ER26-3380-000 · 2026-08-21 · FirstEnergy Service Company

Comments and Protest of FirstEnergy Service Company re PJM Interconnection, L.L.C.'s 07/31/2026 filing proposing to establish a Reliability Backstop…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
    )

Docket No. ER26-3380-000
COMMENTS AND PROTEST OF
FIRSTENERGY SERVICE COMPANY
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 FirstEnergy Service Company (“FirstEnergy”) respectfully submits these comments and protest of the filing submitted by PJM Interconnection, L.L.C. (“PJM”) on July 31, 2026, proposing to establish a Reliability Backstop Procurement (“RBP”) mechanism.2

FirstEnergy agrees that new generation is needed.  Unfortunately, fundamental elements of PJM’s RBP proposal are fatally flawed and as a result these elements cannot be approved consistent with Section 205 of the Federal Power Act (“FPA”).  Section 205 of the FPA provides that the Commission can accept PJM’s RBP proposal only if it is just and reasonable and not unduly discriminatory or preferential.3  The filing utility—PJM— bears the burden of proof to demonstrate its proposal meets these FPA requirements.4  The Commission may accept PJM’s proposal only if there is sufficient evidence in the record to show PJM has carried its Section 205 burden of proof.5  The Commission will reject any

1 18 C.F.R. § 385.211 (2025).
2 PJM Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming from Large Loads, Docket No. ER26-3380-000 (“July 31 RBP Proposal”).
3 16 U.S.C. § 824d(a)-(b).
4 Constellation Mystic Power, LLC v. FERC,  45 F.4th 1028, 1035 (D.C. Cir. 2022); NorthWestern Corp. v. FERC, 884 F.3d 1176, 1182-83 (D.C. Cir. 2018) (“Northwestern Corp.”); Midcontinent Indep. Sys. Operator, Inc., 194 FERC ¶ 61,050, at P 23 (2026); Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236, at P 7 (2018).
5 Northwestern Corp., 884 F.3d at 1182-84; City of Winnfield v. FERC, 744 F.2d 871, 876-77 (D.C. Cir. 1984); NorthWestern Corp., 147 FERC ¶ 61,049, at P 48 (2014).

PDF page 2

2
proposal that falls outside the zone of reasonableness—i.e., does not result in just and reasonable rates in accordance with Section 205.6  Moreover, even if a rate falls within the zone of reasonableness, it may nevertheless violate Section 205 due to being unduly discriminatory or preferential.7

In these comments and protest, FirstEnergy demonstrates that PJM’s filing does not meet the FPA Section 205 just and reasonable standard because:

1. PJM did not follow the Statement of Principles policy directive for
determining how much new capacity to purchase, or how to allocate the
costs;8
2. PJM's load-side collateral requirements are unsupported and not
necessary;
3. PJM's levelized contract framework – which permits suppliers to “front load” the capacity contracts – creates unnecessary affordability risks;

4. PJM’s proposed cost allocation can result in costs not going to new data centers as required by the Statement of Principles and also fails to

comply with fundamental cost allocation criteria;
5. PJM’s Reliability Backstop Procurement should be limited to resources that most effectively address reliability needs;

6. PJM's proposed implementation schedule is compressed unreasonably;
7. PJM’s proposed “opt-out” mechanism allows for unreasonable cost
shifting;
8. FERC should direct PJM to strengthen supplier performance and credit requirements; and

9. FERC should direct PJM to clarify that its proposed gating criteria
require binding contractual commitments for eligible demand response
resources.
In addition to the above, FirstEnergy respectfully submits that FERC should require that, when PJM refiles tariff amendments that comply with the Statement of Principles, 6

Indep. Power Producers of N.Y., Inc. v. FERC, 2022 U.S. App. LEXIS 22081, at * 6, 2022 WL 3210362, at *2 (D.C. Cir. Aug. 9, 2022) (citing Me. Pub. Utils. Comm'n v. FERC, 520 F.3d 464, 471 (D.C. Cir. 2008), rev’d on other grounds, 558 U.S. 165 (2010); FCC v. Prometheus Radio Project, 592 U.S. 414, 423 (2021)).

7 Ala. Elec. Co-op., Inc. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982) (citing U.S. v. Ill. Cent. R.R., 263 U.S. 515, 524 (1924)).
8 Statement of Principles Regarding PJM, National Energy Dominance Council (Jan. 16, 2026), available at https://www.energy.gov/documents/statement-principles-regarding-pjm[https://perma.cc/35HJ- W56E](the “Statement” or “Statement of Principles”).

PDF page 3

3
PJM should provide certain clarifications about the qualifications and criteria for Demand Response to participate in the backstop procurement.

