ER26-3380-000 · 2026-08-20 · Individual No Affiliation
Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers re PJM Interconnection, L.L.C.’s 07/31/2026…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-3380-000
MOTION TO INTERVENE AND PROTEST OF NICHOLAS MAX NEAL AND
DAVID NEAL, DELAWARE STANDARD OFFER SERVICE RATEPAYERS
Pursuant to Rules 211 and 214 of the Commission's Rules of Practice and Procedure, 18 C.F.R. §§ 385.211, 385.214, and the Commission's notice of August 6, 2026, Nicholas Max Neal ("the Customer") and David Neal ("Mr. Neal") (together, "Movants") respectfully move to intervene in the above-captioned proceeding and protest, in part, the July 31, 2026 filing of PJM Interconnection, L.L.C. ("PJM") in Docket No. ER26-3380-000 (Accession No. 20260731-5214) (the "RBP Filing").
I. PRELIMINARY STATEMENT
1. Movants do not ask the Commission to reject the RBP Filing. Movants do not allege that PJM has acted in bad faith. Movants do not contend that the Reliability Backstop Procurement ("RBP") is unnecessary, or that PJM's resource adequacy concerns are unfounded.
2. Movants' objection is narrow. PJM asks the Commission to authorize a novel, one-time procurement of capacity commitments of up to fifteen years, extending through the 2042/2043 Delivery Year, in a quantity defined by the output of PJM's ELCC/Reserve Requirement Study model. Yet the RBP Filing does not disclose to the Commission the independent evaluation of that model which PJM itself commissioned and received in December 2025, nor PJM's own
PDF page 2
published sensitivity analyses quantifying how far the model's output moves when identified modeling questions are resolved one way or another.
3. Those analyses are material because they move the answer in both directions, and by amounts that are not small relative to the procurement PJM proposes. Movants candidly disclose below that the single most-discussed correction — crediting increased thermal generating capability in cold weather — is, on PJM's own analysis, outweighed by a separate correction that increases the reserve requirement. That is precisely Movants' point. The relevant fact is not that PJM's number is too high. The relevant fact is that PJM's own work product shows the number to be materially unstable across unresolved modeling choices, and PJM proposes to commit customers to fifteen-year obligations sized by it without placing that instability before the Commission.
4. This concern is not hypothetical. In the 2024/2025 Base Residual Auction, PJM produced an erroneous Locational Deliverability Area Reliability Requirement for the DPL South Zone — a sub-area of Movants' own distribution zone. The consequence, after the auction was re-run, was an additional $182.8 million in cost for 1.9 percent more capacity. The resulting litigation — brought by, among others, the Delaware Public Service Commission and the Delaware Division of the Public Advocate — was remanded to this Commission by the United States Court of Appeals for the District of Columbia Circuit on January 13, 2026, and remains unresolved.
5. The relief Movants request is modest and lies comfortably within the Commission's authority. PJM has itself consented, "to facilitate Commission approval," to the Commission's exercise of authority to modify the proposed Tariff and RAA language under NRG Power
PDF page 3
Marketing, LLC v. FERC, where such modification is consistent with the filing's overarching objectives. RBP Filing, transmittal § V, at 130–31. Movants ask the Commission to condition acceptance on PJM demonstrating what the procurement target should be once the modeling questions identified by PJM's own consultant are applied — the substitution of a substantiated number for an unsubstantiated one, and nothing more.
II. MOTION TO INTERVENE
A. Identity of Movants
6. The Customer is a retail electric customer of Delmarva Power & Light Company ("DPL"), taking service in the State of Delaware within the DPL transmission zone of the PJM Region under DPL Service Classification MGS-S (Medium General Service — Secondary). The Customer has not selected a competitive electricity supplier and therefore receives Standard Offer Service ("SOS") from DPL. Under DPL's Delaware retail tariff, MGS-S constitutes its own Fixed Price SOS Customer Group. See DPL, P.S.C. Del. No. 8 — Electric, Rider "SOS" § A.
7. Mr. Neal was the DPL customer of record for the same premises, under the same Service Classification MGS-S and likewise taking Standard Offer Service, until approximately August 2025. Mr. Neal is presently obligated, under a written contract with the Customer, to reimburse the Customer for the electric charges billed at that premises. Mr. Neal therefore bears the economic burden of the Standard Offer Service charges that are the subject of this protest, notwithstanding that he is no longer the customer of record.
