTIGATION OF THE SHORTFALL'S CAUSES 42.
Read this passage Filed comments: Reliability and curtailment

VII. COST ALLOCATION: THE PROPOSAL RESTS ON STATE ACTION

printed heading · Topic match: Cost allocation

PJM proposes to allocate the Final RBP Target first to Electric Distributor zones by forecasted load growth, and then to Load Serving Entities in a manner that "permits states to determine the appropriate allocation of RBP UCAP MW to specific LSEs and/or end-use customers, thus allowing Relevant…
Read this passage Filed comments: Cost allocation

VIII. REQUESTED RELIEF

printed heading · Topic match: Cost allocation

Movants respectfully request that the Commission: (a) grant this motion to intervene and accord each Movant party status; (b) direct PJM to address on the record in this proceeding the E3 PJM ELCC / RRS Model Evaluation (December 2025) (Attachment A hereto) and PJM's ELCC Senior Task Force…
Read this passage Filed comments: Cost allocation

IX. COMMUNICATIONS

printed heading

Communications regarding this proceeding should be addressed to: Nicholas Max Neal 111 Centrenest Lane Wilmington, Delaware 19807 Telephone: (845) 263-0012 Email: max@nicholasneal.com David Neal 111 Centrenest Lane Wilmington, Delaware 19807 Telephone: (646) 509-3146 Email: shaun@shaunneal.com
Read this passage

X. CONCLUSION

printed heading

PJM asks the Commission to authorize commitments of up to fifteen years, in a quantity set by a model, without telling the Commission what its own consultant said about that model or what its own sensitivity analyses showed — while proposing to defer, until 2032/2033, the investigation of the…
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Wilmington, Delaware, this 20th day of August, 2026. /s/ David Neal _______________________________ David Neal