COMMENTS AND PROTEST
1. PJM Did Not Follow the Statement of Principles Policy
Directive For Determining How Much New Capacity to
Purchase, or How to Allocate the Costs.
The Statement of Principles directs PJM to conduct a reliability backstop auction to procure new capacity resources, with the procurement to provide a 15-year term of price certainty.9  The Statement also directs that the costs are to be allocated to load-serving entities with new data centers that have not self-procured new capacity or agreed to be curtailable.10  PJM’s proposal makes no effort to comply with this directive.  Instead, PJM proposes to allocate costs based on forecasts that were submitted in 2025.  PJM does not identify the data centers that are included in such forecasts, nor does it make any effort to ensure that the costs that are so allocated go only to new data centers that have not self- supplied or agreed to be curtailable.  As such, PJM cannot demonstrate that the costs will go to new data centers.

PJM cannot justify its failure to adhere to the Statement’s policy guidance.  The Statement was issued on January 16, 2026 and PJM’s filing was submitted on July 31, 2026.  PJM had six and one-half months to identify the new data centers that are within scope, and to hold stakeholder discussions for how to allocate the costs at the wholesale and retail level.  PJM did not do so.  Instead, PJM conducted extensive stakeholder processes in an effort to justify its preferred policy direction, and then refused to implement

9 Statement of Principles, Bullet 1.  Notably, PJM’s proposal does not comply even with this straightforward directive as it contemplates that resources may contract for terms of less than 15 years.
10 Id., Bullet 3.

PDF page 4

4
the stakeholder-endorsed backstop procurement proposal that came out of that process.11 In other words, PJM ran out the clock with stakeholder processes instead of utilizing the allotted time to solicit the data that would be necessary for PJM to allocate the backstop procurement costs as directed by the Statement of Principles.

PJM cannot take refuge in its broad authority to amend the terms of the existing Reliability Assurance Agreement.12  It’s correct to say that Section 16.4 of the RAA gives the PJM Board broad rights to amend the agreement.  And it’s also correct to say that Section 16.4 of Attachment DD of the PJM Open Access Transmission Tariff (“OATT”) describes a “reliability backstop auction.”13  But PJM’s authorization to amend the RAA and the OATT is subject to certain inherent limiting principles.  PJM cannot, for example, create an entirely new power product and impose the costs on wholesale or retail customers simply because it wants to or simply because in its best judgement its corporate principles will be served.

Importantly, PJM was not “starting from scratch.”  As noted, the current OATT describes a “reliability backstop” product.  The Statement of Principles reflects policy guidance and direction from a slate of bipartisan state governors and the White House. And the PJM stakeholder process included a “Joint Proposal” by a group of Electric

11 See PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement and Connect and Manage, available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we- are/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement- and-connect-and-manage.pdf.
12 Available at https://www.pjm.com/pjmfiles/directory/merged-tariffs/raa.pdf.
13 Available at https://www.pjm.com/pjmfiles/directory/merged-tariffs/oatt.pdf, at pp. 6285-87.

PDF page 5

5
Distribution Companies and Data Center Customers for how to implement the Statement and allocate the costs.14

PJM’s proposal is not consistent with any of the above.  Instead, and as noted above and throughout this Protest, PJM has submitted tariff amendments that are inconsistent in material terms with the Statement of Principles and a proposal that was approved by the overwhelming majority of stakeholders.  Even worse, PJM’s tariff amendments call for the costs of its backstop procurement to attach before LSEs (and their respective stakeholders) will have any meaningful opportunity to avoid such costs by exercising their right to exit. That is, PJM proposes to conduct a procurement that it admits it has designed in such a manner that the cost likely will be close to the “notational value” (or cap) of $555/MWD, or approximately $20.7 billion over the 15-year term of the contracts, and for the procurement to be conducted and the costs to attach before LSEs and their stakeholders can exercise their right to avoid such costs by exiting.

There is no scenario where this outcome can be construed as “just and reasonable.” Even if the Commission were inclined to approve the proposal—which given the above would raise serious doubt about the legal durability of such approval—to do so would bring even more uncertainty as LSEs, the PJM states, and other important stakeholders could be forced to resort to extraordinary legal measures to prevent such costs from attaching before the appellate process could address the merits of the Commission’s action. Given the manifest deficiencies in PJM’s filing, and the significant financial and legal risk in going forward, the Commission should: (i) rule that PJM has not met its

14 Available at 20260630-item-02f---joint-edcs-and-data-center-coalition---rbp---executive- summary.pdf.

PDF page 6

6
statutory “just and reasonable” burden for going forward, and (ii) provide guidance for PJM and the stakeholders going forward.  Moreover, in light of the amount of time that has passed since the January 16, 2026 issuance of the Statement of Principles, and the Commission’s experience with obtaining a broadly-supported outcome for PJM capacity issues,15 the Commission should give serious consideration to commencing an FPA Section 206 proceeding and then facilitating settlement negotiations.