8. Movants appear on their own behalf and are not represented by counsel. Movants state these facts precisely because the accuracy of a party's asserted interest is the foundation of its right to be heard.
PDF page 4
B. Movants' Interest
9. Rule 214(b)(2) requires that a movant show that it "has or represents an interest which may be directly affected by the outcome of the proceeding," or that "the movant's participation is in the public interest." 18 C.F.R. § 385.214(b)(2)(ii), (iii). The Customer satisfies the former directly. Mr. Neal satisfies it by virtue of his contractual obligation to pay the charges at issue; in the alternative, his participation is in the public interest under Rule 214(b)(2)(iii), as the person who in fact bears the charges described below and as the former customer of record with direct knowledge of the premises' service history. Both Movants' participation is in the public interest: few, if any, end-use Delaware Standard Offer Service customers appear in the Commission's proceedings at all.
10. The Customer pays a stated, demand-denominated supply charge for capacity. DPL's MGS-S schedule states the Standard Offer Service supply charge as "Supply Capacity, Energy and Ancillary," billed at stated Demand Rates of $15.397739/kW and $9.413973/kW, together with stated energy rates. DPL's Rider "SOS" § B provides that the Standard Offer Service Rate "will include the costs for energy, capacity and ancillary services as reflected in the awarded electric supply prices for specific services in each year."
11. The mechanism by which PJM capacity prices enter that charge is documented by the Delaware Public Service Commission's own technical consultant. In its report on DPL's 2026 SOS procurement, Liberty Consulting Group explained that "[b]idders use $/MW-day capacity auction prices to create a capacity component (in $/MWh) of their SOS bid prices," and that "[l]ower load factor customer classes ... feel a greater impact from capacity prices than high load factor ... customers since they have fewer MWh over which to spread their demand-based capacity charges."
PDF page 5
12. The Customer's supply is procured and repriced annually. The Liberty report describes the two-year supply blocks used for the residential and small commercial procurement group and the single-year blocks used for the Customer's class. Movants note candidly that Liberty attributes the 2026 increase in MGS supply prices principally to energy rather than capacity — the capacity prices applicable to the single-year classes "remained almost unchanged" year over year. Movants accordingly claim no past capacity overcharge. Their concern is prospective: because the Customer's class reprices every year, each successive Base Residual Auction — and any change in PJM's reliability requirement or capacity market outcomes — is reflected in the wholesale supply prices bid to serve the Customer's class in the next annual procurement. The effect passes to Mr. Neal through the reimbursement obligation described in paragraph 7.
13. PJM's prior reliability-requirement error arose in Movants' own distribution zone. The coalition whose section 206 complaint the D.C. Circuit revived — including the Delaware Public Service Commission and the Delaware Division of the Public Advocate — is described by that court as "the DPL Customers." Movants take and pay for service in the DPL zone; their premises lies outside the DPL South sub-zone in which that error's direct price effects fell, and they cite the episode for the narrower propositions stated in Part IV below.
14. Movants do not assert that they will be directly assessed RBP Charges. As discussed in Part VII below, PJM's illustrative allocation does not assign RBP UCAP MW to the DPL zone, and PJM's 2026 Load Forecast Table B9b shows no load adjustment for that zone. Movants' interest arises from the effect of the reliability model, and of this proceeding's disposition of it, on the capacity costs embedded in the wholesale supply prices that set the
PDF page 6
Customer's Standard Offer Service rate, and from the matters raised in Part VII concerning the durability of cost allocation over a fifteen-year term.
15. Whether or not Delaware's state agencies participate in this docket, no other party represents Movants' particular interest as end-use Standard Offer Service customers who bear the charges described above. Movants' participation will not disrupt this proceeding, will not delay it, and imposes no burden on any party.
16. Movants accordingly request that the Commission grant this motion and accord each of them party status.
III. BACKGROUND
A. The RBP Filing
17. On July 31, 2026, PJM submitted a filing under section 205 of the Federal Power Act captioned Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, requesting an effective date of September 29, 2026.