Speaking to the going-forward process: creation of the Reliability Pricing Model (“RPM”) is the analogue for navigating significant policy changes for the PJM capacity product.  As the Commission is aware, over twenty years ago, PJM submitted amendments to its tariff to implement its vision for funding the capacity cost of physical generation.16 Then, as now, the proposed tariff amendments were poorly designed and faced significant opposition from utilities, customers, and state regulators.  The Commission rejected PJM’s filing and instituted an FPA Section 20617 proceeding.  There were many months of settlement negotiations and, ultimately, the majority of PJM’s stakeholders were able to agree, or “not oppose” the RPM construct.18  This background illustrates the arbitrary nature of PJM’s current proposal:  less than 20% of the stakeholders voted for PJM’s RBP proposal,19 whereas almost 60% of the stakeholders voted in favor of a Joint Electric

15 See FERC Docket Nos. ER05-1410, EL05-148, PJM Interconnection, L.L.C., Order Denying Rehearing and Approving Settlement Subject to Conditions, 117 FERC ¶ 61,331 (2006).
16 See id. 17 16 U.S.C. § 824e.
18 PJM Interconnection, 117 FERC ¶ 61,331.
19 See 6/30/26 PJM Members Committee, Supplemental Voting Results, available at mc-voting- results---agenda-item-3l---pjm-rbp-proposal.pdf.

PDF page 7

7
Distribution Company/Data Center Coalition proposal.20  The Commission should follow the RPM playbook: reject PJM’s filing, institute an FPA Section 206 proceeding, and establish settlement proceedings.

2. PJM’s
Proposed
LSE
Collateral
Requirements
Are
Unnecessary and Excessive.
PJM proposes to impose a new and onerous collateral obligation on each LSE allocated RBP Charges.21  Under the Proposed Tariff, the cumulative LSE credit requirement would initially equal $1.5 million multiplied by the total MW of committed RBP Unforced Capacity (“UCAP”) allocated to the LSE.22  PJM has failed to meet its burden under section 205 to demonstrate that its proposed LSE credit requirement is just and reasonable and not unduly discriminatory and the Commission must therefore reject PJM’s unprecedented load-side collateral requirements.

PJM fails to demonstrate why it is necessary to require LSEs to post additional collateral. Retail customers, hopefully the new data centers described in the Statement of Principles, ultimately will take these costs.23  Because retail customers ultimately will pay the RBP costs, there is no justification for imposing new and onerous collateral

20 See 6/30/26 PJM Members Committee, Supplemental Voting Results, available at mc-voting- results---agenda-item-3o---joint-edcs-and-data-center-coalition-rbp-proposal.pdf.
21 See July 31 RBP Proposal at 108-123.
22 Proposed Tariff, Attachment DD at Section 18.8(b)(i)(A).
23 See, e.g., Qualifying Facility Rates & Requirements Implementation Issues Under the Pub. Util. Regul. Pol’ys Act of 1978, 172 FERC ¶ 61,041, at P 40 (2020) (recognizing that “electric utilities with franchised service territories that make sales at retail are often effectively guaranteed the recovery of their energy costs in their retail rates by their state regulatory authorities—provided that such costs are prudently incurred.”); Pa. Power Co. v. Pub. Util. Comm’n, 932 A.2d 300 (Pa. Commw. Ct. 2007).

PDF page 8

8
requirements on LSEs that will likely result in hundreds of millions of dollars in additional collateral, the costs of which will ultimately be borne by retail ratepayers.24 PURPA must-purchase arrangements supporting Qualifying Facility development

are the closest long-term contractual analogue to the sort of commitment that LSEs will be required to assume as a result of PJM’s RBP.25  Under PURPA contracts, however, the purchasing entities generally have been subject to low or no collateral requirements because of their ability to recover costs from retail customers.26  Imposing identical rates, terms and conditions on entities that are not similarly situated is no less discriminatory than treating similar situated entities differently.27  PJM’s proposal is therefore unduly discriminatory and must be rejected.