18. PJM proposes a one-time procurement of new capacity, with commitments "for a fixed term of up to 15 years, starting with the 2028/2029 Delivery Year and ending with the 2042/2043 Delivery Year."
19. PJM proposes to procure a quantity equal to the "Final RBP Target," which "will initially be based on the observed MW UCAP shortfall in the BRA for PJM's 2028/2029 Delivery Year, i.e., the Initial RBP Target." The Final RBP Target is derived from the Initial RBP Target by subtracting verified Qualifying RBP Offset UCAP MW and specified opt-outs. RBP Filing, transmittal at 31–33; proposed Tariff, Attachment DD, §§ 18.1, 18.2.
PDF page 7
20. The Initial RBP Target is 6,831.3 MW. That figure is the amount by which the 2028/2029 Base Residual Auction cleared short of the PJM Region Reliability Requirement — defined in PJM's Tariff as the Forecast Pool Requirement multiplied by the Preliminary PJM Region Peak Load Forecast, less the Unforced Capacity Obligations of Fixed Resource Requirement Entities. The auction cleared at the market price cap of $325/MW-day. PJM states that the 2027/2028 Base Residual Auction likewise cleared 6,623 MW short, at a cap of $333.44/MW-day.
21. The procurement quantity is therefore not merely informed by PJM's reliability model. It is defined by it. The Forecast Pool Requirement and the Reliability Requirement are outputs of PJM's ELCC/Reserve Requirement Study model. On these facts — where both auctions cleared short at the administrative price cap — an error of X MW in the Reliability Requirement produces an error of approximately X MW in the Initial RBP Target, and a corresponding error in the quantity of fifteen-year commitments PJM would enter.
B. PJM's independent evaluation of that model
22. In December 2025, Energy and Environmental Economics, Inc. ("E3") delivered to PJM a report titled PJM ELCC / RRS Model Evaluation. E3 states that it "was retained by PJM to independently assess PJM's Effective Load Carrying Capability / Reserve Requirement Study Model ... for alignment with industry best practices in loss-of-load-probability ... modeling," and notes that "[t]he outputs of the ELCC/RRS model are used directly in PJM's capacity market." The report is provided as Attachment A hereto.
23. E3 identified fourteen "Considerations for Improvement," presented "[i]n order of approximate prioritization." Three are directly pertinent.
PDF page 8
24. Consideration 4 — "Use more temporal granularity to model capability and deliverability of unlimited resources." E3's evaluation states that this "[r]eflects resource capability changing with temperature conditions, increasing model accuracy," and assigns it an Impact Level of: "High impact. Approximately ~8 GW of additional unlimited resource capability in the winter months, ~1% IRM reduction." E3 records the implementation difficulty as "Low difficulty to implement a seasonal approach (which PJM has already done)."
25. Consideration 6 — "De-weight historical resource performance events as new resource performance events under similar weather conditions occur." E3 explains that "[t]he current PJM model methodology draws resource performance profiles from historical performance during the years 2012-2024," that "[a]ny resource performance day within that time period is selectable by the model with equal probability," and that consequently a resource "that performs poorly but implements weatherization, better fuel security, or other enhancements would still be modeled with its pre-enhancement performance."
26. Consideration 3 — "Update the scrambling process to draw resource performance from the same weather conditions used to synthesize load." E3 assigns this a "[m]odest to high impact on IRM and ELCC values as indicated by PJM sensitivity analysis," and notes "[l]ow implementation effort given that PJM has already built this functionality to test impacts as part of Package C."
27. Movants disclose, as they must, E3's overall qualification: "E3 does not view implementation of any of these considerations as strictly necessary for the continued use of the current model in the administration of the capacity market. Instead, they are intended to support continued improvement of PJM's reliability modeling framework over time."
PDF page 9
28. That qualification is important but it does not answer the question presented here. E3 was engaged to assess whether PJM's model remains fit for continued use in administering the capacity market — an annual, self-correcting process in which each Delivery Year's requirement is recalculated and each auction reprices. E3 was not asked, and did not opine, whether the model's output is a sufficient basis for a novel, one-time procurement of commitments extending fifteen years into the future, which by design cannot be recalculated annually. The distinction is the entire subject of this protest.