Even if some additional collateral was appropriate, PJM must be able to show that its proposed collateral requirements are reasonably tailored to the actual credit risk presented by specific LSEs, or substantially similar classes of LSEs.  PJM’s proposal is unjust and unreasonable because it automatically treats such entities as presenting the same nonpayment risk as LSEs without comparable cost-recovery mechanisms.  It does not

24 With respect to FirstEnergy affiliate service territories, FirstEnergy estimates that the collateral requirements will be approximately $363.7 million in total, representing $169 million in the FirstEnergy Ohio area, $20.5 million in the Penn Power area and $174.2 million in the Potomac Edison territory.
25 Public Utility Regulatory Policies Act of 1978 (“PURPA”), Pub. L. No. 95-617, 92 Stat. 3117 (1978), codified in relevant part at 16 U.S.C. § 824a-3.
26 See, e.g., North Carolina Electric Membership Corp., Standard Power Purchase Agreement for Qualifying Facilities (Facilities ≤ 100 kW) (May 21, 2026), available at https://e1.nmcdn.io/assets/ncemcs2/wp-content/uploads/2026/05/NCEMC-Standard-PPA_20260521.pdf; Order Establishing Standard Rates and Contract Terms for Qualifying Facilities, Dkt. No. E-100, Sub 194 (N.C. Util. Comm’n Sept. 30, 2024) (approving standard offer PUPRA PPA without utility collateral requirements); In re Joint Utils. Application for Approval of Proposed Schedules & Standard Power Purchase Agreement for Qualifying Facilities up to 10 MW, Docket No. UM 2299, Order No. 24-070 (Or. P.U.C. Mar. 12, 2024) (approving form of standard QF PPA without utility collateral requirements).
27 See, e.g., Ark. Elec. Energy Consumers v. FERC, 290 F.3d 362, 368 (D.C. Cir. 2002); Complex Consol. Edison Co. of New York v. FERC, 165 F.3d 992, 1013 (D.C. Cir. 1999); Ala. Elec. Co-op. v. FERC, 684 F.2d at 27-28.

PDF page 9

9
explain whether or how regulated cost recovery affects LSE default risk, and it does not identify evidence that LSEs with such recovery mechanisms require collateral equal to approximately half of a 15-year notional payment stream.

These deficiencies alone require rejection of PJM’s collateral proposal.  However, PJM’s collateral proposal suffers from additional flaws:


PJM fails to provide sufficient justification for the $1.5 million per MW figure. PJM does not identify an expected probability of default, a loss-given-default assumption, a historical LSE default experience, a liquidation or replacement period, or any other quantitative measure connecting the proposed $1.5 million per committed RBP MW requirement to a reasonably anticipated loss. 

PJM acknowledges that LSEs and other market participants already are subject to existing collateral requirements, but fails to identify the particular limitation in Attachment Q that prevents it from addressing a reasonably measured RBP exposure through those existing requirements.


PJM provides no details specifying how quickly excess collateral must be returned.  PJM’s proposal to retain absolute discretion to make such determinations is unjust and unreasonable as it fails to protect LSEs from over- collateralization.


If seller collateral remains available when an RBP Seller defaults, PJM should be required to draw upon that collateral and use the proceeds to provide the corresponding shortfall credits to the affected LSEs.  Nothing in PJM’s proposal explains why the use of available seller collateral should be discretionary, or why the proposed tariff provisions are silent regarding the amount, timing, and allocation of any proceeds recovered from such collateral.

In an age of increasing affordability concerns, PJM’s proposal will harm retail customers, because those customers will ultimately bear the costs of these credit requirements.  Absent more compelling justifications than those contained in the current RBP Proposal, the Commission cannot accept PJM’s proposal as within the zone of reasonableness.

PDF page 10

10
3. PJM’s Levelized Contract Framework—Which Permits
Suppliers to “Front Load” the Capacity Contracts—Creates
Unnecessary Affordability Risks.
PJM proposes to clear offers in the RBP Auction based on a levelized cost approach.  PJM bears the burden to show it is just and reasonable.  It cannot, and its approach creates the risk of excessive affordability concerns for retail ratepayers. Specifically, PJM proposes that the levelized cost of all selected RBP offers will not exceed a maximum “willingness to pay” of $555/MW-day, on a MW-weighted average basis over all of the Delivery Years of the RBP.28  As PJM acknowledges, this means sellers can offer substantially different price offers between Delivery Years, so long as the total MW-weighted average of all RBP offers over all of the Delivery Years of the RBP does not exceed $555-day.29

The predictable consequence of this flexibility is that sellers will front-load their costs into the initial years of their contracts, significantly increasing bill impacts in the near term.  A seller, for example, could charge $1,000/MW-day for the first several years of the contract, and then balance that out with sub-market prices in the latter years.  The result is that customers will be forced to bear what could be extremely large increases in capacity costs during the initial Delivery Years of the RBP.  All during a period when there is increasing concern, including concern by members of this Commission,30 about affordability.  Absent a persuasive justification for this levelized offer structure—and there is none—the Commission should reject it.

28 July 31 RBP Proposal at 61-64; Proposed Tariff, Attachment DD at Section 18.5(f).
29 July 31 RBP Proposal at 62-63.
30 See, e.g., United States House of Representatives, Committee on Energy & Commerce, 2/3/2026 Hearing:  Oversight of FERC: Advancing Affordable and Reliable Energy for All Americans, comments of Commission members.

PDF page 11

11
A “levelized” cost structure is not needed.  The Statement of Principles calls for PJM to provide for price certainty for a 15-year term.31  There is significant investment in new generation in areas outside of PJM by vertically-integrated utilities where cost recovery generally is on a straight-line fixed value basis.  And the country’s experience with PURPA contracts reflects that, generally, nonincumbent utility investors are willing to construct new generation on a straight-line fixed value basis.  Doubtless, these factors influenced the Statement of Principles policy directive that PJM was to provide price certainty for a 15-year term.

As a “levelized” cost structure is not needed, and as permitting it could lead to unacceptable affordability issues, PJM has not carried its FPA Section 205 “just and reasonable” burden for going forward.  Accordingly, the Commission should reject PJM’s proposed amendments.

4. PJM Has Failed to Demonstrate That Its Cost Allocation
Proposal Is Just and Reasonable.
PJM proposes that RBP costs will be allocated to LSEs within the territories of Electric Distributors.32  Each Electric Distributor’s territory’s share of RBP costs will be its pro rata share of the difference between the forecasted load adjustments for the 2026/2027 and 2028/2029 capacity auction cycles.33  Each Electric Distributor’s territory’s share will then be allocated to LSEs within that territory.34

31 Statement of Principles, Bullet 1.
32 See July 31 RBP Proposal at 96-97.
33 Id. at 96-97.
34 Id. at 97-98.

PDF page 12

12
This proposal is at odds with FPA Section 205 as well as fundamental principles of cost allocation.  First, PJM’s cost allocation proposal is not meaningfully targeted to ensure the customers ultimately allocated the costs of the RBP will be entities causing the need for the procurement of new generation—i.e. new data center customers, in accordance with the Statement of Principles.  Rather than proposing an allocation methodology specifically targeted to new data centers, PJM instead proposes allocating the costs based on forecasted Load Adjustments for the 2026/2026 and 2028/2029 Delivery Years.  These forecasted Load Adjustments are not, however, limited to new data centers.  Instead, they include facilities with existing contracts and possibly even those already under construction, as well as potentially native non-data load customers as well.  In short, PJM is proposing to allocate the costs of the new generation needed for tomorrow’s data centers to yesterday’s customers.  PJM fails to explain its departure from the Statement of Principles, and therefore fails to meet its burden under FPA Section 205 to demonstrate its cost allocation proposal is just and reasonable.

PJM’s proposal is also inconsistent with the Commission’s fundamental cost allocation principles, particularly the requirement that costs be assigned “roughly commensurate” with the benefits received by customers.35  PJM’s proposed methodology to allocate costs to LSEs based on a single forecasting comparison, along with arbitrary discounts to data center loads, bears no meaningful relationship to reasonably-anticipated new data center load.  To the contrary, PJM’s proposal would allocate costs primarily based

35 See, e.g., Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Order No. 1920-A, 189 FERC ¶ 61,126 at P 157 (Nov. 25, 2024) (Order No. 1920 mandates “consistent with long-established Commission and court precedent, that transmission customers within a transmission planning region need only pay costs that are ‘roughly commensurate’ with the benefits that transmission providers estimate they will receive from a regional transmission facility.”) (citations omitted).

PDF page 13

13
on LSEs with existing data center customers, rather than the new data center customers that are primarily driving the need for the RBP.  This disconnect between cost causers and beneficiaries and the RBP costs to be allocated will be magnified by PJM’s decision that the allocation will remain fixed for a fifteen-year period.  While cost allocation does not require absolute precision,  it does require an “articulable and plausible reason” to believe that the benefits received will be at least “roughly commensurate” with the costs.36  There is, however, no way to know what load conditions will look like in five years, much less fifteen.  Thus, there is no plausible reason to believe that PJM’s zonal cost allocation approach will ensure even a rough match between the costs and the beneficiaries of capacity procured in the RBP.37

PJM’s cost allocation proposal also violates the filed rate doctrine because it will undermine preexisting commercial relationships by attempting to allocate costs to data centers who possibly have already signed FERC-jurisdictional contracts based on a pre- RBP understanding of the market.  As discussed above, PJM’s proposed allocation methodology could include data center facilities that already have binding commitments, including contracts between the data center customer and associated EDCs/LSEs.  Those contracts, to the extent they have been filed and accepted by the Commission, constitute the filed rate for those entities with respect to their energy supply obligations.  PJM’s proposal does not even recognize, much less attempt to justify, the need or reasonableness

36 See Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).  See also Transmission Planning & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051 at P 622 (2011).
37 This allocation mismatch is further compounded by PJM’s proposal to require non-defaulting LSEs to assume an additional payment obligation solely because another LSE failed to satisfy its allocated RBP Charges.  See Proposed Tariff, Attachment DD at Section 18.9(a).  The default of one LSE should not provide an independent basis for increasing the RBP costs assigned to another.