C. PJM's own sensitivity analyses
29. On May 22, 2025, PJM presented to the ELCC Senior Task Force a set of sensitivity analyses on the same model, provided as Attachment B hereto. PJM's results include the following, in PJM's own words:
Sensitivity
PJM's stated result
5. "WICAP" — reflect higher winter output
for unlimited resources
"Decrease in overall system risk (IRM drops
and system is less tight)"
4. "Align" — improve alignment of load
scenarios with temperature bins
"Significant increase in overall system risk
(IRM increases and system is tight)"
7. "WICAP & Align"
"Increase in overall system risk (IRM
increases and system is tighter)... Impact of
'Align' is stronger than impact of 'WICAP'"
8. "WICAP & NoPV1WSE"
"Decrease in overall system risk (IRM drops
and system is less tight)... Almost [all] of
LOLH is in the summer season"
30. PJM quantified the winter capability question directly. Comparing summer and winter ICAP for unlimited resources across nuclear, coal, gas combined cycle, gas combustion turbine, diesel, steam and other thermal classes, PJM's table shows 163,149 MW of summer ICAP against 171,710 MW of winter ICAP — a difference of 8,561 MW.
PDF page 10
31. PJM's own comparison of results states: "Removing PV1 and WSE forced outages eliminates the majority of winter risk (even when paired with the 'Align' sensitivity)," and that "[t]he 'Align' sensitivity increases winter risk and overall risk. However, this increase is mitigated when coupled with the 'WICAP' sensitivity."
32. Movants disclaim any suggestion that these sensitivities establish that PJM's reliability requirement is too high. PJM's Sensitivity 7 shows the opposite when two identified corrections are combined. Movants bring them to the Commission's attention because, taken together, they demonstrate that the Reliability Requirement — and therefore the RBP Target — is materially sensitive to modeling choices that PJM's own consultant has identified as unresolved, in amounts of the same order of magnitude as the 6,831.3 MW PJM proposes to procure for fifteen years.
D. What the RBP Filing says about any of this
33. The RBP Filing does not engage any of it. Movants have searched the complete filing, including its attachments and testimony. The filing refers to "ELCC" approximately 200 times, and refers to the "Installed Reserve Margin" in definitional tariff provisions and as an observed benchmark — the transmittal reports that both recent auctions "cleared 5.6% below the PJM Region Installed Reserve Margin of 20%." RBP Filing, transmittal at 124. It contains no reference to E3 or to Energy and Environmental Economics; no reference to "WICAP"; no reference to "winter capability"; and no reference to the "Reserve Requirement Study." Its seven references to "sensitivity" or "sensitivities" concern Optional Interconnection Studies and the calculation of RBP settlements, not reliability modeling. Nowhere does the filing address how the Reliability Requirement was derived, the independent evaluation PJM commissioned of the
PDF page 11
model that derives it, or PJM's own analyses of how far the derivation moves under identified corrections.
IV. THE COMMISSION SHOULD NOT FIND THE PROCUREMENT
QUANTITY JUST AND REASONABLE ON THIS RECORD
34. Under section 205, PJM bears the burden of showing that its proposal is just and reasonable. 16 U.S.C. § 824d(e). Where the central quantitative term of a proposal — here, how much capacity to buy, and for how long — is the output of a model, PJM's burden includes some demonstration that the output is a reasonable basis for the commitment proposed.
35. PJM has not made that demonstration. It has described the shortfall as an observed auction outcome, which it is, without addressing the fact that the outcome is measured against a modeled requirement whose known sensitivities PJM has studied and not disclosed here.
36. The fifteen-year term is what makes this dispositive. In the ordinary Base Residual Auction, an error in the reliability requirement is bounded: the Delivery Year ends, the model is re-run, and the market reprices. PJM's own conduct illustrates the point — PJM revised its peak load forecast for 2030 downward by 875 MW in its 2026 Long-Term Load Forecast "due to forecasting improvements." PJM corrects its inputs when its methods improve, and customers receive the benefit at the next auction.