PDF page 14

14
of allocating these entities what would essentially constitute additional costs for the same service.

PJM’s cost allocation proposal also fails to meet the requirements of FPA Section 205 because the proposed LSE allocation methodologies are dependent in substantial part on whether and how certain state or other retail regulators choose to exercise their own authority and discretion.  There is no way to determine whether such allocations would be just and reasonable because such determination is left entirely to the discretion of state and other retail regulators.  The justness and reasonableness of a public utility’s proposal cannot be established based on speculative future action, particularly action by third-parties that neither PJM nor the Commission has the authority to control.38

Finally, PJM’s cost allocation proposal runs afoul of the “rule of reason” requiring that sufficient detail regarding FERC-jurisdictional services be included in a public utility’s tariff.  For example, in the affidavit accompanying PJM’s filing, PJM provides a chart with examples of possible RBP cost allocations.39  In this chart, FirstEnergy affiliate Potomac Edison is listed as an “Electric Distributor Zone/Area,” subject to cost allocation. However, the reference to Potomac Edison is unclear because there are multiple FirstEnergy affiliates operating under that banner across three different States.  This ambiguity suggests that FirstEnergy will have to decide how to sub-allocate the RBP costs among these entities, yet the PJM proposal does not even acknowledge, let alone provide details regarding the implementation of, this sub-allocation.  The Commission cannot

38 See, e.g., N.Y. State Pub. Serv. Comm’n v. FERC, 104 F.4th 886 (D.C. Cir. 2024); N.Y. Indep. Sys. Operator, Inc., 183 FERC ¶ 61,130 (2023); Kan. Corp. Comm’n v. FERC, 881 F.3d 924 (D.C. Cir. 2018).
39 See Attachment C, Affidavit of Ms. Danielle Croop at P 46 (“Croop Affidavit”).

PDF page 15

15
approve a rate filing that is so vague and subject to numerous implementation details that have yet to be even contemplated let alone developed.

5. PJM’s Reliability Backstop Procurement Should Be Limited to
Resources That Most Effectively Address Reliability Needs.
PJM proposes to permit a broad range of resources to participate in the RBP, including new generation resources, energy storage resources, demand response resources, and distributed energy resources.40  PJM justifies the RBP as an extraordinary measure necessary to address the approximately 6,831 MW capacity shortfall identified in the 2028/2029 Base Residual Auction and to preserve resource adequacy within the PJM Region.41  Because the stated purpose of the procurement is to address an identified reliability need, the Commission should ensure that the procurement is structured to prioritize the resources that most effectively advance that need.

While demand response, storage, and distributed energy resources may provide value under certain circumstances, not all eligible resource types provide the same level of reliability benefits or operational certainty.  Because the stated purpose of the RBP is to address a reliability shortfall, the Commission should ensure that the procurement appropriately prioritizes resources that provide firm and dependable capacity.  New dispatchable generation resources are capable of producing energy when needed and therefore provide a more direct means of addressing the resource adequacy concerns that PJM identifies as the basis for the proposal.

Worth noting here is that the North American Electric Reliability Corporation (“NERC”)—which is responsible for developing, applying and enforcing mandatory

40 July 31 RBP Proposal at 42 n.112.
41 July 31 RBP Proposal at 31, 68.

PDF page 16

16
reliability standards—has identified that “conventional generators,” such as nuclear, coal and natural gas generators, provide much of the essential reliability services that support reliable operation of the grid today.42  NERC further reports that wind and solar resources lack the spinning mass, that is, the traditional excitation systems, that provide for voltage control and stability to support the transmission grid.43  NERC explains that generators that can be controlled, that is, dispatched on demand, provide system inertia, dynamic reactive support, and frequency response for stable grid operation.44  In an era that is dominated by affordability concerns, it would be reasonable to conclude that scarce customer dollars should be directed to resources that provide or reflect the dispatchable characteristics that are necessary for reliability.

This issue is particularly important given the magnitude of the procurement and the fifteen-year commitments associated with selected resources.45  PJM expressly states that the procurement process is designed to select the “least-cost set of resources” that satisfies the procurement target while remaining within the applicable willingness-to-pay constraint.46  Although cost discipline is important, a procurement justified on reliability grounds should not focus exclusively on minimizing costs without sufficient consideration of the relative reliability value provided by different resource types.

FirstEnergy therefore urges the Commission to ensure that the RBP is narrowly tailored to procure the resources that most effectively address reliability needs.  At a

42 NERC, 2024 Long-Term Reliability Assessment, at p. 29, available at https://www.nerc.com/globalassets/our-work/assessments/2024-ltra_corrected_july_2025.pdf.
43 Id. at pp. 29-30.
44 Id. at p .22.
45 July 31 RBP Proposal at 76-78.
46 July 31 RBP Proposal at 78.