37. The RBP has no such self-correction. Commitments run to the 2042/2043 Delivery Year. If the Initial RBP Target is materially overstated because of a modeling question that PJM's consultant identified in December 2025 and PJM resolves in 2027 or 2028, customers in the zones allocated RBP Charges will nonetheless pay for the resulting commitments for as long as fifteen years — and every customer in the PJM Region, Movants included, will continue to
PDF page 12
bear the effects of the modeled requirement through each annual auction and the supply prices built upon it. The asymmetry between a correctable annual process and an uncorrectable long- term commitment is the reason the modeling record should be before the Commission now.
38. That asymmetry is not theoretical. In the 2024/2025 Base Residual Auction, PJM's LDA Reliability Requirement for the DPL South Zone — a Locational Deliverability Area within Movants' distribution zone — rested on the assumption that certain suppliers would bid; they did not, and the requirement was not corrected. On re-run, the auction cleared at the price cap and PJM procured 1.9 percent more capacity at an additional cost of $182.8 million. See Md. Office of People's Counsel v. FERC, No. 24-1353 (D.C. Cir. Jan. 13, 2026), granting pet. for review of PJM Load Parties v. PJM Interconnection, LLC, 189 FERC ¶ 61,199 (2024). The Delaware Public Service Commission and the Delaware Division of the Public Advocate were among the complainants. The matter is on remand and unresolved.
39. Movants do not contend that the DPL South episode governs this proceeding, and recognize that the D.C. Circuit expressly declined to hold that any refund is due. Movants cite it for a narrower proposition: PJM's reliability requirement calculations have previously proved materially erroneous, at substantial cost, in a sub-zone of Movants' own distribution zone, and the Commission has recent and direct experience of how difficult such an error is to remedy after the fact. The prudent course is verification before commitment, not litigation afterward.
40. The Independent Market Monitor's findings reinforce the need for verification. In its analysis of the 2027/2028 Base Residual Auction — the first of the two shortfall auctions PJM invokes — the Monitor concluded that the auction's results "were not competitive as a result of the inclusion of large new data center loads in the load forecast, the lack of a queue for the
PDF page 13
addition of large new data center loads, the performance assessment interval (PAI) penalties that are part of the CP design, PJM's ELCC approach, the definition of market seller offer caps, the failure to extend the RPM must offer requirement to demand resources, and the product definition and lack of market power mitigation for demand resources." Monitoring Analytics, Analysis of the 2027/2028 RPM Base Residual Auction, Part B, at 2 (July 9, 2026). The Monitor further concluded that "[t]he BRA prices do not reflect supply and demand fundamentals but reflect, in significant part, PJM decisions about the definition of supply and demand," and that "capacity market prices can be significantly affected by forecast data center load that bears little known resemblance to reality." Id. at 2, 4.
41. Movants take no position on the Monitor's proposed remedies, and note that the Monitor's report addresses the 2027/2028 auction rather than the 2028/2029 auction from which the Initial RBP Target is drawn — though the Monitor warns the identified problems "will continue to result in even higher prices unless the related issues are addressed." Id. at 8. Movants cite the report for one proposition: the "observed" shortfall that defines the Initial RBP Target is not a pure market datum. By the assessment of PJM's own independent Market Monitor, it reflects, in significant part, administrative determinations — including the ELCC approach and a load forecast incorporating large-load projections of uncertain reliability. A figure of that character should be substantiated before it fixes fifteen years of procurement obligations.
V. PJM SIMULTANEOUSLY PROPOSES TO DEFER THE TARIFF'S OWN
MANDATED INVESTIGATION OF THE SHORTFALL'S CAUSES
42. PJM's existing Tariff already requires the inquiry Movants seek. As PJM's own transmittal acknowledges, the Tariff contains an "existing requirement for PJM to investigate the cause for clearing short of the reliability requirement and to recommend corrective action." RBP
PDF page 14
Filing, transmittal at 124. And PJM's own footnote quotes the 2027/2028 BRA Report: the shortfall "constitutes a triggering event as defined in the PJM Tariff, mandating an investigation to determine the root causes of the region's failure to secure sufficient resource adequacy." Id. at 124 n.308.
43. Yet the RBP Filing proposes to reset that investigation and corrective-action obligation to the 2032/2033 Delivery Year, on the stated rationale that doing so "avoids posting substantively repetitive reports should the BRAs continue to clear short in the intervening Delivery Years." Id. at 124. The filing does not state whether the root-cause investigation already mandated by the 2027/2028 shortfall has been completed, and no such analysis appears in the filing.
44. The juxtaposition is the problem. PJM proposes to (a) procure up to fifteen years of capacity commitments sized by the shortfall, while (b) deferring until 2032/2033 the Tariff's own mandated investigation into the causes of that shortfall. Whatever the administrative convenience of avoiding repetitive reports, the sequence is backwards: the root-cause analysis the Tariff already requires should be completed and placed on the record before long-duration commitments are fixed by the number it examines — not five Delivery Years after.
VI. THE RELIEF REQUESTED IS AVAILABLE UNDER SECTION 205
45. Movants recognize that in a section 205 proceeding the Commission's role is to determine whether the rate the utility has filed is just and reasonable, and that the Commission may not impose modifications resulting in "an entirely different rate design" from the utility's proposal. NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017).
PDF page 15
46. No such limit is implicated here, for two independent reasons. First, PJM has consented. The RBP Filing states that "to facilitate Commission approval and prompt opening of the RBP procurement window, PJM consents to the Commission's exercise of authority to modify and/or sever the proposed Tariff and RAA language, as needed and permitted under the FPA and NRG Power Marketing, where such modification is consistent with PJM's overarching objectives in this filing," and asks only that the Commission "expressly prescribe the revised rate or rule in its order." RBP Filing, transmittal § V, at 130–31. Conditioning acceptance on substantiation of the procurement target is consistent with PJM's stated overarching objective — procuring capacity to meet the Region's actual resource adequacy need — and alters no element of the RBP's design.
47. Second, the condition sought substitutes one number for another — the precise operation the D.C. Circuit has approved. In Aera Energy LLC v. FERC, 789 F.3d 184, 190–92 (D.C. Cir. 2015) — quoted by PJM's own filing at note 318 — the court affirmed a conditional acceptance that "simply required [the utility] to substitute one number for another." A Final RBP Target substantiated against the modeling questions identified by PJM's own consultant leaves every design element of the RBP untouched: the same procurement mechanism, the same eligibility rules, the same commitment term, the same allocation methodology. Only the quantity changes, and only if the substantiation shows it should.
48. In the alternative, and independent of consent: requiring an applicant to substantiate the central quantitative term of its own filing is not redesign at all — it is the application of the applicant's burden of proof under section 205(e). The Commission may also accept and suspend the filing for a nominal period and set the procurement quantity for further proceedings, or
PDF page 16
accept the mechanism while directing that the Final RBP Target be established in a compliance filing supported by the analyses identified herein.
VII. COST ALLOCATION: THE PROPOSAL RESTS ON STATE ACTION
THAT HAS NOT OCCURRED
49. PJM proposes to allocate the Final RBP Target first to Electric Distributor zones by forecasted load growth, and then to Load Serving Entities in a manner that "permits states to determine the appropriate allocation of RBP UCAP MW to specific LSEs and/or end-use customers, thus allowing Relevant Electric Retail Regulatory Authorities ('RERRA') to appropriately assign costs to their respective retail customers, including data centers."
50. Movants state candidly that PJM's zonal step does not, on PJM's illustrative example, allocate RBP UCAP MW to the DPL zone, and that PJM's 2026 Load Forecast Table B9b shows no load adjustment for the DPL zone in any year from 2026 through 2046. To that extent PJM's allocation directs cost toward the zones whose forecast load growth gives rise to the shortfall, and Movants do not criticize that design.
51. Movants' concern is with what happens when the design's premise fails. PJM states that "[s]hould the relevant RERRA(s) decline to communicate RBO MW to the relevant Electric Distributors ..., PJM has proposed to apply a backup default cost allocation." The protection PJM offers to existing customers thus depends on affirmative, discretionary action by state regulators that has not yet occurred, over a term of up to fifteen years.
52. PJM further relies on the Statement of Principles Regarding PJM issued January 16, 2026, in which the governors of the PJM states "agreed to ... [u]se their Authorities to Allocate Costs to Data Centers and Protect Residential Customers." Movants do not question the sincerity
PDF page 17
of that commitment. It is, however, a statement of intent by persons who are not parties to this proceeding and who cannot be bound by any order the Commission issues here. A section 205 filing must be shown just and reasonable on its own terms.