PDF page 17

17
minimum, the Commission should require PJM to demonstrate that the proposed framework appropriately prioritizes firm and dependable capacity resources and does not result in the procurement of resources that provide less reliability value than reasonably available dispatchable alternatives.

6. PJM’s Proposed Implementation Schedule Is Unreasonably
Compressed.
PJM proposes to commence the Reliability Backstop Procurement on September 30, 2026 and requests that the Commission act on the filing by September 29, 2026.47 PJM’s proposed schedule would therefore permit the procurement to begin immediately following Commission approval.  While FirstEnergy appreciates the need for prompt action, PJM’s proposed implementation schedule provides insufficient time for affected LSEs, Electric Distributors, state regulators, and retail customers to evaluate the consequences of the proposal and take steps to mitigate resulting obligations.  The RBP is not a minor modification to PJM’s capacity construct, but an entirely new procurement mechanism.  The RBP will create substantial long-term payment obligations, impose unprecedented collateral requirements, and rely upon state-specific cost-allocation determinations that, in many jurisdictions, have not yet been developed.48  For these reasons, PJM has failed to demonstrate that the compressed timeline is just and reasonable. PJM acknowledges that implementation of its proposal requires substantial coordination among PJM, Electric Distributors, states, Regional Electric Reliability 47

July 31 RBP Proposal at 2-3, 130.
48 July 31 RBP Proposal at 96-99, 103-105, 116-117.

PDF page 18

18
Regulatory Authorities (“RERRAs”), and load-serving entities.49  Yet, the proposal would move forward before all of these entities have had a reasonable opportunity to determine whether and how, they will implement the proposal.

The compressed schedule is particularly problematic given the magnitude of the financial obligations at issue.  As discussed above, PJM proposes to require LSEs allocated RBP costs to post hundreds of millions of dollars collateral.  FirstEnergy’s affiliates alone estimate the collateral costs for their retail customers could be in excess of $350 million. Before such obligations are imposed, affected entities should have a reasonable opportunity to assess the proposal, evaluate potential mitigation measures, and coordinate with state regulators regarding cost recovery and compliance.  Moreover, unlike prior significant market reforms—most notably RMM, which is discussed in more detail above—affected parties have no meaningful opportunity to avoid these costs.  Once the procurement occurs and long-term commitments are established, LSEs will become subject to the resulting allocation framework and associated collateral requirements.

Here, PJM has failed to demonstrate that its compressed implementation schedule is just and reasonable.  Although PJM cites the 2028/2029 Delivery Year resource adequacy shortfall as the basis for the proposal, PJM has not shown that delaying commencement of the procurement for a reasonable period would undermine the stated objectives of the RBP.  Indeed, PJM’s tariff contemplates a RBP-like procurement only occurring after three years of resource adequacy shortfalls, while only two have occurred to date.

49 For example, PJM's cost-allocation framework depends on states and/or RERRAs developing and communicating allocations of RBP obligations among LSEs within each service territory. July 31 RBP Proposal at 98-99.

PDF page 19

19
PJM doubtless will assert that the Statement of Principles requires the Commission to act now.  But the simple fact is that PJM ran six and one-half months off of the clock in stakeholder processes, only to reject the consensus position advanced by the majority of Electric Distribution Companies and customer representatives that emerged from that stakeholder process.50  Having run the clock, and been entirely unwilling to work with its stakeholders, it would be unjust and unreasonable to wave PJM through the regulatory process because of an impending deadline.  PJM is proposing to lock up obligations of as much as—in its own words—$20.7 billion of its stakeholders’ dollars.  If more time is needed to get it right, then more time should be afforded.

7. PJM’s Proposed “Opt-Out” Mechanism Will Allow
Unreasonable Cost Shifting Among Load Customers.
With regard to Electric Distributors, PJM proposes to reduce the Initial RBP Target based on requests from certain Electric Distributors, such as municipal utilities and cooperatives, to “opt out.”51  Thus, an Electric Distributor whose territory qualifies for an “opt out” relating to capacity procurement will not have any cost responsibility assigned to it.  Such an “opt out” is unduly discriminatory under FPA Section 205 and therefore cannot be approved.  Large load in those territories eligible for the “opt out” is no less real than large load in any other territory, and PJM provides no reasonable basis for treating such loads differently under the RBP.  The proposed ”opt out” is also inconsistent with cost- causation principles because it will result in customers in other territories subsidizing

50 See PJM Board Decisional Letter on Critical Issue Fast Path – Reliability Backstop Procurement and Connect and Manage, available at https://www.pjm.com/-/media/DotCom/about-pjm/who-we- are/public-disclosures/2026/20260727-board-decisional-letter-on-cifp-reliability-backstop-procurement- and-connect-and-manage.pdf.
51 July 31 RBP Proposal at 31-33, 44-46.