53. Delaware illustrates the gap. The Delaware Public Service Commission opened its large load tariff proceeding, Docket No. 25-0826, in October 2025 — announcing the effort as one to ensure that "large load facilities, like data centers, do not shift costs to other ratepayers." Del. PSC, Delaware PSC Opens Docket for Large Load Tariff, Pauses Interconnections (Oct. 14, 2025). That proceeding remains pending. Delaware has not yet adopted the rate structures on which PJM's allocation design depends.
54. Movants therefore request that the Commission require PJM to specify the backup default cost allocation with particularity and to demonstrate that it is just and reasonable as applied to zones and customer classes that neither caused nor benefit from the shortfall, including in the event a RERRA does not act within the RBP timeline.
VIII. REQUESTED RELIEF
55. Movants respectfully request that the Commission:
(a) grant this motion to intervene and accord each Movant party status;
(b) direct PJM to address on the record in this proceeding the E3 PJM ELCC / RRS Model Evaluation (December 2025) (Attachment A hereto) and PJM's ELCC Senior Task Force sensitivity analyses (May 22, 2025) (Attachment B hereto), and their implications for the RBP Target;
PDF page 18
(c) consistent with PJM's consent to modification, condition acceptance of the RBP Filing on PJM demonstrating the Final RBP Target calculated under the modeling questions identified by E3, including at minimum E3's Considerations 3, 4 and 6, individually and in combination, or explaining why each does not materially affect the Target;
(d) direct PJM to complete and file the root-cause investigation and corrective-action recommendations already required by its Tariff in respect of the 2027/2028 and 2028/2029 shortfalls before RBP commitments are finalized, and decline to accept — or condition — the proposed deferral of that investigation obligation to the 2032/2033 Delivery Year;
(e) require PJM to specify the backup default cost allocation applicable where a RERRA does not communicate RBO MW, and to demonstrate that it is just and reasonable;
(f) in the alternative, accept and suspend the filing for a nominal period and establish further proceedings limited to the RBP Target and cost allocation; and
(g) grant such other relief as the Commission deems just and reasonable.
56. Movants do not request that the Commission reject the RBP Filing, and do not oppose PJM proceeding with the RBP mechanism on a schedule that permits the matters above to be addressed.
ATTACHMENTS
Attachment A — Energy and Environmental Economics, Inc., PJM ELCC / RRS Model Evaluation (December 2025) (presented to the PJM ELCC Senior Task Force, Dec. 9, 2025).
PDF page 19
Attachment B — PJM Interconnection, L.L.C., ELCC Accreditation Methodology: Update on Sensitivity Analyses (ELCC Senior Task Force, May 22, 2025).
IX. COMMUNICATIONS
57. Communications regarding this proceeding should be addressed to:
Nicholas Max Neal
111 Centrenest Lane
Wilmington, Delaware 19807
Telephone: (845) 263-0012
Email: max@nicholasneal.com
David Neal
111 Centrenest Lane
Wilmington, Delaware 19807
Telephone: (646) 509-3146
Email: shaun@shaunneal.com
X. CONCLUSION
58. PJM asks the Commission to authorize commitments of up to fifteen years, in a quantity set by a model, without telling the Commission what its own consultant said about that model or what its own sensitivity analyses showed — while proposing to defer, until 2032/2033, the investigation of the shortfall's causes that PJM's Tariff already mandates. Movants ask only that PJM be required to substantiate the number before the commitments are made, and that the Commission satisfy itself that the resulting quantity is just and reasonable. For the foregoing reasons, Movants respectfully request that the Commission grant this motion to intervene and the relief requested herein.
Respectfully submitted,
/s/ Nicholas Max Neal /s/ David Neal
PDF page 20
_______________________________ _______________________________ Nicholas Max Neal David Neal
111 Centrenest Lane 111 Centrenest Lane
Wilmington, Delaware 19807 Wilmington, Delaware 19807
(845) 263-0012 (646) 509-3146
max@nicholasneal.com shaun@shaunneal.com
Pro se Pro se
Dated: August 20, 2026
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding, in accordance with Rule 2010 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.2010. Dated at Wilmington, Delaware, this 20th day of August, 2026.
/s/ David Neal
_______________________________
David Neal