PDF page 20

20
customers in the territories receiving an “opt out.”  There is no lawful basis for requiring a data center located outside of a cooperative’s service territory to subsidize generation procured to serve a data center located within a cooperative's service territory.

8. PJM Should Strengthen Supplier Performance and Credit
Requirements.
The Commission should ensure that customers are adequately protected against supplier non-performance over the fifteen-year commitment term.  While PJM proposes numerous measures intended to reduce development risk and increase the likelihood that selected resources achieve commercial operation, those protections are directed primarily toward construction risk and the risk that a resource fails to come online in the first instance.52  For example, PJM proposes to assess an RBP UCAP MW shortfall charge when a committed resource fails to achieve commercial operation and provide committed capacity.53  PJM further proposes that a resource’s commitment may ultimately be rescinded if the resource fails to provide any committed RBP UCAP MW after three consecutive Delivery Years.54  These provisions help address development risk, but they again do not fully protect customers against the possibility that a resource satisfies its initial commercial operation obligations and subsequently underperforms during the balance of its fifteen-year commitment term.

This concern is particularly significant because the RBP would provide selected suppliers with long-term, customer-supported revenue streams extending for up to fifteen years.55  LSEs, and ultimately retail customers, will remain responsible for funding those

52 July 31 RBP Proposal at 60-61, 80-81, 116-118
53 July 31 RBP Proposal at 60-61.
54 July 31 RBP Proposal at 60-61.
55 July 31 RBP Proposal at 61-64, 76-78.

PDF page 21

21
commitments throughout the contract term.  Yet PJM has not demonstrated that the proposed performance assurance framework provides commensurate protection against the long-term risks associated with supplier underperformance after commercial operation has been achieved.  The asymmetry is particularly striking because PJM proposes substantial, and unnecessary, collateral requirements to protect suppliers against the risk of customer non-payment.

If the Commission permits PJM to proceed with the RBP, it should require PJM to strengthen protections available to customers following commercial operation.  Such protections could include enhanced performance assurance requirements, ongoing credit support, or other mechanisms designed to ensure that resources receiving long-term RBP commitments remain accountable to customers throughout the entire commitment period. Given the magnitude of the proposed procurement and the duration of the associated commitments, customers should receive protections that are commensurate with the risks and obligations they are being asked to bear.

9. PJM Must Clarify How Its Gating Criteria Apply to Demand
Response Resources.
PJM must clarify how its proposed gating criteria apply to demand response resources.  As drafted, the proposal appears to require only a contract or agreement evidencing a “plan or evidence of deployed enabling infrastructure,” not a contract or agreement demonstrating a clear and binding commitment to provide the MWs sold into the RBP.56

That ambiguity is significant.  If demand response resources may satisfy the gating criteria based merely on a “plan,” rather than a binding commitment for the underlying

56 July 31 RBP Proposal at 74-75.

PDF page 22

22
demand response capability, the proposal risks treating speculative resources as equivalent to committed resources.  Such a result would defeat the purpose of the RBP and require data centers to pay for capacity that has not genuinely been procured. The Commission should require PJM to clarify that eligible demand response resources must be supported by binding contractual commitments.  Absent such a requirement, PJM has failed to demonstrate that the proposal is just and reasonable.

CONCLUSION
FirstEnergy respectfully requests that the Commission consider the foregoing comments and protest in its consideration of PJM’s RBP Proposal, reject PJM’s filing, institute an FPA Section 206 proceeding, and establish settlement proceedings. Respectfully submitted,

/s/ Michael Kunselman
Morgan E. Parke
Michael Kunselman
Vice President, Associate General Counsel
Jonathan Namazi
Daniel T. Lloyd
Davis Wright Tremaine LLP
Senior Counsel
1301 K Street, NW
FirstEnergy Service Company
Suite 500 East
341 White Pond Drive
Washington, DC 20005
Akron, OH 44320

Tel: (202) 973-4295
Tel: (330) 620-9585
michaelkunselman@dwt.com
Tel: (330) 384-5947
jonathannamazi@dwt.com
  mparke@firstenergycorp.com
  dlloyd@firstenergycorp.com
August 21, 2026

PDF page 23

CERTIFICATE OF SERVICE
I hereby certify that I have caused the foregoing document to be served upon all the parties listed on the official service list for the above-referenced proceeding, pursuant to the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure.

Dated at Washington, D.C. this 21st day of August, 2026.
/s/ Daniel Klein
Daniel Klein
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, D.C. 20005